TROUP COUNTY GA 900 DALLIS STREET REROOF SPEC.pdf

PDF 5 MB Posted

Attached to
900 Dallis Street Re-Roof Project
Solicitation number
PE-77030-NONST-2024-000000006
Issued by
Terrell County, Georgia

About this file

The document is a specification for the Troup County GA - 900 Dallis Street Reroof project, issued by the Troup County Board of Commissioners. The project consists of the reroofing of the 900 Dallis Street Building, including tearoff, new insulation, new metal roof, and new 60 mil fully-adhered TPO roof system and accessories. Sealed bids are due by 2:00 PM on April 30, 2024 at the Troup County Purchasing Department. A mandatory pre-bid meeting will be held on April 9, 2024 at the project site. The contract will be awarded on a lump sum basis, and the project is to be substantially complete within 90 consecutive calendar days.

The bid package includes a 5% bid bond, and the successful bidder will be required to provide 100% performance and payment bonds. The Owner reserves the right to reject any or all bids and to award the project based on best value for Troup County. Bidders must provide a completed Troup County Vendor Application, E-Verify Forms, and W-9 prior to beginning work, and all subcontractors must provide a Troup County E-Verify Form.

View the file

Other files

File Type Posted
900 Dallis Street Re_Roof _ Addenda 1.docx DOCX document
2024_03_27 23_01599 _ TROUP CO_ 900 DALLIS ST.pdf PDF
900 DALLIS STREET RE_ROOF BID NOTICE.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TROUP COUNTY GA 900 DALLIS

STREET REROOF

900 DALLIS, ST

TROUP COUNTY, Georgia 30240

TROUP COUNTY

23-01599

ElsiEckstein Snapshot

TROUP COUNTY GA 900

DALLIS STREET REROOF

SECTION 000101 - PROJECT

TITLE PAGE

000101 - 1 Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties. It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

DOCUMENT 000101 - PROJECT TITLE PAGE

1.1 PROJECT MANUAL VOLUME 1

A. TROUP COUNTY GA 900 DALLIS STREET REROOF.

B. TROUP COUNTY.

C. Owner Project No. <Insert number>.

D. Architect Project No. 23-01599 .

E. 2WR+PARTNERS.

F. 11 Nith Street, Suite 120 .

G. Columbus, GA, 31901 .

H. Phone: (706)571-6923 .

I. Fax: (706)571-6928 .

J. Issued: 9-29-2023 .

K. Copyright 2023 2WR+Partners . All rights reserved.

END OF DOCUMENT 000101

SECTION 00 0110 – TABLE

OF CONTENTS

SECTION 00-0110 – TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 00 0110 - Table of Contents

B. 00 1113 - Advertisement for Bids

C. 00 2113 - Instructions to Bidders

D. 00 4000 - Procurement Forms and Supplements

E. 00 4100 - Bid Form

SPECIFICATIONS

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 01 1000 - Summary

B. 01 3000 - Administrative Requirements

C. 01 3216 - Construction Progress Schedule

D. 01 4000 - Quality Requirements

E. 01 5000 - Temporary Facilities and Controls

F. 01 6000 - Product Requirements

G. 01 7000 – Execution Requirements

H. 01 7419 - Construction Waste Management and Disposal

2.02 DIVISION 02 -- EXISTING CONDITIONS

A. 02 4119 – Selective Demolition

2.03 DIVISION 03 -- CONCRETE

2.04 DIVISION 05 -- METALS

2.05 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

A. 06 1000 - Rough Carpentry

B. 06 1600 - Sheathing

2.06 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

A. 07 0150.19 – Preparation for Reroofing

B. 07 1326 – Self-Adhering Sheet Waterproofing

C. 07 2100 – Thermal Insulation

D. 07 4113.16 Standing-Seam Metal Roof Panels

E. 07 5423 - Thermoplastic Polyolefin Roofing

F. 07 7100 - Roof Specialties

G. 07 9200 – Joint Sealants

2.07 DIVISION 08 -- OPENINGS

2.08 DIVISION 09 – FINISHES

END OF SECTION

00-0110 Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

SECTION 001113 –

ADVERTISEMENT FOR BIDS

001113 - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

SECTION 001113 – ADVERTISEMENT FOR BIDS

PART 1 - GENERAL

1.1 THE OWNER (HERINAFTER REFERRED TO AS OWNER):

A. Troup County, Georgia

B. Address:

100 Ridley Avenue

LaGrange, GA 30240

1.2 THE ARCHITECT (HEREINAFTER REFERRED TO AS ARCHITECT):

A. 2WR + Partners

B. Address:

11 9th Street, Suite 120

Columbus, GA 31901

INVITATION TO BID

Troup County Re-Roof Project

900 Dallis Street, LaGrange, Ga 30240

The Board of County Commissioners of Troup County will receive sealed bid proposals for: Troup County GA –

900 Dallis Street, Re-Roof Project, as described in the construction documents for this project. Construction documents for this project and bid proposal documents can be obtained at www.troupcountyga.gov/purchasing/bids.

