About this file

This is an environmental audit requirement document (RFP Attachment B-9) for the Jet Propulsion Laboratory (JPL) 5X Mission Assurance Support Services solicitation. The document outlines mandatory environmental audit requirements for subcontractors proposing to lease real property directly to JPL/California Institute of Technology.

The requirements specify that selected offerors must submit a comprehensive environmental audit report prior to award, prepared by an approved firm. The report must detail compliance with federal, state, and local environmental regulations, identify all hazards and contaminants, and document the presence of storage tanks, sumps, pits, dump sites, landfills, pipelines, transformers, capacitors, asbestos, and hazardous materials. The document is related to a broader solicitation (TS-2663-1101135) for JPL's Mission Assurance Support Services, which involves two Time & Material subcontracts: one for Staff Augmentation and one for Task-Based services. This is a small business set-aside under NAICS 541715, with a four-year base period and two three-year options.

View the file

Other files for this federal contract opportunity

Other files attached to 5X MISSION ASSURANCE SUPPORT SERVICES RECOMPETE, newest first.
File Type Posted
5X MASS Pre-proposal Conference.pptx PPTX presentation
TS-2663-1101135 Addendum No. 4.pdf PDF
Question and Answers for 5X Mission Assurance Support Services Recompete.pdf PDF
TS-2663-1101135-A15R1.xlsx XLSX spreadsheet
TS-2663-1101135 Addendum No. 2.pdf PDF
TS-2663-1101135 Addendum No. 1.pdf PDF
TS-2663-1101135-A1.docx DOCX document
TS-2663-1101135-A3.doc DOC document
TS-2663-1101135-A21.doc DOC document
TS-2663-1101135-A22.docx DOCX document
TS-2663-1101135-B13.doc DOC document
Staff Augmentation Subcontract Exhibit 11 - Information Security and Information Technology Requirements_11.22.2024.docx DOCX document
Task-Based Subcontract Exhibit 3- Sample Subcontract Work Order.pdf PDF
Task-Based Subcontract Exhibit 13 - ELI Template Requirements.pdf PDF
Task-Based Subcontract Exhibit 15 - JPL Subcontractor Environmental Safety and Health Plan Requirements.docx DOCX document
Task-Based Subcontract Exhibit 17 -Standard of Conduct and Procedures for Handling Subcontractor Personnel Problems.docx DOCX document
TBD-B-2.02 Task-Based Standard Subcontract 02.25.25.docx DOCX document
TBD-B-2.02 Staff Augmentation Standard Subcontract 02.25.2025.docx DOCX document
TS-2663-1101135-A15.xlsx XLSX spreadsheet
TS-2663-1101135-B4.docx DOCX document
TS-2663-1101135-B7.doc DOC document
TS-2663-1101135-B10.doc DOC document
TS-2663-1101135-B11.docx DOCX document
Staff Augmentation Subcontract Exhibit 6 - Software License Agreement for Use of JPL-Furnished Software .doc DOC document
Staff Augmentation Subcontract Exhibit 7- Sample Monthly Status and Cost Report Summary.pdf PDF
Staff Augmentation Subcontract Exhibit 13 - ELI Template Requirements.pdf PDF
Staff Augmentation Subcontract Exhibit 15 - JPL Subcontractor Environmental Safety and Health Plan Requirements.docx DOCX document
TS-2663-1101135-2.02 1.25.2025.docx DOCX document
TS-2663-1101135-A2.doc DOC document
TS-2663-1101135-A7.docx DOCX document
TS-2663-1101135-A14.docx DOCX document
TS-2663-1101135-A17.xlsx XLSX spreadsheet
TS-2663-1101135-B17.docx DOCX document
Staff Augmentation Subcontract Exhibit 1 - Staff Augmentation Subcontract - Job Classifications_10.28.24.docx DOCX document
Staff Augmentation Subcontract Exhibit 2- Subcontract Work Order Procedure.docx DOCX document
Staff Augmentation Subcontract Exhibit 4- Sample Weekly Summary Status Report.pdf PDF
Staff Augmentation Subcontract Exhibit 5 - Jet Propulsion Laboratory Five Year Fiscal Calendar.pdf PDF
Staff Augmentation Subcontract Exhibit 10 - Subcontractor Personnel Travel Policy.docx DOCX document
Staff Augmentation Subcontract Exhibit 18 -Leased Worker Safety Curriculum Needs Assessment 10.2021.docx DOCX document
Task-Based Subcontract Exhibit 1 - Task Based Subcontract- Job Classifications_01.14.25.docx DOCX document
Task-Based Subcontract Exhibit 5 - Jet Propulsion Laboratory Five Year Fiscal Calendar.pdf PDF
Task-Based Subcontract Exhibit 8- Sample Monthly Status and Cost Report.pdf PDF
TS-2663-1101135-A20.doc DOC document
TS-2663-1101135-B5.doc DOC document
TS-2663-1101135-B12.docx DOCX document
Staff Augmentation Subcontract Exhibit 3- Sample Subcontract Work Order.pdf PDF
Staff Augmentation Subcontract Exhibit 8- Sample Monthly Status and Cost Report.pdf PDF
Staff Augmentation Subcontract Exhibit 12 - Unescorted Access Subcontractor Badging Instructions and Requirements.docx DOCX document
Staff Augmentation Subcontract Exhibit 17 -Standard of Conduct and Procedures for Handling Subcontractor Personnel.docx DOCX document
Task-Based Subcontract Exhibit 2- Subcontract Work Order Procedure.docx DOCX document
Show all 50

