This document is the TSA Test and Evaluation Division Policy for TSA-Approved Independent Third-Party Acceptance Testing of Donated, Bailed, and Non-TSA-Funded Transportation Security Equipment (Version 2.0, November 3, 2026).
The policy establishes requirements for approving and overseeing third-party acceptance testing organizations when donors, sponsors, commercial entities, airport authorities, or airlines fund acceptance testing activities. TSA-approved organizations may conduct First Article Acceptance Test and Evaluation (FAT&E), Factory Acceptance Tests (FAT), Site Acceptance Tests (SAT), Operational Readiness Acceptance Tests (ORT), Network Throughput Acceptance Testing (NTT), and Operational Run-In testing for donated, bailed, and non-TSA-funded transportation security equipment. The policy does not apply to T&E Division-led testing, CBIS Integrated Site Acceptance Testing (ISAT), formal qualification testing, algorithm certification, or third-party testing used in TSA qualification decisions. Approval is valid for up to two years; organizations must submit reapproval packages at least 60 calendar days before expiration. The TSA Test and Evaluation Division Executive Director is the approval authority. Organizations must maintain project-specific independence from Original Equipment Manufacturers (OEMs), System Integrators, installers, and affiliated entities and may not perform acceptance testing on work they installed or materially supported, regardless of internal firewalls or separate business units. TSA-approved Third-Party Acceptance Testing organizations must execute testing per TSA PMO-approved plans and procedures, submit results within required timeframes (Acceptance Test Status Notification within two hours and reports within 48 hours of completion), maintain auditable records, safeguard Sensitive Security Information, and cooperate with TSA observation and performance assessments. The donor or sponsor must ensure their contracts require compliance with TSA-approved third-party organizations, project-specific independence, use of TSA-approved test articles and templates, proper SSI handling, and TSA reporting requirements, and typically fund any additional acceptance testing required to resolve independence concerns.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TSA Test and Evaluation Division Policy for the
TSA-Approved Independent Third-Party Acceptance Testing of
Donated, Bailed, and Non-TSA-Funded Transportation Security
Equipment
Version: 2.0
November 3, 2026
TSA Independent Third-Party Acceptance Testing Policy version 2.0 i
APPROVAL:
Thomas Tomaiko
Independent Test Agent
Executive Director, Test and Evaluation Division
Security Capabilities
Transportation Security Administration ii
TABLE OF CONTENTS
ACRONYMS
1. PURPOSE
2. SCOPE AND APPLICABILITY
3. AUTHORITIES AND REFERENCES
3.1 GOVERNING REFERENCES
3.2 HISTORICAL REFERENCES
4. POLICY
5. ROLES AND RESPONSIBILITIES
5.1 TRANSPORTATION SECURITY EQUIPMENT (TSE) PORTFOLIO/PROGRAM MANAGEMENT
OFFICE (PMO)
5.2 DEPLOYMENT AND SUSTAINMENT DIVISION (DSD) / CAPABILITY ACCEPTANCE
MANAGEMENT BRANCH (CAMB)
5.3 DEPLOYMENT AND SUSTAINMENT DIVISION (DSD) / REGIONAL DEPLOYMENT
COORDINATOR (RDC)
5.4 DSD INTEGRATED LOGISTICS SUPPORT (ILS) CONFIGURATION MANAGEMENT (CM)
5.5 DSD GOVERNMENT PROPERTY / ACCOUNTABLE PROPERTY OFFICER (APO)
5.6 DONOR, SPONSOR, AIRPORT AUTHORITY, AIRLINE, OR COMMERCIAL ENTITY
5.7 TSA-APPROVED THIRD-PARTY ACCEPTANCE TESTING ORGANIZATION
5.8 OEM, SYSTEM INTEGRATOR, INSTALLER, AND LOCAL TSA
5.9 TEST AND EVALUATION (T&E) DIVISION
6. THIRD-PARTY ACCEPTANCE TESTING ORGANIZATION APPROVAL
LIFECYCLE
7. TESTING EXECUTION AND REPORTING
7.1 ACCEPTANCE TEST READINESS
7.2 ACCEPTANCE TEST EXECUTION
7.3 REPORTING
7.4 RESULT STATUS LANGUAGE
8. TERMS AND CONDITIONS APPLICABILITY
APPENDIX A: TSA-APPROVED THIRD-PARTY ACCEPTANCE TESTING
ORGANIZATION APPROVAL PROCESS
iii
APPENDIX B: TSA-APPROVED THIRD-PARTY ACCEPTANCE TESTING
ORGANIZATION PERFORMANCE ASSESSMENT APPROACH
APPENDIX C: ACCEPTANCE TESTING CATEGORIES FOR DONATED, BAILED,
AND NON-TSA-FUNDED TSE
APPENDIX D: SOURCE DOCUMENT LINEAGE AND DISPOSITION CROSSWALK . 1
APPENDIX E: RETIRED AND UPDATED TERMINOLOGY
APPENDIX F: RESPONSIBLE, ACCOUNTABLE, CONSULTED, AND INFORMED
(RACI) CHART
iv
ACRONYMS
Acronym Definition
APO Accountability Property Officer
ATR Acceptance Test Request
CAMB Capability Acceptance Management Branch
CAP Capability Acceptance Process
CBIS Checked Baggage Inspection System
CIL Configuration Item List
CM Configuration Management
CMP Configuration Management Plan
DHS Department of Homeland Security
DSD Deployment and Sustainment Division
FAT Factory Acceptance Test
FAT&E First Article Acceptance Test and Evaluation
FDRS Field Data Reporting System (from Transportation Security Equipment [TSE])
FRD Functional Requirements Document
GPM Government Property Management
ILS Integrated Logistics Support
ISAT Integrated Site Acceptance Test (for Checked Baggage Inspection Systems only)
ISO/IEC
International Organization for Standardization / International Electrotechnical
Commission
NAT Retired: Network Acceptance Test (now Network Throughput Acceptance Test)
NCIL Network Configuration Item List
NDA Nondisclosure Agreement
NTT Network Throughput Acceptance Test
OEM Original Equipment Manufacturer
ORD Operational Requirements Document
ORT Operational Readiness Acceptance Test
PMO Portfolio/Program Management Office
QLR Quick Look Report (i.e., Acceptance Test Report)
RACI Responsible, Accountable, Consulted, and Informed
RDC Regional Deployment Coordinator
SAT Site Acceptance Test
SI System Integrator
SME Subject Matter Expert v
Acronym Definition
SSI Sensitive Security Information
T&E Test and Evaluation
TED Retired: Test and Evaluation Division (now T&E Division)
TPT
Third Party Tester / Third Party Acceptance Tester (now TSA-approved Third-Party
Acceptance Testing organization)
TRN Acceptance Test Readiness Notification
TSA Transportation Security Administration
TSE Transportation Security Equipment
TSN Acceptance Test Status Notification
VRTM Verification Requirements Traceability Matrix
1. PURPOSE
This policy establishes TSA Test and Evaluation (T&E) Division requirements for approving, using, overseeing, and assessing TSA-approved Third-Party Acceptance Testing organizations.
