TUMR 232120 Repair Bldg 80 HVAC SOW.pdf
PDF 1 MB Posted
- Solicitation number
- W50S9323B0002
- Issued by
-
Department of the Army National Guard
About this file
This statement of work outlines requirements for replacing the HVAC system at Building 80 for the 156th Wing of the Puerto Rico Air National Guard. The contractor will remove the existing chiller and three air handling units, and install a new 80-ton chiller, three new air handling units, a new water pump, LED lighting, and make other repairs. The performance period is 120 calendar days. The contractor must provide all labor, equipment, and materials except for a designated storage area. The contractor must also develop safety, environmental, and waste management plans and obtain necessary permits. The work must meet standards for demolition, safety, and technical specifications. The Army National Guard is the contracting agency, with submissions and invoices requiring Army forms and approval by the contracting officer and contracting officer's representative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AF FORM 66.pdf | ||
| 2. QASP TUMR232120.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUERTO RICO AIR NATIONAL GUARD
156TH WING
MUÑIZ AIR NATIONAL GUARD BASE
200 JOSE A. SANTANA AVE, CAROLINA, PR 00979-1502
~ Accountability, Trust, Leadership ~
CUI
Statement of Work: TUMR232120
REPAIR BLDG. 80 HVAC SYSTEM
156 WG Muñiz Air National Guard Base (ANGB), Puerto Rico (PR)
Prepared by:
156th Civil Engineer Squadron (CES) / Engineering Flight (CEN)
February 10, 2023
Table of Contents
1.0 DEFINITIONS AND ACRONYMS
2.0 GENERAL
3.0 GOVERNMENT FURNISHED PROPERTY, MATERIAL EQUIPMENT and SERVICES (GFP/M/E/S)
4.0 CONTRACTOR FURNISHED PROPERTY, MATERIALS, EQUIPMENT and SERVICES (GFP/M/E)
5.0 REQUIREMENTS. The Contractor shall:
6.0 SITE VISIT ........................................................................................ Error! Bookmark not defined.15
7.0 FEDERAL ACQUISITION REGULATION (FAR)
8.0 COMPLIANCY
9.0 WORKPLACE SAFETY
10.0 APPLICABLE PUBLICATIONS
11.0 TECHNICAL EXIBITS
1.0 DEFINITIONS AND ACRONYMS
1.1 Definitions.
1.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific suppliers or services to the government. The term used in this contract refers to the prime.
1.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
1.1.3 CONTRACTING OFFICER’S REPRESENTATIVE (COR). An employee of the US
Government designated by the KO to monitor Contractor’s performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
1.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the work statement.
1.1.5 DELIVERABLE. Anything that can be physically delivered and included no manufactured things such as meeting minutes or reports.
1.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the key personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, and offer can be rejected if it does not have a firm commitment from the person that persons that are listed in the proposal.
1.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
1.1.8 QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
1.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of
Contractor’s performance.
1.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
1.1.11 SUB-CONTRACTOR. One that enters into a contract with a prime contractor. The
Government does not have privacy of contract with the sub-contractor.
