Attached to
Trower Avenue Paving (Linda Vista Avenue to Solano Avenue)
Solicitation number
2026-IFB - PC-057
Issued by
Napa County, California

About this file

This is a Bid Set Plans document prepared by the City of Napa, California for the Trower Avenue Paving Project extending from Linda Vista Avenue to Solano Avenue. The project involves grinding and overlay paving operations, curb and gutter replacement, sidewalk reconstruction, and pavement markings and striping along Trower Avenue. Key construction activities include grinding three inches of existing asphalt concrete and placing two inches of new HMA over pavement fabric and a one-inch HMA leveling course, with six-inch HMA plugs at marked digout locations. The project requires removal of existing curb, gutter, and adjacent asphalt concrete, construction of new curb and gutter per City Standard S-1A, removal and reconstruction of sidewalk per City Standard S-4, installation of curb ramps per City Standard S-9, and adjustment of all utility manholes, valves, and boxes to grade. Sealed bids are due by Thursday, December 10, 2026, at 3:00 pm through electronic submission via the procurement portal at https://procurement.opengov.com/portal/cityofnapa. The bid set plans are dated November 10, 2026, and prepared under the direction of registered professional engineer Tam Duong, RCE 54927.

The plans include detailed specifications for pavement sections, construction notes, signing and striping details with thermoplastic markings per California MUTCD standards, and quantities for various curb, gutter, sidewalk, and striping elements throughout the project corridor. General notes specify that contractors must protect existing facilities not called out for removal, trim tree branches prior to grinding and paving, refrain from placing "No Parking" barricades more than 72 hours prior to construction, and allow paving and concrete removal limits to be laid out by the contractor, verified by City Inspector, and potentially adjusted by the City Engineer. The document indicates this is a Bid Set marked "NOT FOR CONSTRUCTION," establishing it as preliminary planning documentation for the bidding process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9'

N56° 25' 46"E 435.44'

±6 2'

4'

5'

LI

N

DA

V

IS

TA

A V

EN

UE

LL

O

YD

D

RI

V

E

LAP CT

TROWER AVENUE

2 2

1+37, 7.06' L

1+80, 7.38' L

1+80, 12.38' L 4+12, 14.12' L

4+12, 17.77' L

4+71, 8.26' L

4+71, 13.24' L

1+37, 15.71' L

L=45.99', R=500.00' D=005°16'

L=692.48', R=3650.00'

D=010°52'

±128SF

±32LF

5'

4'

15'

±6

2'TROWER AVENUE

O

XF

O

RD

ST

RE

ET

FA

IR

FA

X

D

RI

V E

6+45, 30.07' L 6+84, 29.18' L

6+74, 14.35' L

6+74, 9.36' L 7+81, 8.28' L

7+96, 12.51' L

L=692.48', R=3650.00' D=010°52' L=692.48', R=3650.00'D=010°52'

GENERAL NOTES

1. THE PROPERTY LINES, UTILITY INFORMATION & THE AERIAL

IMAGE AS SHOWN ON THESE PLANS ARE APPROXIMATE &

FOR REFERENCE ONLY.

2. CONTRACTOR SHALL NOT PLACE "NO PARKING"

BARRICADES MORE THAN 72 HOURS PRIOR TO

CONSTRUCTION WORK.

3. EXISTING FACILITIES, CONCRETE, LANDSCAPING, &

UTILITIES NOT CALLED OUT TO BE REMOVED SHALL BE

PROTECTED IN-PLACE.

4. CONTRACTOR SHALL TRIM TREE BRANCHES PER PROJECT

SPECIFICATIONS PRIOR TO GRINDING & PAVING.

DIGOUT & HMA PLUG

LEGEND

(N) CONCRETE SURFACE

SAWCUT LINE

EXISTING RIGHT-OF-WAY

(APPROXIMATE LOCATION)

REMOVE (2) TREES - 30" & 40"

EXISTING MANHOLE SEWER

EXISTING MANHOLE TELEPHONE

EXISITNG MANHOLE STORM DRAIN

EXISTING WATER VALVE(E) ELECTRICAL LINE

(E) GAS LINE

(E) STORM DRAIN LINE

(E) SANITARY SEWER LINE

(E) WATER LINE

EXISTING MONUMENT

CONSTRUCTION NOTES

1 GRIND 3" & PLACE 2" HMA OVER PAVEMENT FABRIC & 1" HMA LEVELING

COURSE. AT MARKED DIGOUT LOCATIONS, OVER EXCAVATE & PLACE 6"

HMA PLUG. SEE DETAIL 1, SHT C-3.00.