TSA-approved Third-Party Acceptance Testing organizations conduct acceptance testing of
Transportation Security Equipment (TSE) when a donor, sponsor, commercial entity, airport authority, airline, or other non-TSA entity funds the acceptance testing.
This policy consolidates and updates prior TSA T&E Division guidance on third-party acceptance testing, including guidance on donated TSE acceptance testing, Third-Party Acceptance Testing organizations approval, performance monitoring, and acceptance test reporting.
This policy supersedes the historical guidance and memoranda identified in Appendix D to the extent they address TSA-approved Third-Party Acceptance Testing of donated, bailed, and non-TSA-funded TSE.
The T&E Division will review this policy at least every two (2) years, or sooner if TSA policy, Capability
Acceptance Process (CAP) procedures, acquisition guidance, TSA Security Operations, or TSA Security
Capabilities require it.
2. SCOPE AND APPLICABILITY
This policy applies to TSA-approved Third-Party Acceptance Testing organizations that conduct acceptance testing for the following TSE activities:
1. Donated TSE under the CAP.
2. Bailed TSE when the sponsor, donor, vendor, airport, airline, or other non-TSA entity funds the
TSE acceptance testing.
3. Non-TSA-funded commercial moves or changes involving TSA-owned TSE, including commercially driven checkpoint lane changes, relocations, or integrations requiring acceptance testing.
4. Checkpoint network integration testing, including Network Throughput Acceptance Test
(NTT), when associated with donated, bailed, or non-TSA-funded TSE activities.
This policy applies to the following TSE acceptance testing activities:
• First Article Acceptance Test and Evaluation (FAT&E);
• Factory Acceptance Test (FAT);
• Site Acceptance Test (SAT);
• Operational Readiness Acceptance Test (ORT);
• NTT, when required; and
• Operational Run-In, when the Portfolio/Program Management Office (PMO), Deployment and
Sustainment Division (DSD), or approved acceptance test plan requires Operational Run-In after acceptance testing.
This policy does not apply to T&E Division-led testing to include:
• TSE acceptance testing;
• Checked Baggage Inspection System (CBIS) Integrated Site Acceptance Test (ISAT);
• CBIS ISAT with Operational Run-In;
• Formal qualification testing, algorithm certification testing, operational testing, or system evaluation reporting;
• Third-party testing used in TSA qualification decisions under the TSA Third Party Testing
Framework, except as a reference for broader third-party testing principles; or
• Long-term maintenance, sustainment, or operational monitoring beyond acceptance testing, unless a TSA-approved acceptance test plan or decision authority specifically requires additional acceptance testing.
3. AUTHORITIES AND REFERENCES
Appendix D provides a source document lineage and disposition crosswalk.
3.1 Governing References
The following references govern or support this policy:
1. TSA Test and Evaluation Policy: Establishes TSA T&E roles, responsibilities, and independent acceptance test authority.
2. TSA Test and Evaluation Guidebook: Describes TSA acceptance testing categories, the T&E
Division roles, acceptance testing activities, reporting, and relationships to broader T&E Division evaluation concepts.
3. TSA Acquisition Manual, Appendix C: Capability Acceptance Process: Describes the process for evaluating, accepting, and implementing donated capability, including business case, memorandum of understanding, offer, acceptance, and tracking activities.
4. Capability Acceptance Process Terms and Conditions: Establish terms and conditions that donors and related non-TSA sponsors must follow.
5. T&E Division Acceptance Testing Overall Result Status Guidance: Defines the T&E Division reporting categories, concerns, deficiencies, incomplete acceptance testing, and acceptance test result status language.
6. Configuration Audit Procedure for ILS, Version C, dated July 30, 2013: Defines the procedures for conducting a configuration audit on TSE on behalf of TSA to ensure the accuracy of the identifying documentation.
7. Memorandum: Organizational Alignment of Configuration Management (CM) Roles dated
October 11, 2018: Provides clarification and organizational alignment of CM roles and associated duties.
8. Configuration Management Plan (CMP), Version E, dated August 31, 2018: Defines the CM processes and procedures used throughout the life cycle of TSE developed, integrated, acquired, deployed, and maintained by TSA.
3.2 Historical References
1. T&E Division Support to Third-Party Acceptance Testing for Donated Systems, Version 1.2, September 2023: Historical base document consolidated into this policy.
2. Memorandum for Record: Acceptance Testing of Transportation Security Equipment (TSE), October 2023: Supersedes the prior 2021 acceptance testing category table and establishes applicable tester and funder categories.
3. Memorandum: Policy Direction for Third Party Acceptance Testing of Transportation Security
Equipment Under the Capability Acceptance, October 2021: Historical policy direction for third-party acceptance testing and organization certification.
4. Memorandum for Record: Third Party Acceptance Test Agent Approval Process, October 2021:
Historical approval process consolidated into Appendix A.
5. TSA Third Party Testing Framework, Version 2.0, April 2026: External reference for broader TSA third-party testing data acceptance processes. This framework does not replace this policy for acceptance testing.
4. POLICY
TSA permits the use of TSA-approved Third-Party Acceptance Testing organizations for donated, bailed, or non-TSA-funded commercial TSE acceptance testing when all the following requirements are met:
1. The TSA T&E Division has approved the Third-Party Acceptance Testing organization.
2. The TSA-approved Third-Party Acceptance Testing organization uses the most current TSA
PMO-approved acceptance test plan and procedures.