1.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
1.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
1.2 Acronyms.
1.2.1 AEI – Army Enterprise Info Structure
1.2.2 AFARS – Army Federal Acquisition Regulation Supplement
1.2.3 ANG – Air National Guard
1.2.4 AR – Army Regulation
1.2.5 AUP – Acceptable Use Policy
1.2.6 BBP – Better Business Practice
1.2.7 CDM – Concept Development Meeting
1.2.8 CFR – Code of Federal Regulations
1.2.9 CM – Contract Manager
1.2.10 COMSEC – Communications Security
1.2.11 CONUS – Continental United States
1.2.12 COR – Contracting Officer Representative
1.2.13 COTS – Commercial-Off-The-Shelf
1.2.14 CUI – Controlled Unclassified Information
1.2.15 DA – Department of the Army
1.2.16 DAF – Department of the Air Force
1.2.17 DD250 – Department of Defense Form 250 (Receiving Report)
1.2.18 DD254 – Department of Defense Contract Security Requirement List
1.2.19 DFARS – Defense Federal Acquisition Regulation Supplement
1.2.20 DMDC – Defense Manpower Data Center
1.2.21 DOD – Department of Defense
1.2.22 FAR – Federal Acquisition Regulation
1.2.23 FEMA – Federal Emergency Management Agency
1.2.24 FPCON – Force Protection Condition
1.2.25 FPM – Final Planning Meeting
1.2.26 HQDA – Headquarter Department of Army
1.2.27 IA – Information Assurance
1.2.28 IAW – In Accordance With
1.2.29 IPM – Initial Planning Meeting
1.2.30 IT – Information Technology
1.2.31 JTR – Joint Travel Regulation
1.2.32 JTF – Joint Task Force
1.2.33 KO – Contracting Officer
1.2.34 MHE – Material Handling Equipment
1.2.35 MOA – Memorandum of Agreement
1.2.36 MPM – Mid-Planning Meeting
1.2.37 MSR – Monthly Status Report
1.2.38 NACI – National Agency Check Inquires
1.2.39 NGB – National Guard Bureau
1.2.40 NLT – Not Later Than
1.2.41 OCI – Organizational Conflict of Interest
1.2.42 OCONUS – Outside Continental United States
1.2.43 ODC – Other Direct Costs
1.2.44 OPSEC – Operations Security
1.2.45 PCO – Procuring Contracting Officer
1.2.46 PII – Protection of Personally Identifiable Information
1.2.47 POC – Point of Contact
1.2.48 PoP – Period of Performance
1.2.49 PRS – Performance Requirements Summary
1.2.50 SOW – Scope of Work
1.2.51 QA – Quality Assurance
1.2.52 QAP – Quality Assurance Program
1.2.53 QASP – Quality Assurance Surveillance Plan
1.2.54 QC – Quality Control
1.2.55 QCP – Quality Control Program
1.2.56 SME – Subject Matter Experts
1.2.57 TAR – Travel Authorization Request
1.2.58 TE – Technical Exhibit
1.2.59 WAWF-RA – Wide Area Workflow-Receipt and Acceptance
2.0 GENERAL
2.1 Scope. The Contractor shall provide supervision, transportation, labor, materials, equipment, fuel and any other needed materials and quality control necessary, except as specified in
Paragraph 3.0 as Government Furnished items, to provide a new HVAC unit and its components at the Ops Bldg. 80 located in Muñiz ANGB in Carolina, PR as specified in this
SOW.
2.2 Background. Building 80 served as the main building for the Contingency Response Group and part of the Operations Group for the 156th Wing. Currently, the temperature of building
80 rises the 80 F degrees and is unbearable to work. As a mitigation, tactical HVAC units were temporally placed in different spots of the building to counter measure the heat. This building needs a new HVAC system to replace the non-serviceable chiller and three air handler units. The main purpose of this project is having an adequate temperature control in the working areas. More specific details are in section 5.0.
2.3 Period of Performance (PoP). The PoP shall be 120 calendar days (4 months).
2.4 General Information
2.4.1 Quality Control (QC). The contractor shall develop and maintain an effective QC Plan
(QCP) to ensure services are performed in accordance with this SOW. The contract shall develop and implement procedure to identify, prevent and ensure no recurrence of defective services. The Contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the Contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary. A QCP shall be submitted to the COR NLT 10 days after contract award. After acceptance of the QCP, the Contractor shall obtain the
KO’s acceptance in writing of any proposed changes to its QCP.
2.4.2 Quality Assurance (QA). The Government shall evaluate the contractor’s performance under this contract in accordance with the QA Surveillance Plan (QASP). This plan is primarily focus on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s)
(defect rate(s)).
2.4.3 Recognized Holidays. The following are recognized US holidays. The contractor shall not perform services on these days.
2.4.3.1 New Year’s Day
2.4.3.2 Martin Luther King Jr.’s Birthday
2.4.3.3 President’s Day
2.4.3.4 Memorial Day
2.4.3.5 Juneteenth National Independence Day
2.4.3.6 Independence Day
2.4.3.7 Labor Day
2.4.3.8 Columbus Day
2.4.3.9 Veteran’s Day
2.4.3.10 Thanksgiving Day
2.4.3.11 Christmas Day
2.4.4 Place and Performance of Services. The Contractor shall provide services between the hours of 0730 – 1600 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings.