2 GRIND & OVERLAY LIMITS SHALL BE AS SHOWN & FROM LIP OF GUTTER TO

LIP OF GUTTER. CONFORM WITH (E) PAVEMENT. SEE DETAIL 2, SHT C-3.00.

3 REMOVE (E) CURB, GUTTER & ADJACENT AC (MIN. 2-FT FROM LIP OF

GUTTER). CONSTRUCT NEW CURB & GUTTER PER CITY STD S-1A.

LF AS SHOWN.

4 REMOVE (E) SIDEWALK. CONSTRUCT NEW SIDEWALK PER CITY STD S-4.

SF AS SHOWN.

REMOVE (E) SIDEWALK, CURB, GUTTER & ADJACENT AC (MIN. 2-FT FROM

#SPECIFICATIONS PRIOR TO GRINDING & PAVING.

5. ALL EXISTING UTILITY MANHOLES, VALVES & BOXES SHALL

BE ADJUSTED TO GRADE WITHIN THE PAVING &

CONCRETE WORK LIMITS.

6. PAVING & CONCRETE REMOVAL LIMITS AND AC DIGOUT

SHALL BE LAID OUT BY CONTRACTOR, VERIFIED BY CITY

INSPECTOR & MAY BE ADJUSTED BY CITY ENGINEER.

7. WHERE NEW CONCRETE CONFORMS TO EXISTING

CONCRETE, PROVIDE CONCRETE CONNECTION PER CITY

STD S-4B.

DATE

PLANS PREPARED

UNDER THE DIRECTION OF

SHEETS:

DWG LOG #

DATE: NOVEMBER 10, 2026

S 26-024

TAM DUONG, RCE 54927

A B C D E F G H I J K L

DRAWN BY: LM

CHECKED BY: RC

OF 6 -

TROWER AVENUE PAVING

LINDA VISTA AVE TO SOLANO AVE

BYDATEDESCRIPTIONNO.

REVISIONS BID SET

NOT FOR CONSTRUCTION

RE

GI

ST

ER

ED

PROFESSI NOO AL ENGINEER

STAT

A

A

E O OF FC LI

IRN

M

TA

D

C I IV L

U

C 54927

ONG

11/10/26

M A

TC

H

LI

N

E

LO

W

ER

L

EF

T

M A

TC

H

LI

N

E

U

PP

ER

R

IG

HT

PAVING PLAN

2 C 2.00

M A

TC

H

LI

N

E

SH

EE

T C -2

.0

0' 20' 40'

SCALE: 1" = 20'

REFERENCE CONTROL POINTS TABLE

POINT # NORTHING

1880991.04

EASTING

6468561.07

ELEVATION

91.68

DESCRIPTION

FND MON NO TAG

15'

84'

±6 4'N56° 09' 47"E 1330.42'

5'

43' 8'

SO

LA

N O

A V

E

TROWER AVENUE

BRIARWOOD

STREET

5 5

19+04, 15.94' L

19+81, 12.11' L

20+65, 27.74' L

22+20, 22.32' L

22+62, 27.68' L

79'

7'

29'

N56° 09' 47"E 1330.42'

10'

±33 SF

8'

M A

HE

R

ST

TR

EE

T

RA

LE

IG

H

ST

RE

ET

TROWER AVENUE

14+24, 7.79' L

15+03, 15.04' L

16+26, 7.97' L

16+46, 8.97' R

16+75, 18.89' R

CONSTRUCTION NOTES

1 GRIND 3" & PLACE 2" HMA OVER PAVEMENT FABRIC & 1" HMA LEVELING

COURSE. AT MARKED DIGOUT LOCATIONS, OVER EXCAVATE & PLACE 6"

HMA PLUG. SEE DETAIL 1, SHT C-3.00.

2 GRIND & OVERLAY LIMITS SHALL BE AS SHOWN & FROM LIP OF GUTTER TO

LIP OF GUTTER. CONFORM WITH (E) PAVEMENT. SEE DETAIL 2, SHT C-3.00.