3. The TSA-approved Third-Party Acceptance Testing organization uses the applicable TSA DSD-
Integrated Logistics Support-Configuration Manager-approved configuration baseline, including the Configuration Item List (CIL), or other PMO/DSD-approved configuration artifacts when performing the acceptance test CIL validation.
4. The TSA-approved Third-Party Acceptance Testing organization submits the acceptance test results and reports to TSA as required.
5. The TSA-approved Third-Party Acceptance Testing organization provides the T&E Division with the opportunity to review the Acceptance Test Status Notification (TSN), Acceptance Test Report
(e.g., Quick Look Report), supporting data, or other required artifacts.
6. The PMO, DSD Capability Acceptance Management Branch (CAMB), DSD Regional
Deployment Coordinator (RDC), or other designated decision authorities use the results to inform acceptance, go-live, deployment, or risk decisions.
The TSA-approved Third-Party Acceptance Testing organizations and the T&E Division do not make final decisions on TSA acceptance, deployment, go-live, or operational use. The PMO, DSD CAMB, DSD RDC, or other TSA decision authority make those decisions.
TSA approval of a Third-Party Acceptance Testing organization applies at the organization level only. It does not automatically make the organization eligible to perform acceptance testing on every project. For each project, the organization must be independent of the Original Equipment Manufacturers (OEMs), OEM-affiliated organizations, System Integrators, installers, and System Integrator affiliated organizations that performed or materially supported work subject to acceptance testing. The OEM, System Integrator, installer, or any affiliated entity may provide installation, readiness, technical, corrective action, and site support services, but may not perform independent third-party acceptance testing for the same TSE project.
Independence is a required condition for project eligibility. It separates the organization that installs, integrates, commissions, repairs, or corrects the TSE from the organization that determines whether that work meets the acceptance requirements before TSA makes its final TSE acceptance decision. An organization may not perform acceptance testing on work that the organization, its affiliate, or its personnel installed, integrated, commissioned, repaired, corrected, or otherwise materially supported. This prohibition applies even if the organization uses separate personnel, business units, internal firewalls, or quality control processes. This requirement prevents actual, potential, or apparent organizational conflicts of interest, including a financial interest in whether the work is found acceptable.
If a project-specific relationship raises an actual, potential, or apparent independence concern, CAMB, DSD, and PMO will determine the appropriate response.
Possible responses may include additional acceptance testing, retesting by a different third-party acceptance testing organization, corrective action, project-specific disqualification, suspension, or removal. Unless TSA determines otherwise in writing, the donor, sponsor, airport authority, or commercial entity is responsible for funding any additional acceptance testing required to resolve independence concerns.
5. ROLES AND RESPONSIBILITIES
See the Responsible, Accountable, Consulted, and Informed (RACI) Chart in Appendix F which lays out:
• R = Responsible: Performs or coordinates the work
• A = Accountable: Final authority or decision owner
• C = Consulted: Provides input/review
• I = Informed: Kept aware of status/results
Note: Final acceptance of a TSE into TSA inventory is executed by the DSD Government Property /
Accountable Property Officer (APO) upon receipt of required property documentation (e.g., signed TSA
Form 251 or DD-1149). Final “go-live” and deployment decisions depend on the specific project scenario. Therefore, the RACI chart identifies when the PMO, DSD RDC, or DSD CAMB acts as the accountable TSA decision authority.
5.1 Transportation Security Equipment (TSE) Portfolio/Program Management Office (PMO)
Responsibilities:
• Owns the TSE requirements baseline, including applicable Functional Requirements Document
(FRD), Operational Requirements Document (ORD), Verification Requirements Traceability
Matrix (VRTM), and program-specific requirements.
• Coordinates with the T&E Division for review and concurrence on acceptance test plans and procedures.
• Coordinates with DSD ILS CM and the OEM to maintain approved TSE configuration baselines.
• Reviews and submits the official Acceptance Test Readiness Notification (TRN) to the TSA-approved Third-Party Acceptance Testing organization (copying the Acceptance Test Request
[ATR] mailbox ATR@tsa.dhs.gov and other required stakeholders) when acting as the accountable TSA representative for program requirements, configuration, or acceptance decisions. While the OEM, System Integrator, donor, or airport may prepare the TRN information, the PMO must make the official submission to formally authorize the acceptance testing, confirm the applicable TSA-approved plan/procedures, and verify the configuration baseline.
Decision Authority:
• Approves OEM-developed acceptance test plans and procedures as program or contract deliverables mapped to the TSA-approved VRTM.
• Makes risk acceptance decisions for deviations from approved requirements, procedures, or configuration baselines.
• Decides whether to use statistical sampling approaches for acceptance testing, if applicable.
mailto:ATR@tsa.dhs.gov
• Uses TSA-approved Third-Party Acceptance Testing organization results, T&E Division review comments, and stakeholder input to inform acceptance or deployment decisions.
5.2 Deployment and Sustainment Division (DSD) / Capability Acceptance Management Branch
(CAMB)
Responsibilities:
• Manages the CAP for donated TSE.
• Coordinates donor compliance with current CAP Terms and Conditions.
• Coordinates with the donor, PMO, T&E Division, DSD stakeholders, and TSA-approved Third-
Party Acceptance Testing organization.
• Reviews and submits the official TRN to the TSA-approved Third-Party Acceptance Testing organization (copying the ATR@tsa.dhs.gov mailbox and other required stakeholders) when acting as the accountable TSA representative for CAP donation acceptance coordination.
While the OEM, System Integrator, donor, or airport may prepare the TRN information, CAMB must make the official submission to formally authorize the acceptance testing, confirm the applicable TSA-approved plan/procedures, and verify the configuration baseline.
• Receives, logs, and tracks acceptance testing results for donation activities.
• Provides operational performance feedback to T&E Division for Third-Party Acceptance Testing organization performance assessments, including performance concerns or recommended corrective action.
• Does not approve TSA-approved Third-Party Acceptance Testing organizations.