Performance shall be the installation mentioned in paragraph 1.1. The contractor, shall at all times, maintain an adequate work force for the uninterrupted performance of all tasks defined within this SOW when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
2.4.4.1 Unscheduled gate closures by Security Forces may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by Contractor’s personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
2.4.4.2 The Contractor’s employees shall become familiar with and obey the regulations of the installation; including, fire, traffic, safety, and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All Contractor’s employees shall carry proper identification with them at all times. The Contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance.
2.4.5 Security Requirements. The Contractor shall comply with all applicable installation/facility access and local Security Forces procedures, which may be obtained from the COR. The
Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Security Office. The
Contractor shall ensure compliance with all personal identity verification requirements as directed by DOD and/or local policies. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
The Contractor shall coordinate all on-site activity, as required, in conjunction with the
COR and the appropriate installation/facility representatives. Installation Entry Access
List (EAL) is required fifteen to thirty (15-30) calendar days ahead for processing, prior to base access approval being granted, along with DD Form 369, Police Record
Check and driver’s license copy. Additionally, Contractor’s personnel will be responsible to coordinate any escorting required for temporary workers, as determined by Security
Forces. Contractors are not compensated for failure to comply with Security Forces policies and procedures for entry.
2.4.5.1 For Contractors that do not require a Common Access Card (CAC), but require access to a DOD facility/installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures. Using the National Crime
Information Center Interstate Identification (NCIC-III) and Terrorist Screening
Database (TSDB) (Army Directive 2014 – 05/AR 190-13), and applicable installation, facility and area commander installation/facility access, and local Security Forces policies and procedures (provided by a Government representative).
2.4.5.2 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DOD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct
COMSEC monitoring and recording of telephone calls originating from, or terminating at DOD organizations. Therefore, the Contractor is advised that any time Contractor place or receive a call they are subject to COMSEC procedures. The Contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The Contractor shall abide by all Government regulations concerning the authorized use of the Government’s computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
2.4.5.3 Protection of Personally Identifiable Information (PII). The Contractor shall protect all
PII encountered in the performance of services in accordance with DFARS 224.103 and
DODD 5400.11, Department of Defense Privacy Program, and DOD 5400.11-R. If a
PII breach results from the Contractor’s violation of the aforementioned policies, the
Contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.
2.4.5.4 Anti-terrorism Level 1 (AT) Awareness Training. All Contractor’s employees requiring access to any installation/facility and controlled access areas shall complete AT Level 1 within ten (10) calendar days after contract start date and within ten (10) calendar days of new employees commencing performance. The
Contractor shall submit certificates of completion for each affected Contractor and sub-contractor employee, to the COR or KO if a COR is not assigned, within ten (10) calendar days after completion of training. AT Level 1 is available at http://jko.jten.mil/course/atl1/launch.html.
2.4.5.5 Photos. Only key Contractor’s personnel are authorized to take pictures of the construction area. Careful planning must be taken to ensure no aircraft, facilities or military personnel appear in pictures inadvertently. A list of key personnel required to take pictures will be submitted to the COR for approval NTL ten (10) days after project award.
2.4.6 Physical Security. The contractor shall safeguard all Government property provided for
Contractor use. At the close of each work period, Government Facilities, equipment and materials shall be secured.
2.4.6.1 Key Control. This SOW does not require handling of keys or key cards issued by the government.
2.4.7 Special Qualifications. The contractor shall ensure all employees possess all required licenses for operating heavy equipment, welding licenses, Material Handling Equipment
(MHE) (i.e. forklift) and any others, in the performance of this contract. The Government does not provide training to Contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services.
2.4.8 Post Award Conference/Periodic Progress Meetings. The Contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition
Regulations (FAR) subpart 42.5. The KO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor’s performance. At these meeting, the KO will apprise the contractor of how the Government views the Contractor’s performance and the Contractor shall apprise the Government of problems, if any, being experienced. The Contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
2.4.8.1 Weekly Progress Report: The Contractor shall provide the Contracting Office (KO) and
Contracting Officer Representative (COR) assigned with a Weekly Progress Report every Thursday evening unless otherwise notified.