REMOVE (E) CURB, GUTTER & ADJACENT AC (MIN. 2-FT FROM LIP OF

4 REMOVE (E) SIDEWALK. CONSTRUCT NEW SIDEWALK PER CITY STD S-4.

SF AS SHOWN.

5 REMOVE (E) SIDEWALK, CURB, GUTTER & ADJACENT AC (MIN. 2-FT FROM

LIP OF GUTTER). CONSTRUCT "CASE C" CURB RAMP PER CITY STD S-9. FIELD

FIT TO EXISTING SITE CONDITIONS & VERIFY EXISTING ELEVATIONS &

DIMENSIONS PRIOR TO CONSTRUCTION. SIDEWALK SECTION SHALL BE PER

CITY STD. S-4 & CURB/GUTTER SECTION SHALL BE PER CITY STD. S-1A.

REPLACE REMOVED ADJACENT AC SECTION WITH 6" HMA PLUG.

DIGOUT & HMA PLUG

LEGEND

(N) CONCRETE SURFACE

SAWCUT LINE

EXISTING RIGHT-OF-WAY

(APPROXIMATE LOCATION)

REMOVE (2) TREES - 30" & 40"

EXISTING MANHOLE SEWER

EXISTING MANHOLE TELEPHONE

EXISITNG MANHOLE STORM DRAIN

EXISTING WATER VALVE(E) ELECTRICAL LINE

(E) GAS LINE

(E) STORM DRAIN LINE

(E) SANITARY SEWER LINE

(E) WATER LINE

EXISTING MONUMENT

GENERAL NOTES

1. THE PROPERTY LINES, UTILITY INFORMATION & THE AERIAL

IMAGE AS SHOWN ON THESE PLANS ARE APPROXIMATE &

FOR REFERENCE ONLY.

2. CONTRACTOR SHALL NOT PLACE "NO PARKING"

BARRICADES MORE THAN 72 HOURS PRIOR TO

CONSTRUCTION WORK.

3. EXISTING FACILITIES, CONCRETE, LANDSCAPING, &

UTILITIES NOT CALLED OUT TO BE REMOVED SHALL BE

PROTECTED IN-PLACE.

4. CONTRACTOR SHALL TRIM TREE BRANCHES PER PROJECT

SPECIFICATIONS PRIOR TO GRINDING & PAVING.

SPECIFICATIONS PRIOR TO GRINDING & PAVING.

5. ALL EXISTING UTILITY MANHOLES, VALVES & BOXES SHALL

BE ADJUSTED TO GRADE WITHIN THE PAVING &

CONCRETE WORK LIMITS.

6. PAVING & CONCRETE REMOVAL LIMITS AND AC DIGOUT

SHALL BE LAID OUT BY CONTRACTOR, VERIFIED BY CITY

INSPECTOR & MAY BE ADJUSTED BY CITY ENGINEER.

7. WHERE NEW CONCRETE CONFORMS TO EXISTING

CONCRETE, PROVIDE CONCRETE CONNECTION PER CITY

STD S-4B.

DATE

PLANS PREPARED

UNDER THE DIRECTION OF

SHEETS:

DWG LOG #

DATE: NOVEMBER 10, 2026

S 26-024

TAM DUONG, RCE 54927

A B C D E F G H I J K L

DRAWN BY: LM

CHECKED BY: RC

OF 6 -

TROWER AVENUE PAVING

LINDA VISTA AVE TO SOLANO AVE

BYDATEDESCRIPTIONNO.

REVISIONS BID SET

NOT FOR CONSTRUCTION

RE

GI

ST

ER

ED

PROFESSI NOO AL ENGINEER

STAT

A

A

E O OF FC LI

IRN

M

TA

D

C I IV L

U

C 54927

ONG

11/10/26

M A

TC

H

LI

N

E

LO

W

ER

L

EF

T

M A

TC

H

LI

N

E

U

PP

ER

R

IG

HT

PAVING PLAN

3 C 2.01

M A

TC

H

LI

N

E

SH

EE

T C -2

.0

0' 20' 40'

SCALE: 1" = 20'

DATE

PLANS PREPARED

UNDER THE DIRECTION OF

SHEETS:

DWG LOG #

DATE: NOVEMBER 10, 2026

S 26-024

TAM DUONG, RCE 54927

A B C D E F G H I J K L

DRAWN BY: LM

CHECKED BY: RC

OF 6 -

TROWER AVENUE PAVING

LINDA VISTA AVE TO SOLANO AVE

BYDATEDESCRIPTIONNO.