5X MISSION ASSURANCE SUPPORT SERVICES RECOMPETE has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jet Propulsion Laboratory

California Institute of Technology

Notice to Prospective Subcontractors of Requirement for an Environmental Audit of the Lease Facilities (RFP Attachment B-9)

If you propose to lease real property directly to the California Institute of Technology/Jet Propulsion Laboratory (JPL), then JPL reserves the right to impose the following requirements on the offeror(s) selected for negotiations.

1.

Requirement for an Environmental Audit of the Premises. The offeror(s) selected for negotiations will be required to submit prior to award an environmental audit report (report), acceptable to JPL, which identifies the exact extent to which the facilities proposed in response to this solicitation, and the real property in or on which they are situated, ARE, and ARE NOT, in compliance with the applicable requirements of federal, state and local environmental laws, regulations and ordinances. The report shall be prepared and attested to by a firm recognized as conducting environmental audits acceptable to JPL. The report shall fully disclose any and all hazards and contaminants in/on/under the facilities or real property and the location(s), nature and extent of such hazards or contaminants. The report shall disclose the locations, nature and condition of any and all of the following (but disclosure shall not be limited to these): storage tanks, sumps, pits, dump sites, landfills, pipelines, transformers, capacitors, asbestos, hazardous materials and waste products. The report shall include, or the preparer of the report shall make available to JPL on JPL request, complete documentation, data, laboratory reports, tests and survey results in support of the matters studied and the matters attested to in the report. The report shall be updated just prior to the award of a subcontract for the lease or purchase of the premises.

2.

Requirement for Environmental Audits of Subcontract Real Property Leases. The offeror agrees that it will obtain, and submit to JPL for JPL approval, an environmental audit report of the real property prior to its award of any subcontract for lease of real property as a direct charge to a subcontract with JPL. To be directly chargeable to a subcontract with JPL a subcontract for the lease of real property shall not be awarded unless the environmental audit report complies with paragraph (a) above and has first been found acceptable by JPL.

3.

Investigation of Lease Sites by JPL Environmental Affairs Program Office Personnel. By submitting its proposal (or quotation or bid), the offeror agrees to submit an environmental audit report required by this notice on request and to assist JPL Environmental Affairs Program Office personnel in confirming the environmental audit report findings through a view of the property which is the subject of the report and a review of any supporting documentation.

JPL 2896-B9, 1/13