2.4.8.2 Project Progress: Actual progress against the construction schedule to be submitted through the use of AF Form 3064 (Contract Progress Schedule) or other appropriate schedule based on the Critical Path Method (CPM).
2.4.8.3 Activities: Completed activities, upcoming activities, and equipment/material order status shall be included.
2.4.8.4 Summary of Issues: All past, current, and future issues that impact the project.
2.4.9 Contract Manager (CM). The Contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the Contractor when the CM is absent, shall be designated in writing to the
KO within three (3) calendar days after contract award. The CM or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, or KO if a COR is not assigned, to resolve issues, receive technical instructions, and ensure adequate performance of services.
The CM shall ensure that Contractor’s employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure Contractor’s employees understand that services performed outside the scope of the contract are performed wholly at the expense of the Contractor.
2.4.10 Identification of Contractor Employees. All Contractor’s personnel attending meetings, answering Government telephones and working in other situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The Contractor shall ensure that all documents or reports produced by Contractor’s personnel are suitably marked as
Contractor products or that Contractor participation is appropriately disclosed. The
Contractor’s status as a “Contractor” shall be predominantly displayed in all correspondence types (to include signature block on emails) and dealings with Government or non-
Government entities. Contractor’s personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word
“Contractor” displayed. The Contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e. badges and vehicle passes) shall be returned to the COR within the ten (10) days of an employee’s departure or contract completion.
2.4.11 Combating Trafficking in Persons. The US Government has adopted a zero-tolerance policy regarding trafficking in persons. Contractors and Contractor’s employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the US Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The
Contractor shall take appropriate action, up to and including termination against employees or sub-contractors that violate US Government policy as described at FAR 22.17.
Contractor shall complete the following online training within ten (10) calendar days after contract award – Course number is N-US189-HB; available at http://jko.jten.mil/.
2.4.12 Data Rights. The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the
Contractor without written permission from the KO. All materials supplied to the
Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy ten (10) calendar days after contract completion. This right does not abrogate any other Government rights.
2.4.13 Organizational Conflicts of Interest (OCI). The Contractor and sub-contractor personnel performing services under this contract may receive have access to or participate in the development of proprietary or source selection. In addition to substantial (e.g. cost or pricing information, budget information or analyses, specifications or work statements, etc.).
Perform evaluation services, which may create current or subsequent OCIs, as defined in
FAR Subpart 9.5. The Contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
2.4.14 Safety Plan. Contractor shall submit a Safety Plan to the COR NLT ten (10) calendar days after contract award.
2.4.15 Environmental Plan. Contractor shall submit an Environmental Plan to the COR NLT ten (10) calendar days after contract award. Include all “Oficina de Gerencia y
Permisos” (OGPe) and “Departamento de Recursos Naturales y Ambientales” (DRNA) environmental requirements for the project and any environmental permitting needed, including evidence of environmental compliance such as Categorical Exclusion or
Environmental Assessment (NEPA like process).
2.4.16 Waste Management Plan. Contractor shall submit Waste Management Plan to the
COR NLT ten (10) calendar days after contract award. The Contractor shall submit to the COR for approval prior to commencement of services, IAW UFGS 01 74 19
Construction Waste Management and UFGS 02 81 00 Transportation and Disposal of
Hazardous Waste. The project waste diversion goal is 60%. Approval of the Contractor’s
Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. This plan shall be coordinated with the installation waste management plan so there are no conflicts. This plan may be incorporated with the Environmental Plan. Disposal slips from landfill and/or recycler must be submitted to the COR to report amounts of debris landfilled or recycled on April 1st and October 1st of the past 6 months, respectively.
If the project ends before these dates, submit the report with the closure documentations.