REVISIONS BID SET

NOT FOR CONSTRUCTION

RE

GI

ST

ER

ED

PROFESSI NOO AL ENGINEER

STAT

A

A

E O OF FC LI

IRN

M

TA

D

C I IV L

U

C 54927

ONG

11/10/26

DETAILS

4 C 3.00

(E) AB

COMPACTED SOIL

(E) AC LAYER

MORE THAN 3"

(E) AB VARIES

(E) AC

(N) PAVEMENT

FABRIC

(E) FG = (N) FG

PROVIDE A STRAIGHT LINE AT

THE CONFORM (NO JAGGED

EDGES). SAW CUT IF NECESSARY

ADD TACK COAT ALONG

ENTIRE EDGE AND TOP

SURFACE OF (E) AC PVMT

1 PAVEMENT SECTION

NOT TO SCALE

COMPACTED SOIL

2 TYPICAL SECTION CONFORM WITH (E) PAVEMENT

NOT TO SCALE

(E) AC PVMT

SECTION

PAVEMENT SECTION

PER PLAN

2" HMA TO MATCH (E)

1" THICK LAYER OF 3 8"

HMA LEVELING COURSE

6" HMA PLUG,

4" AGGREGATE,

SEE PLAN VIEW

FOR LOCATIONS

PAVEMENT SECTION.

TAC COAT BETWEEN

HMA LAYERS

3 CURB RAMP PAY LIMIT

NOT TO SCALE

CURB RAMP PAY LIMIT

CURB & GUTTER

RAMP RAMP

(E) AC LAYER

LESS THAN 3"

(E) AB VARIES

COMPACTED SOIL

(E) AC PVMT

SECTION

PAVEMENT SECTION

PER PLAN

PAVEMENT SECTION.

TAC COAT BETWEEN

HMA LAYERS

(E) FG = (N) FG

PROVIDE A STRAIGHT LINE AT

THE CONFORM (NO JAGGED

EDGES). SAW CUT IF NECESSARY

ADD TACK COAT ALONG

ENTIRE EDGE AND TOP

SURFACE OF (E) AC PVMT

TROWER AVENUE

LL

O

YD

D

RI

V

E

LA

P

C T

LI

N

D A

V

IS

TA

A

VE

N

UE

32 - 80± LF

27B - 75± LF

27B - 510± LF

32 - 98± LF 32 - 423± LF

39A - 216± LF

DB

±1 2'

±1 2'

6'

8'

8'

8' 6'

8'

±1 2'

2'

39 - 1020± LF 6'

2'8'

6'

39 - 150± LF

±1 2'

2'

8'

8'

8'

39A - 88± LF

8' 2'

27B HATCH - 102± LF

12' SPACING

39A - 284± LF

27B HATCH - 18± LF

12' SPACING

27B

27B HATCH - 21± LF

12' SPACING

39A - 136± LF 39A - 136± LF39A - 40± LF

22 - 48± LF

22 - 48± LF

22 - 48± LF

22 - 48± LF

DB

38 - 76± LF

27B - 62± LF

39A - 108± LF

39A - 108± LF

39 - 124± LF

22 - 122± LF

27B - 18± LF

39 - 18± LF

22 - 18± LF

38 - 18± LF

39A - 18± LF

FA

IR

FA

X

D

RI

V E

TROWER AVENUE

O

XF

O

RD

ST

RE

ET

38 - 80± LF

39A - 216± LF

DB

DB

32 - 136± LF

39A - 216± LF

27B - 258± LF

39 - 516± LF

8'

8'

6'

6'

6'

2'

8'

39A - 132± LF

8'

±1

8'

±1 2'

2'

8'

6'

'29 - 90± LF

39A - 112± LF

27B - 238± LF

39 - 632± LF

39A - 112± LF 39A - 40± LF

39A - 40± LF

27B

27B

27B HATCH 27B HATCH

27B HATCH - 63± LF

12' SPACING

39A - 40± LF

22 - 48± LF

22 - 83± LF

22 - 48± LF

REMOVE "NO

PARKING" SIGN

REPLACE WITH R81(CA)