All sealed bid proposals from Contractors will be received by Troup County Purchasing Department, in 100

Ridley Avenue, Suite 3100, until 2:00 PM at the time prevailing in LaGrange, Georgia on 30 APRIL 2024 for the Troup County GA – 900 Dallis Street, Re-Roof Project. At the time and place noted above, the sealed bid proposals will be publicly opened. The exterior of the package must be clearly marked identifying the contents of the package. All sealed bid proposals shall include a fully completed/executed BID PROPOSAL FORM (as provided in the bid proposal documents) and the required 5% Bid Bond. Each response shall include one (1) original bid proposal, three (3) hard copies, and one (1) electronic copy of the complete bid proposal.

The contract, if awarded, will be on a lump sum basis. No bid may be withdrawn for a period of sixty (60) days after time has been called on the date of the opening.

The anticipated start date for construction shall be within sixty (60) consecutive calendar days after award.

The project is to be substantially complete within ninety (90) consecutive calendar days.

Bid proposals delivered to:

Troup County Purchasing Department 100 Ridley Ave., Suite 3100 LaGrange, GA 30240

Late bids will NOT be accepted.

Mandatory Pre-Bid Meeting will be held at 2:00 PM on 9 APRIL 2024 at the Project Site.

All requests for clarification or additional information must be made via email ONLY to Diana Evans, Troup County Purchasing Director at devans@troupcountyga.gov. No phone calls or contacts other than email is allowed. Contacting any other party prior to the bid opening for clarification or additional information will require that any bid submitted by said bidder being non-responsive. No requests for information will be allowed after 15 APRIL 2024.

Any and all addenda for this project will be posted at www.troupcountyga.gov/puchasing/bids.

A Bid Bond equal to 5% of the bid amount is required. Both a Performance Bond and a Payment Bond will be required in the amount equal to 100% of the contract price from the successful bidder. The bonding surety must be either authorized by the Insurance Commissioner of Georgia to do business in Georgia or must be on the United States Treasury’s list of approved bond sureties.

The successful bidder shall be required to provide comprehensive and liability insurance wherein the County is named as co-insured, contractor is also required to provide a certificate of insurance for Workmen’s Compensation Insurance.

The successful bidder must provide a completed Troup County Vendor Application, E-Verify Forms and a W-9 prior to beginning work. All subcontractors must provide a Troup County E-Verify Form prior to beginning work on site.

The Owner reserves the right to reject any or all bids and to waive technicalities and informalities.

The Owner reserves the right to interview any or all respondents.

The Owner reserves the right to award the project, as determined to be in the best interest of Troup County.

The Owner reserves the right to award the project, as determined to provide the best value for Troup County.

Troup County Board of Commissioners

BY: ______________________________

Diana Evans, Purchasing Director

Troup County, Georgia

SECTION 04000 –

PROCUREMENT FORMS AND

SUPPLEMENTS

SECTION 00 4000

PROCUREMENT FORMS AND SUPPLEMENTS

PART 1 GENERAL

1.01 FORMS

A. Use the following forms for the specified purposes unless otherwise indicated elsewhere in the procurement requirements.

B. Substitution Request Form (During Procurement): CSI/CSC Form 1.5C - Substitution Request

(During the Bidding/Negotiating Stage).