2.4.16.1 April’s Report (October through March)
2.4.16.2 October’s Report (April through September)
2.4.17 Health and Safety Plan (HSP). The Contractor shall prepare a site-specific HSP to comply with Air Force, Occupational Safety and Health Administration (OSHA), United States
Environmental Protection Agency (USEPA), state PR-OSHA, and local health and safety regulations regarding the proposed work. The Contractor shall also submit a HSP that included worker health and safety practices for the asbestos and lead work activities. The
HSP must include valid certificates for each worker that will be included in the demolition, showing they have completed the Asbestos Hazard Emergency Response Act (AHERA), OSHA, and PR-OSHA training requirements. The Contractor shall notify the KO and COR within three (3) calendar days if a change is required to the HSP. The Contractor shall adhere to USEPA guidelines for designating the appropriate levels of protection needed at the demolition site(s) as applicable. The Contractor shall maintain and have readily available written certification that the approved HSP has been reviewed and briefed with all personnel that work at the project site prior to the employee’s start date.
2.4.18 Site Closure Report. The Contractor shall prepare and submit to the Base Environmental
Management Office and COR, for review and approval, a draft and final closure report as required for the asbestos and lead abatement permits. Typical processing time is twenty-one
(21) calendar days for the initial review/approval and, if necessary, fourteen (14) days for resubmittal review/approval.
3.0 GOVERNMENT FURNISHED PROPERTY, MATERIAL EQUIPMENT
and SERVICES (GFP/M/E/S)
3.1 The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.
3.2 Property. Government will authorize contractor to an area for material storage and temporary office.
3.3 Material. None.
3.4 Equipment. None.
3.5 Services. None.
3.6 Utilities. None.
4.0 CONTRACTOR FURNISHED PROPERTY, MATERIALS,
EQUIPMENT and SERVICES (GFP/M/E)
4.1 General. Except for those items specifically stated to be Government-Furnished in paragraph
3.0, the Contractor shall furnish everything required to perform these services as indicated in paragraph 2.1.
4.2 Bathroom. The Contractor shall provide portable bathrooms for their employees during the
PoP accompanied by its periodical maintenance.
5.0 REQUIREMENTS. The Contractor shall:
5.1 General Information:
5.1.1 Building 80: Is a one-story concrete and masonry facility used as CRG for Muniz ANGB.
5.2 Contractor shall be responsible for requesting and obtaining all required permits as per
Federal and State laws and regulations.
5.2.1 Replace Bldg. 80 HVAC Chiller with an 80 tons chiller to include: entire line of cold water in the black steel and grotto; all accessories needed for the piping of the chiller; circuit of electricity; all the electrical wiring and plumbing for the controls of the chiller.
5.2.2 Replace all three (3) air handling units to include: thermometers (pressure switch and flexible), pressure switch and flexible; electrical wiring; smoke detectors; three (3) magnetic starters; three (3) VFD.
5.2.3 Replace water pump with a 7.5 hp water pump.
5.2.4 Contractor shall apply Adsil anticorrosion treatment for the coils.
5.2.5 Start-up supervision by a certified Trane Technician.
5.2.6 Install four (4) LED 2’ x 4 light panels in the mechanical rooms.
5.2.7 Insulation the cold-water piping with urethane.
5.2.8 Install junction at TDC insulated of supply and return.
5.2.9 Install al drainages.
5.3 Internal cleaning of the supply and return ducts of the three (3) air handling units.
5.4 Contractor shall apply of mastic to all pipes inside the mechanical rooms.
5.5 Contractor shall replace existing lighting system with 2’ x 4’ LED 3500 lumens Flat Panels.
5.6 Paint mechanical rooms flooring with epoxy floor paint.
5.7 Certified balancing of the cold-water system.
5.8 Contractor shall properly dispose all removed materials and equipment.
6.0 FEDERAL ACQUISITION REGULATION (FAR).
6.1 This statement of work does not supersede any FAR stipulations that may appear in this contract.
6.2 For more up to date information visit https://www.acquisition.gov/browse/index/far.
7.0 COMPLIANCY
7.1 The Contractor is subject to all Installation Fire, Safety, Security, Civil Engineer, OPSEC, Traffic Regulations and all applicable Federal and State Regulations.
7.2 Fire Safety. The Contractor shall comply with all local fire regulations and NFPA 241 during all demolition and construction work. All fire extinguishers required shall be provided and maintained by the contractor but must be approved for use by the KO prior to use.