REMOVE "NO

PARKING" SIGN

REPLACE WITH R81(CA)

REMOVE "NO

PARKING" SIGN

REPLACE WITH

R81(CA)

39 27B

27B HATCH

DB

DATE

PLANS PREPARED

UNDER THE DIRECTION OF

SHEETS:

DWG LOG #

DATE: NOVEMBER 10, 2026

S 26-024

TAM DUONG, RCE 54927

A B C D E F G H I J K L

DRAWN BY: LM

CHECKED BY: RC

OF 6 -

TROWER AVENUE PAVING

LINDA VISTA AVE TO SOLANO AVE

BYDATEDESCRIPTIONNO.

REVISIONS BID SET

NOT FOR CONSTRUCTION

RE

GI

ST

ER

ED

PROFESSI NOO AL ENGINEER

STAT

A

A

E O OF FC LI

IRN

M

TA

D

C I IV L

U

C 54927

ONG

11/10/26

M A

TC

H

LI

N

E

LO

W

ER

L

EF

T

M A

TC

H

LI

N

E

U

PP

ER

R

IG

HT

M A

TC

H

LI

N

E

SH

EE

T C

-4 .0

SIGNING & STRIPING PLAN

5 C 4.00

STRIPING NOTES

INSTALL "STOP" MARKING & STOP LINE

PER STOP APPROACH DETAIL.

LEGEND

39 - 186 ± LF

CA MUTCD DETAIL NUMBER

ESTIMATED QUANTITY

LADDER CROSSWALK - A24F

4'

10'

2' 1'

INSTALL PAVEMENT MARKINGS

WORDS PER CALTRANS A24D (TYP)

DOUBLE SIDED BLUE REFLECTOR (TYP)

INSTALL TYPE IV ARROW (TYP)

INSTALL "BIKE LANE

SYMBOL" AND BIKE

LANE ARROW

INSTALL GREEN

PAVEMENT

WHITE

GREEN

DETAIL 39A

4' x 5' to 8' GREEN

PAVEMENT

DIRECTION OF

TRAFFIC FLOW

WHITE

6'

6'

6'

15'

5' MIN

6' MAX

DETAIL 39A

WHEN NOT

AGAINST GUTTER

GENERAL NOTES

1. ALL STRIPING AND MARKINGS SHALL BE THERMOPLASTIC

AND PLACED PER CURRENT CA MUTCD STANDARDS.

2. CONTRACTOR SHALL CAT-TRACK A MINIMUM OF 2 DAYS

AFTER PAVING OPERATIONS. CONTRACTOR SHALL ALLOW

3 DAYS FOR ENGINEER REVIEW AND APPROVAL.

3. CAT-TRACK MUST APPROVED BY ENGINEER PRIOR TO FINAL

STRIPING.

DB

BASIC CROSSWALK - A24F

6' MIN1'

INSTALL WHITE "STOP" LETTERING

4'

8'

8'

INSTALL 1' WIDE WHITE STOP BAR

INSTALL 1' WHITE CROSSWALK BAR

C

EN

TERLIN

E

PER PLA

NINSTALL BASIC OR LADDER CROSSWALK

PER MARKING DETAILS.

0' 20' 40'

SCALE: 1" = 20'

YIELD MARKINGS-ROADWAY

24" 12"

YIELD MARKINGS-BIKE LANE

12" 6"

STOP APPROACH

PAVEMENT MARKINGS CROSSWALK

BR

IA

RW

O

O D

ST

RE

ET

TROWER AVENUE

32 - 256± LF

39 - 392± LF

37B - 135± LF

6'

6'

SO

LA

N O

A

VE

39A - 108± LF

39A - 108± LF

9A - 304± LF

39 - 202± LF

8'

6'

6'

±1

1'

38 - 96± LF

8'

8'

27B - 196± LF

27B HATCH - 45± LF

12' SPACING

39A - 40± LF 39A - 40± LF

2' 27B

39 39

22 - 155± LF

22 - 48± LF

DB

DB

RA

LE

IG

H

ST

RE

ET

M A

HE

R

ST

TR

EE

T

32 - 322± LF

39 - 306± LF

27B - 306± LF

39A - 216± LF

32 - 195± LF

39 - 109± LF

8'

8'

DB

TROWER AVENUE

39 - 65± LF

8' 6'