C. Bid Form: Section 00 4100 - Bid Form.

D. Procurement Form Supplements:

1. Bid Security Form: AIA A310.

2. Unit Prices Form: Section 00 4322 - Unit Prices Form.

3. Proposed Schedule of Values Form: AIA G703.

E. Representations and Certifications:

1. Bidder's Qualifications: AIA A305.

1.02 REFERENCE STANDARDS

A. AIA A305 - Contractor's Qualification Statement; 1986.

B. AIA A310 - Bid Bond; 2010.

C. AIA G703 - Continuation Sheet; 1992.

D. CSI/CSC Form 1.5C - Substitution Request (During the Bidding/Negotiating Stage);

Current Edition.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF

SECTION

ElsiEckstein Snapshot

SECTION 004100 – BID FORM

004100 - 1 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for

SECTION 00 4100 - BID FORM

THE PROJECT AND THE PARTIES

1.01 TO:

A. Troup County, Georgia

(Owner) 100 Ridley

Avenue

LaGrange, Georgia 30240

1.02 FOR:

A. Project: Troup County GA 900 Dallis Street Reroof

B. Architect's Project Number: 23-

01599

1.03 DATE: (BIDDER TO ENTER DATE)

1.04 SUBMITTED BY: (BIDDER TO ENTER NAME AND ADDRESS)

A. Bidder's Full Name

1. Address

2. City, State, Zip

1.05 OFFER

A. Having examined the Place of The Work and all matters referred to in the Instructions to Bidders and the Bid Documents prepared by for the above mentioned project, we, the undersigned, hereby offer to enter into a Contract to perform the Work for the Sum of:

B.

dollars ($ ), in lawful money of the United States of America.

C. We have included the required security deposit as required by the Instruction to Bidders.

1.06 ACCEPTANCE

A. This offer shall be open to acceptance and is irrevocable for thirty days from the bid closing date.

B. If this bid is accepted by Owner within the time period stated above, we will:

1. Execute the Agreement within seven days of receipt of Notice of Award.

2. Furnish the required bonds within seven days of receipt of Notice of Award.

3. Commence work within ten days after written Notice to Proceed of this bid.

C. If this bid is accepted within the time stated, and we fail to commence the Work or we fail to provide the required Bond(s), the security deposit shall be forfeited as damages to Owner by reason of our failure, limited in amount to the lesser of the face value of the security deposit or the difference between this bid and the bid upon which a Contract is signed.

D. In the event our bid is not accepted within the time stated above, the required security deposit shall be returned to the undersigned, in accordance with the provisions of the Instructions to Bidders; unless a mutually satisfactory arrangement is made for its retention and validity for an extended period of time.

1.07 CONTRACT TIME

SECTION 004100 – BID FORM

004100 - 2 Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for

A. If this Bid is accepted, we will:

B. Complete the Work in calendar days from Notice to Proceed.

1.08 UNIT PRICES

A. The following are Unit Prices for specific portions of the Work as listed. The following is the list of Unit Prices:

B. ITEM DESCRIPTION - UNIT QUANTITY - UNIT PRICE - ITEM VALUE

1.09 CHANGES TO THE WORK

A. When Architect establishes that the method of valuation for Changes in the Work will be net cost plus a percentage fee in accordance with General Conditions, our percentage fee will be:

1. percent overhead and profit on the net cost of our own Work;

2. percent on the cost of work done by any Subcontractor.

1.10 ADDENDA

A. The following Addenda have been received. The modifications to the Bid Documents noted below have been considered and all costs are included in the Bid Sum.

1. Addendum # Dated .

2. Addendum # Dated .

3. Addendum # Dated .

4. Addendum # Dated .

5. Addendum # Dated .

6. Addendum # Dated .

1.11 BID FORM SIGNATURE(S)

A. The Corporate Seal of

B.

C. (Bidder - print the full name of your firm)

D. was hereunto affixed in the presence of:

E.

F. (Authorized signing officer, Title)

G. (Seal)

H.

I. (Authorized signing officer, Title)

SECTION 011000 -

SUMMARY

011000 - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

SECTION 011000 - SUMMARY

1.1 PROJECT INFORMATION

A. Project Identification: Troup County GA – 900 Dallis Street Reroof.

B. Owner: Troup County Board of Commissioners.

C. Architect: 2WR + Partners.

D. The Project consists of the reroofing of 900 Dallis Street Building. Reroofing to include tearoff, new insulation, new metal roof and new 60 mil fully-adhered TPO roof system and accessories.

1.2 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price.

1.3 DESCRIPTION OF ALTERATIONS WORK

A. Scope of demolition and removal work is indicated on drawings and specified in Section 024100

B. Scope of alterations work is indicated on drawings.

1.4 OWNER OCCUPANCY

A. Owner intends to continue to occupy the portions of the existing building during the entire construction period.

1.5 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

B. Arrange use of site and premises to allow:

1. Owner occupancy.

2. Work by Others.

3. Work by Owner.

4. Use of site and premises by the public.

C. Provide access to and from site as required by law and Owner.

SECTION 011000 -

SUMMARY

011000 - 2

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

1. Do not obstruct roadways, sidewalks, or other public ways without permit.

D. Existing building spaces may not be used for storage.

E. Utility Outages and Shutdown:

1. Limit disruption of utility services to hours the building is unoccupied.

2. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Owner and authorities having jurisdiction.