• Uses the TSA-approved Third-Party Acceptance Testing organization provided independent acceptance testing results, T&E Division review and comments of these results when requested and provided, and stakeholder input to make final donation acceptance or go-live decisions.
5.3 Deployment and Sustainment Division (DSD) / Regional Deployment Coordinator (RDC)
Responsibilities:
• Coordinates regional deployment activities and local stakeholder readiness.
• Reviews and submits the official TRN under the approved TSA process to the TSA-approved
Third-Party Acceptance Testing organization (copying the ATR@tsa.dhs.gov mailbox and other required stakeholders) when acting as the accountable TSA representative for deployment or commercial-move activities. While the OEM, System Integrator, donor, or airport may prepare the TRN information, the RDC must make the official submission to formally authorize the acceptance testing, confirm the applicable TSA-approved plan/procedures, and verify the configuration baseline.
• Supports project specific TSA decision authority’s go-live and deployment decisions for assigned projects, as applicable.
• Coordinates with the T&E Division, CAMB, PMO, local TSA, airport authorities, OEMs, and
TSA-approved Third-Party Acceptance Testing organizations.
• Provides performance feedback to the T&E Division on Third-Party Acceptance Testing organization execution, communication, and reporting.
5.4 DSD Integrated Logistics Support (ILS) Configuration Management (CM)
Responsibilities:
• Maintains the approved TSE configuration baseline on behalf of the Portfolio/PMO.
• Maintains or supports the CIL and other configuration control artifacts.
• Coordinates configuration changes through the appropriate Configuration Control Board.
• Coordinates with the OEM, Portfolio/PMO, T&E Division, and other stakeholders to ensure acceptance testing uses the correct configuration baseline.
• Provides configuration verification expectation guidance for FAT&E, FAT, SAT, ORT, and NTT, as applicable per Configuration Audit Procedure for ILS, Version C, dated July 30, 2013;
Memorandum: Organizational Alignment of Configuration Management (CM) Roles, dated
October 11, 2018; and Configuration Management Plan (CMP), Version E, dated August 31, 2018.
5.5 DSD Government Property / Accountable Property Officer (APO)
Responsibilities:
• Performs TSA property accountability actions for TSE accepted into TSA inventory, as applicable.
• Enters TSE into Government Property Management (GPM) and TSA’s property management system of record, Sunflower Assets (Sunflower), after receipt of required property documentation.
• Uses signed TSA Form 251, Vendor Shipping and Receiving Report, or Department of Defense
Requisition and Invoice/Shipping Document DD-1149, as applicable, to support entry of TSE into
TSA property records.
• Coordinates with CAMB, RDCs, PMO/Portfolio, DSD ILS CM, donors, OEMs, System
Integrators, and local TSA, as needed, to obtain information required for accurate asset accountability.
• Supports reconciliation of property documentation, configuration information, serial numbers, asset identifiers, location data, and other required property record information.
• Coordinates with appropriate TSA financial management and property stakeholders, as applicable, when donated, bailed, or non-TSA-funded TSE activities affect asset accountability, capitalization, or financial reporting.
• Determines whether required property documentation is sufficient to enter TSE into GPM and
Sunflower under applicable TSA property management procedures.
• Does not make acceptance testing, go-live, deployment, operational use, or third-party acceptance testing organization approval decisions.
5.6 Donor, Sponsor, Airport Authority, Airline, or Commercial Entity
Responsibilities:
• Funds the services of a TSA-approved Third-Party Acceptance Testing organization when TSA does not fund the acceptance testing.
• Selects and contracts with a TSA-approved Third-Party Acceptance Testing organization. Status as a TSA-approved Third-Party Acceptance Testing organization applies at the organization level only and does not guarantee eligibility for every project.
• Must ensure the selected organization is independent of the OEM, OEM-affiliated organizations, system integrators, installers, and system integrator- or installer-affiliated organizations. The donor must not select any organization to perform acceptance testing on work that the organization, its affiliate, or its personnel installed, integrated, commissioned, repaired, corrected, or otherwise materially supported, even if the organization uses separate personnel, business units, or internal firewalls.
• TSA may require additional acceptance testing, targeted acceptance testing, or retesting by a different TSA-approved Third-Party Acceptance Testing organization before donation acceptance, go-live, deployment, operational use, or risk acceptance if:
o Acceptance testing was incomplete;
o The TSA-approved Third-Party Acceptance Testing organization did not perform acceptance testing in accordance with TSA PMO-approved acceptance test plans and procedures;
o Acceptance testing identified unresolved security effectiveness or safety deficiencies; or o Acceptance testing involved an actual, potential, or apparent conflict of interest affecting independence.
• Ensures the TSA-approved Third-Party Acceptance Testing organization follows OEM-developed
TSA PMO-approved plans and procedures, T&E Division provided templates, and CAMB’s terms and conditions.
• Coordinates project schedule, site access, local support, and acceptance test article logistics.
• Complies with current CAP Terms and Conditions, when applicable.
• Provides feedback to CAMB, DSD, PMO, and the T&E Division on Third-Party Acceptance
Testing organization performance.
• Funds additional acceptance testing, targeted acceptance testing, retesting by a different TSA-approved Third-Party Acceptance Testing organization, or other acceptance testing that TSA requires to resolve actual, potential, or apparent independence concerns, unless TSA determines otherwise in writing.
5.7 TSA-Approved Third-Party Acceptance Testing Organization
Responsibilities:
• Executes independent acceptance testing in accordance with TSA PMO-approved plans and procedures.
• Maintains project-specific independence from the OEM, system integrator, installer, and any affiliated entities. It must not perform acceptance testing on work that the organization, its affiliate, or its personnel installed, integrated, commissioned, repaired, corrected, or otherwise materially supported, regardless of separate personnel, business units, or internal firewalls.
• Accurately and completely follows TSA PMO-approved acceptance test plans and procedures.
• Accurately and completely fills out T&E Division-provided Acceptance Test Report templates, data sheets, reporting formats, and other required test artifacts.
• Verifies the TSE configuration against the approved CIL or other configuration baseline as the
TSA-approved acceptance test plan and procedures require.
• Provides required daily updates, TSNs, Acceptance Test Reports (i.e., QLRs), data sheets, and supporting evidence.
