TSS D1-3 Change Order Notice V.25.1~1.pdf
PDF 1 MB Posted
- Solicitation number
- 25-494DOT-FINAD-B-46358
- Issued by
- Illinois
About this file
This is a Change Order Notice from the Chief Procurement Office for General Services regarding a Technical Supportive Services contract for Districts 1-3 of the Department of Transportation (DOT). The change order extends the existing contract until May 1, 2025, from its current expiration date of January 31, 2025. The vendor will continue to provide technical assistance to Disadvantaged Business Enterprises (DBEs) in Highway Districts 1-3.
The change order is being implemented to avoid a lapse in coverage while a replacement contract is put in place. Per Illinois procurement regulations, this notice must be posted on the Bulletin/BidBuy system for 14 days as it affects the contract timeline. The reference number for this procurement is B-46358.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| CurrentPage: |
| PageCount: |
| DropDownList1: DOT - Transportation |
| ProcurementTitle: Technical Supportive Services for Districts 1-3 |
| BBREFNO.: B-46358 |
| thedetails: This is to extend the contract until May 1, 2025 and add money to avoid a lapse in coverage as the current contract will expire on January 31, 2025. This added time will allow us time to get a replacement contract in place. The Vendor shall continue to provide the Agency's DBEs technical assistance in the Agency's Highway Districts 1-3. |
| CheckBox1: 0 |
| CheckBox2: 1 |
File details come from the government source that posted it. Updated .