7.2.1 Hot-work operations. Those involving welding, soldering, brazing, or torch heating (i.e.
open flame or grinders) shall not commence before an AF Form 592 is completed and signed by the Fire Inspector. The Contractor shall contract the Fire Department’s inspection section at least one (1) workday prior to –hot work operations for assistance and completing the Form 592. There shall be no open burning of waste materials or debris during this contract.
7.3 Digging Permit. Contractor must request a digging permit to the COR and have it approved prior start any digging work.
7.4 Confined Space Entry. Contractor must request a confined space entry AF Form 1024 to the COR and have it approved prior to entering a confined space.
7.5 Contractor must be registered (current) in the System for Award Management (SAM) internet program at http://www.sam.gov.
7.6 All invoices must be submitted using Wide Area Workflow (WAWF) internet program and verify the statuses at https://wawf.eb.mil.
7.7 Contractor Manpower Reporting Application (CMRA): The Contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each
Government fiscal year (FY), which runs from October 1st through September 30th.
8.0 WORKPLACE SAFETY
8.1 The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.
8.2 The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. The KO may notify the
Contractor of hazards in Contractor’s operations/performance that endanger Government personnel or property and require appropriate abatement or mitigation action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.
8.3 Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the KO or COR, must be corrected immediately,
8.4 Solid Waste Management. Any and all debris generated by the Contractor’s operations shall be removed from the base. All waste materials and debris generated by work under this contract shall be processed, handled, transported, stored, and disposed of by the Contractor
IAW all Federal, State, and local regulations and laws. All waste streams will be quantified and reported to the Base Environmental Manager. The Contractor shall be responsible for any permit or feeds associated with the use of off-base disposal locations.
8.5 All refuse and remaining materials related to the work will be taken daily to a refuse container provided by the Contractor.
8.6 Only company cars with distinctive logos posted at the passenger and driver doors will be authorize inside Base premises.
8.7 All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.
8.8 At the end of each working day all areas will be clear from equipment, tools and materials.
8.9 Special precautions will be taken at no cost to Government to protect Base property during the project execution.
8.10 The use of Personal Protective Equipment (PPE) is mandatory at all times while working on the project.
8.11 The Contractor shall be liable for any loss, destruction or damage and deterioration to
Government property, including vegetation and landscaping, resulting from Contractor operations. Any damage to Government or personal property shall be repaired or replace to the KO’s satisfaction at the Contractor’s expense.
8.12 All work under this project shall meet applicable County, Territorial, Federal and Air
National Guard construction codes, regulations and policies.
8.13 Contractor shall coordinate with KO to verify the existing site and facility conditions. Any differing conditions shall be notified in writing to request clarification.
8.14 Equipment or fixtures Government Furnished Contractor Installed (GFCI): None anticipated.
8.15 Comply with all specifications applicable found and included by reference in the www.wbdg.org site. This will include the following UFC and UFGS:
- UFC 1-200-1 DoD Building Code
- UFGS 23 01 30 41 HVAC System Cleaning
- UFGS 23 03 00 00 20 Basic Mechanical Materials and Methods
- UFGS 23 64 10 Water Chillers, Vapor Compression Type
8.16 For additional information on drawings and specifications, and for entering the site premises contact the Base Civil Engineer (BCE) office in Building 25, Muñiz ANGB telephone (787)
253-9578.
8.17 For additional environmental information, contact the Environmental Manager Office in
Building 71, Muñiz ANGB telephone (787)253-5192.
8.18 For additional safety information contact the Safety Office in Building 22, Muñiz ANGB telephone at (787)253-5275.
8.19 For additional fire information contact the Fire Department in Building 3, Muñiz ANGB telephone at (787)253-5222.
8.20 For additional security information contact the Base Defense Operation Center (BDOC) in
Building 99, Muñiz ANGB telephone at (787)253-5204.