• Maintains SSI, proprietary, and acceptance test data safeguards.
• Maintains auditable records.
• Cooperates with TSA review, observation, and performance assessment.
• Reports issues, deficiencies, incomplete acceptance testing, deviations, and safety/security concerns promptly.
• Complies with current TSA-approved Third-Party Acceptance Testing policy and procedures.
• Does not make final TSA acceptance, deployment, go-live, operational use, or risk acceptance decisions.
5.8 OEM, System Integrator, Installer, and Local TSA
OEMs, system integrators, installers, and local TSA may support third-party acceptance testing by:
• Providing installation and readiness support;
• Providing TSE operation assistance;
• Providing technical information that TSA requests;
• Supporting corrective actions;
• Providing access to TSE logs, configuration information, and TSE Field Data Report System
(FDRS) or other reporting or log data; and
• Supporting site coordination.
The OEM, System Integrator, installer, or any affiliated organization may provide installation, readiness, technical, corrective action, and site support services, but must not perform independent third-party acceptance testing for the same TSE project.
5.9 Test and Evaluation (T&E) Division
Responsibilities:
• Establishes and maintains approval criteria for organizations seeking TSA-approved Third-Party
Acceptance Testing status and manages the Third-Party Acceptance Testing organization application process.
• Provides recommendations to the T&E Division Executive Director for Third-Party Acceptance
Testing organization approval, reapproval, corrective action, suspension, or removal.
• Reviews and concurs with OEM-developed acceptance test plans and procedures.
• Reviews TSNs, Acceptance Test Reports (e.g., QLRs), data sheets, or supporting artifacts developed by TSA-approved Third-Party Acceptance Testing organizations.
• Maintains acceptance test report templates and acceptance test articles.
• Provides TSA PMO-approved acceptance test plans and procedures, templates, and acceptance test articles to TSA-approved Third-Party Acceptance Testing organizations upon request through the acceptance test planning process (e.g., ATR@tsa.dhs.gov mailbox).
• Performs periodic assessments of TSA-approved Third-Party Acceptance Testing organizations in coordination with DSD/CAMB and other TSA stakeholders.
• Does not provide day-to-day contract administration for donor, airport, or commercial contracts with TSA-approved Third-Party Acceptance Testing organizations.
• Does not make final go-live, acceptance, deployment, or operational use decisions.
• Reviews conflict-of-interest disclosures and recommends appropriate action to the T&E Division
Executive Director or other designated TSA decision authority, as applicable.
6. THIRD-PARTY ACCEPTANCE TESTING ORGANIZATION APPROVAL LIFECYCLE
The T&E Division manages approval of TSA-approved Third-Party Acceptance Testing organizations through a structured lifecycle process with the following target timelines:
1. Application: The applicant submits a complete application package to the T&E Division via the
ATR mailbox (ATR@tsa.dhs.gov). The T&E Division acknowledges receipt and performs an initial completeness check within 5 business days.
2. Technical Review: The T&E Division conducts a technical evaluation of the complete application package (typically within 10 business days of confirming a complete submission, or upon receipt of any requested supplemental information).
3. Approval Decision: The T&E Division prepares a technical recommendation, and the T&E
Division Executive Director issues a written approval, conditional approval, or denial decision
(typically within 5 business days of the technical recommendation, for a total target review time of 20 business days from receipt of a complete package). Approved status is valid for up to two
(2) years.
4. Event-Specific Coordination: For each project, the accountable TSA representative submits the official TRN (at least five [5] business days prior to standard TSE acceptance testing or 15 business days prior to FAT&E and NTT), and the Third-Party Acceptance Testing organization provides at least 72 hours advance notice prior to onsite testing.
5. Performance Monitoring: The T&E Division continuously monitors organizational performance across acceptance test events and conducts periodic performance assessments (see Appendix B).
6. Reapproval: Approval is valid for up to two (2) years. Organizations seeking reapproval must submit a renewal package at least 60 calendar days prior to the expiration of their current approval term.
7. Corrective Action, Suspension, or Removal: Initiated immediately when warranted by performance deficiencies, non-compliance, or compromises to project-specific independence.
When requested, organizations must submit a corrective action plan within 10 business days unless TSA specifies a different timeframe.
The T&E Division Executive Director is the approval authority for initial approval, reapproval, suspension, or removal from the TSA-approved list. The T&E Division prepares technical recommendations for the T&E Division Executive Director. See Appendix A for the detailed approval process and Appendix B for performance assessments.
7. TESTING EXECUTION AND REPORTING
7.1 Acceptance Test Readiness
Before a TSA-approved Third-Party Acceptance Testing organization conducts acceptance testing, the following readiness requirements must be met:
• The accountable TSA representative (i.e., the PMO, DSD RDC, or DSD/CAMB, depending on the project type) must review and submit the official TRN to the TSA-approved Third-Party
Acceptance Testing organization, copying the ATR@tsa.dhs.gov mailbox and required stakeholders. While the OEM, System Integrator, donor, or airport may prepare the TRN information, the accountable TSA representative must make the official submission.
• By submitting the TRN, the accountable TSA office confirms and must include:
o The specific TSA PMO-approved plan and procedures to use;
o The applicable software version, algorithm version, and configurable settings;
o The applicable CIL or other TSA PMO-approved configuration baseline (e.g., software, detection algorithm, and applicable configurable settings impacting security effectiveness); and o Any TSA PMO-approved deviations.
• The OEM must complete its own post-installation readiness review or commissioning before requesting independent Third-Party Acceptance Testing. TSA designed the independent acceptance testing to confirm readiness and shall not serve as the OEM’s initial troubleshooting event.
• The TSA-approved Third-Party Acceptance Testing organization has attained the required acceptance test articles.
• The TSA-approved Third-Party Acceptance Testing organization must work with CAMB, Local
TSA, OEM, and other stakeholders and attain the required site access, escorts, badging, storage, and safety support.
• The TSA-approved Third-Party Acceptance Testing organization has provided the required 72-hour advance notice to TSA.
7.2 Acceptance Test Execution
The TSA-approved Third-Party Acceptance Testing organization must:
• Execute acceptance testing in accordance with the TSA PMO-approved plan and procedures.