2'

8'

±1 1'

6'

2'8' 8' 6'

2'

6'

27B - 54± LF

39A - 40± LF 39A - 112± LF 39A - 112± LF

39A - 216± LF

±1 1'

6'

8'

39 - 921± LF

27B (HATCH) 71± LF

12' SPACING

27B

27B HATCH27B HATCH - 66± LF

12' SPACING

27B HATCH - 15± LF

12' SPACING

22 - 48± LF

22 - 48± LF

REMOVE "NO

PARKING" SIGN

REPLACE WITH R81(CA)

DB

DATE

PLANS PREPARED

UNDER THE DIRECTION OF

SHEETS:

DWG LOG #

DATE: NOVEMBER 10, 2026

S 26-024

TAM DUONG, RCE 54927

A B C D E F G H I J K L

DRAWN BY: LM

CHECKED BY: RC

OF 6 -

TROWER AVENUE PAVING

LINDA VISTA AVE TO SOLANO AVE

BYDATEDESCRIPTIONNO.

REVISIONS BID SET

NOT FOR CONSTRUCTION

RE

GI

ST

ER

ED

PROFESSI NOO AL ENGINEER

STAT

A

A

E O OF FC LI

IRN

M

TA

D

C I IV L

U

C 54927

ONG

11/10/26

M A

TC

H

LI

N

E

LO

W

ER

L

EF

T

M A

TC

H

LI

N

E

U

PP

ER

R

IG

HT

SIGNING & STRIPING PLAN

6 C 4.01

M A

TC

H

LI

N

E

SH

EE

T C -4

.0

STRIPING NOTES

INSTALL "STOP" MARKING & STOP LINE

PER STOP APPROACH DETAIL.

LEGEND

39 - 186 ± LF

CA MUTCD DETAIL NUMBER

ESTIMATED QUANTITY

INSTALL PAVEMENT MARKINGS

WORDS PER CALTRANS A24D (TYP)

DOUBLE SIDED BLUE REFLECTOR (TYP)

INSTALL TYPE IV ARROW A24A (TYP)

INSTALL "BIKE LANE

SYMBOL" AND BIKE

LANE ARROW

INSTALL GREEN

PAVEMENT

WHITE

GREEN

DETAIL 39A

4' x 5' to 8' GREEN

PAVEMENT

DIRECTION OF

TRAFFIC FLOW

WHITE

6' 6'

6'

5' MIN

6' MAX

DETAIL 39A

WHEN NOT

AGAINST GUTTER

GENERAL NOTES

1. ALL STRIPING AND MARKINGS SHALL BE THERMOPLASTIC

AND PLACED PER CURRENT CA MUTCD STANDARDS.

2. CONTRACTOR SHALL CAT-TRACK A MINIMUM OF 2 DAYS

AFTER PAVING OPERATIONS. CONTRACTOR SHALL

ALLOW 3 DAYS FOR ENGINEER REVIEW AND APPROVAL.

3. CAT-TRACK MUST APPROVED BY ENGINEER PRIOR TO

FINAL STRIPING.

DB

BASIC CROSSWALK - A24F

6' M

IN

1'

INSTALL BASIC OR LADDER CROSSWALK

PER MARKING DETAILS.

INSTALL TYPE VI ARROW A24A (TYP)

INSTALL RAILROAD CROSSING

SYMBOL - A24B (TYP)

INSTALL TYPE I ARROW A24A (TYP)

INSTALL TYPE VII ARROW A24A (TYP)

0' 20' 40'

SCALE: 1" = 20'

INSTALL WHITE "STOP" LETTERING

4'

8'

8'

INSTALL 1' WIDE WHITE STOP BAR

INSTALL 1' WHITE CROSSWALK BAR

STOP APPROACH

PAVEMENT MARKINGS CROSSWALK

C

EN

TERLIN

E

PER PLA

N

Trower Ave Paving Bid Set
Sheets and Views
01-G1-TrowerPaving-01 G1.00-Index & Cover
02-03-C2-Paving-02-C2.00-Paving
02-03-C2-Paving-03-C2.01-Paving
04-C3-Details-06 C3.00-Details
05-06-C4-Striping-05-C4.00-Striping
05-06-C4-Striping-06-C4.01-Striping

File details come from the government source that posted it. Updated .