9.0 APPLICABLE PUBLICATIONS
9.1 Publications applicable to this SOW are listed below.
Publication Date of
Publication Mandatory/Advisory Website
Federal Acquisition Regulation Mandatory www.acquisition.gov/bro wse/index/far
Defense Federal Acquisition Regulation Mandatory http://www.acq.osd.mil/dp ap/dars/dfarspgi/current/in dex.html
AR 190-13 The Army Physical Security Feb 25 Mandatory http://www.apd.army.mil/ ProductMaps/PubForm/A
R.aspx
AR 530-1 Operations Security Sep 26, 2014 http://armypubs.army.mil/ ProductMaps/PubForm/A
R.aspx DOD 5220.22-M National Industrial Security Program
May 18, 2016 http://www.dtic.mil/whs/d irectives/corres/pub1.html
DG 415-5 General Facilities Design June 1, 2011 Advisory https://www.wbdg.org/FF
C/ARMYCOE/NATLGU
ARD/dg_415_5.pdf
UFC 4-010-01 Oct 1, 2013 Mandatory https://pdc.usace.army.mil
/library/ufc/4-010-01/ DOD Min. AT/FP Standards For Buildings
29 CFR 1926 OSHA Construction January 2014 Mandatory www.OSHA.gov
AR 385-10 Chapter 4 Safety Program http://www.ngbpdc.ngb.ar my.mil/pubs/385/ngr385_
10.pdf DAFI 32-9005 AFGM2020-01 Real Property Accountability
Dec 23, 2020 Mandatory
10.0 TECHNICAL EXIBITS
10.1 Technical Exhibit 1. Performance Requirements Summary (PRS)
10.1.1 This PRS included performance objectives the Government will use to determine
Contractor performance and will compare contractor performance to the Acceptable
Quality Level (AQL).
Performance Objective
Performance Standards
Acceptable Quality Levels (AQL)
Surveillance Method / By Whom
Demolition Demolition Service Meet the standard 100% of the time as approved on the work schedule
Weekly/COR
Safety Standards Compliance with safety requirements
Contractor shall have available all records as required on the SOW
Weekly/COR
10.2 Technical Exhibit 2. Submittal List
Description Type QTY Due Remarks Material Approval Submittals: (All materials used on project)
1. All communications cable
2. Joint Boxes 3.PVC conduits
4. Metal conduits
AF Form 3000 1 each NLT 7 days prior installing
Must be signed by:
KO
COR
Contractor (return copy)
Environmental & Waste Management Plan
AF Form 3000 1 Approved 7 days before NTP
Must be signed by:
KO
COR
Contractor (return copy)
Schedule Of Material Submittals AF Form 66 1 To be included with Bid Offer at bid Opening
CE provided and completed only by awarded Contractor.
Quality Assurance Plan AF Form 3000 1 Approved 7 days before NTP
Must be signed by:
KO
COR
Contractor (return copy)
Safety Plan AF Form 3000 1 Approved 7 days before NTP
Must be signed by:
KO
COR
Contractor (return copy)
Warranty AF Form 3000 1 Before final invoice is certified
Must be signed by:
COR
CE
10.3 Technical Exhibit 3. Design and Construction Standards and References.
10.3.1 American Society for Testing and Materials (ASTM) – Latest Edition
10.3.2 Unified Facilities Guide Specification (UFGS)
10.3.3 All Federal applicable UFC, UFGS and ANG ETL’s must be verified at www.wbdg.org.
10.4 Technical Exhibit 4. Invoice Requirements.
10.4.1 Electronic pictures of work to be invoiced (Before and After).
10.4.2 Breakdown for Payment
10.4.3 Monthly Report from : Contractor Manpower Reporting Application (CMRA)
10.4.4 Progress Report of activities
10.4.5 Contractor and COR Draft and Interim of DD Form 1354 Transfer and Acceptance of Real Property
10.5 Technical Exhibit 5. Closeout Documentation.
10.5.1 Contractor workmanship letter of warranty up to one year.
10.5.2 Recycling or landfill proof of disposition document.
10.5.3 Contractor certificates of no debts to suppliers and vendors.
10.5.4 Commissioning and acceptance of system.
10.5.5 Contractor and COR completed DD Form 1354 Transfer and Acceptance of Real
Property
10.5.6 Certification of work by a professional refrigeration provider IAW Puerto Rico’s
Law 416 (if applicable)
10.5.7 Contractor’s as-built drawing (electronically PDF and CAD file) as applicable.