• Use the required TSA-approved acceptance test articles, tools, procedures, data sheets, and templates.
• Document configuration, serial numbers, software, firmware, detection algorithm, and other required TSE information per TSA PMO-approved CIL.
• Document deviations, limitations, deficiencies, and concerns.
• Stop or pause acceptance testing when the TSA PMO-approved plan requires (e.g., security effectiveness limitation) or when safety/security concerns arise.
• Notify CAMB, PMO, DSD, T&E Division, or other designated stakeholders of issues according to the approved process.
7.3 Reporting
Unless TSA directs otherwise, the TSA-approved Third-Party Acceptance Testing organization must provide the following:
• Acceptance testing schedule;
• Daily updates for multi-day events;
• TSN within two (2) hours after completion of the acceptance test;
• Acceptance Test Report (e.g., Quick Look Report) within 48 hours after completion of the acceptance test, unless TSA agreed to another timeframe (e.g., to accommodate weekends or holidays);
• Acceptance Test data sheets;
• Aborted acceptance test report, when applicable;
• Corrective action documentation, when applicable; and
• Supporting evidence.
Unless otherwise directed, reports should identify:
• Acceptance test event;
• Site;
• TSE model and serial number;
• Configuration baseline;
• Acceptance test plan and procedures performed;
• Overall acceptance test status;
• Safety findings;
• Security effectiveness findings;
• Configuration findings;
• Efficiency and functional findings;
• Deficiencies, discrepancies, concerns, and notes;
• Any deviations from the TSA PMO-approved plan and procedures;
• Supporting evidence - T&E Division highly encourages photographs. TSA may require photographs when necessary or useful to properly verify deficiencies, configuration conditions, inspection results, safety concerns, or other findings; and
• Recommended follow-up actions.
7.4 Result Status Language
Acceptance test results must align with the T&E Division Acceptance Testing Overall Result Status
Guidance.
The TSA-approved Third-Party Acceptance Testing organization’s results support, but do not replace, the
TSA decision authority’s acceptance or go-live decision.
The T&E Division may review the TSA-approved Third-Party Acceptance Testing organization’s reports and provide comments such as:
• TSE does not present safety or security effectiveness concerns;
• TSE does not present safety or security effectiveness concerns, with deficiencies identified;
• TSE presents safety or security effectiveness concerns; or
• Incomplete acceptance test.
The TSA decision authority (e.g., PMO or DSD) determines the final acceptance, deployment, go-live, or operational use decision.
8. TERMS AND CONDITIONS APPLICABILITY
DSD/CAMB owns and maintains the current Capability Acceptance Process Terms and Conditions for each donation project.
Donors and non-TSA sponsors must comply with current Capability Acceptance Process Terms and
Conditions.
The donor or sponsor must ensure that its contracts or agreements with TSA-approved Third-Party
Acceptance Testing organizations, at a minimum, require compliance with the following Terms and
Conditions:
• Use of TSA-approved Third-Party Acceptance Testing organizations;
• Project-specific independence from the OEM, System Integrator, installer, and any affiliated entities, including the prohibition against testing work that the organization, its affiliate, or its personnel installed, integrated, commissioned, repaired, corrected, or materially supported (even with separate business units or internal firewalls);
• Compliance with TSA PMO-approved acceptance test plans and procedures;
• Use of TSA-approved acceptance test articles and templates;
• Responsibility for acceptance test article shipping, care, custody, and damage requirements;
• TSA inspection or observation rights;
• TSA reporting requirements, which includes reporting to DSD CAMB, PMO, DSD RDC, and
T&E Division as directed;
• Proper SSI handling and safeguarding requirements;
• Data protection, record retention, storage, and transmission requirements;
• Corrective action requirements; and
• Any additional terms that DSD CAMB, DSD RDC, PMO, or T&E Division require.
DSD CAMB maintains the applicable Terms and Conditions for each donation project.
A-1
APPENDIX A: TSA-APPROVED THIRD-PARTY ACCEPTANCE TESTING ORGANIZATION
APPROVAL PROCESS
A.1 Purpose
This appendix describes the process for approving TSA-approved Third-Party Acceptance Testing organizations.
A.2 Application Submission
A prospective TSA-approved Third-Party Acceptance Testing organization must submit an application package to the T&E Division.
The package must include evidence that the organization can meet the approval criteria in this appendix.
A.3 Review and Decision
1. Completeness Review (Target: Five [5] Business Days): The T&E Division reviews the application package for administrative completeness within five (5) business days of receipt at
ATR@tsa.dhs.gov.
2. Requests for Additional Information: The T&E Division may request clarifying or supplemental information from the applicant. If the T&E Division requests additional information, the technical review timeline pauses until the applicant submits a complete response.
If the applicant does not provide the requested information within five (5) business days, the T&E
Division may close the application without approval.
3. Technical Evaluation and Recommendation (Target: 10 Business Days): Upon confirming a complete application package, the T&E Division evaluates the applicant against the criteria in
Section A.4 and prepares a formal recommendation for approval, conditional approval, or denial within 10 business days.
4. Final Decision and Notification (Target: Five [5] Business Days): The T&E Division
Executive Director makes the final decision, and the T&E Division notifies the applicant in writing within five (5) business days of the recommendation (resulting in an overall target timeframe of 20 business days from receipt of a complete application package, unless TSA requires additional review time).
A.4 Approval Criteria Checklist
Requirement Evidence Required Adjudication Comment /
Recommendation
Independence from OEM, System Integrator, installer, and affiliated entities (including not acceptance testing work installed, integrated, commissioned, repaired, corrected, or materially supported by the organization or its affiliates, regardless of internal firewalls) to mitigate any conflict-of-interest limitations.
Conflict-of-interest disclosure or statement of independence
[ ] Meets
[ ] Does not meet
Maintains independence of judgment and integrity Conflict-of-interest disclosure
[ ] Meets
Safeguards SSI under 49 C.F.R. Part 1520 and TSA policy
SSI procedures, training records
[ ] Meets
A-2
Comment /
Recommendation
Flows SSI requirements to subcontractors, joint ventures, and teaming partners.
Contract clauses or written process
[ ] Meets
Maintains positive suitability determinations for personnel requiring access
Suitability documentation
[ ] Meets
Maintains ISO 9001:2015 or ISO/IEC 17025 quality management system, or TSA-accepted equivalent
Certification or equivalent evidence
[ ] Meets
Demonstrates relevant experience verifying configuration baselines, hardware/software revisions, and configurable settings
Procedures and sample records
[ ] Meets
Demonstrates relevant acceptance testing experience Past performance and resumes
[ ] Meets
Demonstrates qualified key personnel Acceptance Test lead, deputy, SME resumes
[ ] Meets
Maintains data authentication process Data review procedures
[ ] Meets
Maintains secure data storage and access controls IT/security process
[ ] Meets
Executes NDAs with TSA where required NDA records
[ ] Meets
Demonstrates experience working with OEM and TSA to tailor TSA core acceptance test plans to site-specific acceptance test events or provides an overview of proposed tailoring process.
Sample acceptance test plan or process evidence.
[ ] Meets
Demonstrates ability to work with OEM and submit event-specific acceptance test plan at least seven (7) business days before acceptance test
Process evidence
[ ] Meets
Demonstrates ability to execute acceptance testing according to TSA PMO-approved plan Process evidence
[ ] Meets
Demonstrates ability to work with Donor to provide at least 72 hours advance notice and allow TSA observation of acceptance test
Process evidence
[ ] Meets
Inspects acceptance test articles before acceptance testing
Acceptance test article inspection process
[ ] Meets
A-3
Comment /
Recommendation
Allows TSA inspection of acceptance testing process and approval criteria
Written acknowledgment
[ ] Meets
A.5 Approval Duration and Renewal
Initial approval and reapproval are valid for up to two (2) years unless suspended, revoked, or shortened by TSA. To prevent a lapse in approved status, a TSA-approved Third-Party Acceptance Testing organization must submit its reapproval package to ATR@tsa.dhs.gov at least 60 calendar days before its current two-year approval period expires. Approval remains contingent on satisfactory performance and continued compliance with this policy.
B-1
APPENDIX B: TSA-APPROVED THIRD-PARTY ACCEPTANCE TESTING ORGANIZATION
PERFORMANCE ASSESSMENT APPROACH
B.1 Purpose
This appendix establishes how TSA monitors and assesses TSA-approved Third-Party Acceptance Testing organization performance.
B.2 Performance Categories
TSA assesses performance in five (5) categories:
1. Technical Quality;
2. Schedule Timeliness;
3. Reporting Quality;
4. Compliance;
5. Responsiveness.
B.3 Data Sources
Assessments may use:
• TSNs;
• QLRs;
• Acceptance Test Reports;
• Data sheets;
• TSA PMO-approved Acceptance Test Plans and procedures;
• Report revisions and rework;
• Procedural compliance observations;
• Timeliness records;
• CAP documentation;
• Stakeholder feedback;
• T&E Division technical reviews;
• Corrective action records; and
• Prior performance assessments.
TSA should not use one data source as the sole basis for approval, reapproval, suspension, or removal.
B.4 Rating Scale
Rating Definition
5 Exceptional Exceeds expectations and demonstrates proactive improvement
4 Exceeds Expectations Meets all expectations and exceeds some
3 Meets Expectations Meets most expectations with only minor issues
2 Needs Improvement Several expectations not met or moderate issues observed
1 Unsatisfactory Major expectations not met or significant issues observed
B.5 Reapproval Thresholds
Recommendation:
• Average rating of 3.0 or higher across all categories supports reapproval.
B-2
• More than one rating of 1 or 2, or an average below 3.0, should trigger corrective action, at-risk status, suspension, or non-renewal consideration.
• Any serious safety, security, integrity, data handling, or independence issues may trigger immediate review regardless of score.
B.6 Corrective Action
The T&E Division may recommend that the organization submit a corrective action plan when performance issues arise.
A corrective action plan should include:
• Issue description;
• Root cause;
• Corrective action;
• Responsible person;
• Due date;
• Evidence of completion; and
• Prevention measures.
B.7 Suspension or Removal
The T&E Division Executive Director may suspend or remove approval when the organization:
• Fails to follow TSA PMO-approved acceptance test plan and procedures;
• Fails to safeguard SSI or acceptance test data;
• Loses independence;
• Produces unreliable or incomplete acceptance test results;
• Misses reporting deadlines repeatedly;
• Fails to correct identified issues; or
• No longer meets approval criteria.
B.8 Appeal or Reconsideration
Recommendation: A suspended or removed organization may submit a written reconsideration request within 30 calendar days of notification. The request should include corrective actions and supporting evidence. The T&E Division Executive Director makes the final reconsideration decision.
C-1
APPENDIX C: ACCEPTANCE TESTING CATEGORIES FOR DONATED, BAILED, AND
NON-TSA-FUNDED TSE
The October 2023 memorandum supersedes the October 2021 acceptance testing category table. This appendix clarifies the applicable acceptance tester and responsible funder for donated, bailed, and non-
TSA-funded TSE acceptance testing. The following table is the controlling baseline for this policy.
Category Definition Applicable acceptance tester
Responsible funder
Notes
Donated TSE
TSE donated to TSA under CAP or another approved donation pathway
TSA-approved
Third-Party
Acceptance
Testing organization unless TSA directs otherwise
Donor
Donor-funded acceptance testing must use a TSA-approved Third-
Party Acceptance
Testing organization.
Bailed TSE
TSE bailed to TSA under an approved bailment or temporary transfer arrangement where a non-TSA sponsor funds the TSE, use, or acceptance testing.
TSA-approved
Third-Party
Acceptance
Testing organization unless TSA directs otherwise
Vendor, donor, bailment sponsor, or TSA if TSA requirements drive the acceptance testing
The applicable agreement or decision record must document the funding source and acceptance tester.
Non-TSA-funded commercial activity involving TSA-owned TSE
Commercially driven lane changes, moves, upgrades, relocations, or integrations affecting
TSA-owned TSE
TSA-approved
Third-Party
Acceptance
Testing organization unless TSA directs otherwise
Commercial entity or non-TSA sponsor
Applies when non-
TSA activity causes the need for acceptance testing.
TSA activity involving TSA-owned TSE
TSA-funded acquisition, deployment, upgrade, relocation, or other TSA-directed activity
T&E Division TSA
Outside the main scope of this policy except for lineage and comparison.
D-1
APPENDIX D: SOURCE DOCUMENT LINEAGE AND DISPOSITION CROSSWALK
Source document Date Disposition
Superseded / controlling relationship
Notes
T&E Division Support to
Third-Party Acceptance
Testing for Donated
Systems, Version 1.2
September
Folded into body and appendices
Superseded by this consolidated policy once signed
Base document updated for terminology and scope.
Memorandum for
Record: Acceptance
Testing of TSE
October
Folded into body and Appendix D
Supersedes 2021 acceptance testing category table
Controlling category/funder/tester baseline.
Policy Direction for
Acceptance Testing of
TSE
October
Historical lineage and partial content folded into body
Superseded by
October 2023 table
Retained for origin of category framework.
Third Party Acceptance
Test Agent Approval
Process
October
Folded into
Appendix A
Updated by this consolidated policy Terminology updated.
Policy Direction for
Third Party Acceptance
Testing of TSE Under the
Capability Acceptance
October
Folded into body, Appendix A, Appendix C
Updated by this consolidated policy
Approval criteria and process requirements retained.
TSA Acquisition Manual
Appendix C: Capability
Acceptance Process
August
External reference
Remains governing
CAP process Do not reproduce.
TSA Test and Evaluation
Guidebook, Revision 7 External reference
Remains governing
T&E Guidebook Do not reproduce.
TSA Third Party Testing
Framework, Version 2.0 April 2026
External reference / lineage
Separate framework for third-party test data in qualification
Not the governing acceptance testing policy.
Third-Party Acceptance
Testing Organization
Performance Assessment
Approach
Folded into
Appendix B
Updated by this policy once signed
Used for lifecycle monitoring.
T&E Division
Acceptance Testing
Overall Result Status
Guidance
External reference
Governs result/status reporting
Do not reproduce in full.
E-1
APPENDIX E: RETIRED AND UPDATED TERMINOLOGY
Retired / legacy term Replacement Notes
Third Party
[Acceptance] Tester
(TPT)
TSA-approved Third-Party
Acceptance Testing organization Use updated terms except in historical titles.
Third Party
[Acceptance] Tester
(TPT) Agent
TSA-approved Third-Party
Acceptance Testing organization Use updated term.
Acceptance Testing
(AT) Third Party Tester
TSA-approved Third-Party
Acceptance Testing organization Use updated term.
Third Party
[Acceptance] Testing for Donated Systems
Third-Party Acceptance Testing of
Donated TSE Clarifies scope and terminology.
Acceptance Testing
(AT)
acceptance testing Do not use “AT” as acronym in new policy.
Network Acceptance
Testing (NAT)
Network Throughput Acceptance
Testing (NTT), if applicable
Retire unless a specific legacy document requires historical reference.
ISAT for donated TSE Out of scope
ISAT applies to the T&E Division performed CBIS integrated site acceptance testing (ISAT), not donated TSE third-party acceptance testing.
APM/T&E Division
(TED)
T&E Division
Update to current organizational nomenclature.
Capability Acceptance
Management Division
(CAMD)
Deployment and Sustainment
Division (DSD) Capability
Acceptance Management Branch
(CAMB)
Use Capability Acceptance Management
Branch unless legacy quote requires otherwise.
TSA Independent Third-Party Acceptance Testing Policy version 2.0 F-1
APPENDIX F: RESPONSIBLE, ACCOUNTABLE, CONSULTED, AND INFORMED (RACI) CHART
RACI key:
• R = Responsible: Performs or coordinates the work
• A = Accountable: Final authority or decision owner
• C = Consulted: Provides input/review
• I = Informed: Kept aware of status/results
RACI Chart: TSA-Approved Third-Party Acceptance Testing of Donated, Bailed, and Non-TSA-Funded TSE
Activity / Decision Area
T&E
Division
Executive
Director
T&E
Division
PMO /
Portfolio
DSD /
CAMB
DSD /
RDC
DSD ILS
CM
Donor /
Sponsor /
Airport /
Airline /
Comm.
Entity
TSA-
Approved
Third-
Party
Accept.
Testing
Org.
OEM /
System
Integrator
Local TSA
Establish and maintain TSA third-party acceptance testing policy
A R C C C C I I I I
Submit third-party acceptance testing organization application package
I C I I I I I R I I
Review third-party acceptance testing organization application package
A R C C I C I C I I
Request additional information from applicant A R C C I C I C I I
TSA Independent Third-Party Acceptance Testing Policy version 2.0 F-2
Division
Executive
Director
T&E
Division
PMO /
Portfolio
DSD /
CAMB
DSD /
RDC
DSD ILS
CM
Donor /
Sponsor /
Airport /
Airline /
Comm.
Entity
TSA-
Approved
Third-
Party
Accept.
Testing
Org.
OEM /
System
Integrator
Local TSA
Prepare technical recommendations for approval, conditional approval, denial, suspension, or removal
A R C C C C I C I I
Make initial approval, reapproval, suspension, or removal decision
A R C C I C I I I I
Notify applicants in writing of approval decision A R I I I I I I I I
Maintain TSA-approved third-party acceptance testing organization list
A R C C I I I I I I
Manage Capability Acceptance
Process for donated TSE I C C A/R C C C I C C
Maintain current CAP Terms and Conditions by donation project
I C C A/R C C I I I I
Ensure donor/sponsor compliance with CAP Terms and Conditions
I C C A/R C C R C C C
Select and contract with TSA-approved third-party acceptance testing organization
I I C C I I A/R C I I
TSA Independent Third-Party Acceptance Testing Policy version 2.0 F-3
Division
Executive
Director
T&E
Division
PMO /
Portfolio
DSD /
CAMB
DSD /
RDC
DSD ILS
CM
Donor /
Sponsor /
Airport /
Airline /
Comm.
Entity
TSA-
Approved
Third-
Party
Accept.
Testing
Org.
OEM /
System
I…
This is the start of the file's text. The full file is on GovTribe.