3. Prevent accidental disruption of utility services to other facilities.

1.6 WORK SEQUENCE

A. Coordinate construction schedule and operations with Owner.

END OF SECTION 011000

SECTION 013000 –

ADMINISTRATIVE

REQUIREMENTS

013000 - 1

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

SECTION 013000 – ADMINISTRATIVE REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

C. Construction progress schedule.

D. Coordination Drawings.

E. Submittals for review, information, and project closeout.

F. Number of copies of submittals.

G. Submittal procedures.

1.2 RELATED REQUIREMENTS

A. Conditions of the Contract.

B. Section 013216 – Construction Progress Schedule: Form, content, and administration of schedules.

C. Section 017000 – Execution and Closeout Requirements: Additional coordination requirements.

D. Section 017800 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

PART 2 – PRODUCTS - NOT USED

PART 3 - EXECUTION

3.1 COORDINATION

A. Coordination: Coordinate construction operations included in various Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

SECTION 013000 –

013000 - 2

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

B. If necessary, prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their

Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other constractors to avoid conflicts and to ensure orderly progress of Work. Such administrative activities include, but are not limited to the following:

1. Preparation of Constractor’s Construction Schedule.

2. Preparation of Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work.

3.2 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. General: In addition to Project superintendent, provide other administrative and supervisory personnel as required for proper performance of the Work.

1. Include special personnel required for coordination of operations with other contractors.

3.3 PRECONSTRUCTION MEETING

A. Architect will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

4. Major subcontractors as determined by Project Team.

SECTION 013000 –

013000 - 3

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

C. Agenda:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract.

6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Scheduling.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.4 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required:

1. Contractor.

2. Owner.

3. Architect.

4. Contractor’s superintendent.

5. Major subcontractors.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

SECTION 013000 –

013000 - 4

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

9. Maintenance of quality and work standards.

10. Effect of proposed changes on progress schedule and coordination.

11. Other business relating to work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.5 PREINSTALLATION CONFERENCES

A. Conduct and pre-installation conference at the project site before each activity that requires coordination with other construction or as required by the Project Manual.

B. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installation that have preceded or will follow, shall attend the meeting. Advise Architect of schedule meeting dates.

C. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

1. Contract Documents.

2. Options.

3. Related Change Orders.

4. Purchases.

5. Deliveries.

6. Submittals.

7. Review of mockups.

8. Possible conflicts.

9. Compatibility problems.

10. Time schedules.

SECTION 013000 –

013000 - 5

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

11. Weather limitations.

12. Manufacturer’s written recommendations.

13. Warranty requirements.

14. Compatibility of materials.

15. Acceptability of substrates.

16. Temporary facilities and controls.

17. Space and access limitations.

18. Regulations of authorities having jurisdiction.

19. Testing and inspecting requirements.

20. Required performance results.

21. Protection of construction and personnel.

D. Record significant conference discussions, agreements, and disagreements.

E. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

3.6 COORDINATION MEETINGS

A. Conduct coordination meetings at regular intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and pre-installation conferences.

B. Attendees: In addition to representatives of Owner, and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

C. Agenda: Review and correct or approve minutes of the previous coordinating meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

1. Combined Contractor’s Construction Schedule: Review progress since the last coordinating meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to Combined Contractor’s Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties

SECTION 013000 –

013000 - 6

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927) involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

2. Schedule Updating: Revise Combine Contractor’s Construction Schedule after each coordination meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting.

3. Review present and future needs of each contractor present, including the following:

a. Interface requirements.

b. Sequence of operations.

END OF SECTION 011000

01 3216 - 1

DALLIS STREET REROOF

SECTION 013216 –

CONSTRUCTION PROGRESS

SCHEDULE

PART 1 GENERAL

1.01 SECTION

INCLUDES

SECTION 01 3216

CONSTRUCTION PROGRESS SCHEDULE

A. Preliminary schedule.

B. Construction progress schedule, with network analysis diagrams and reports.

1.02 RELATED SECTIONS

A. Section 01 1000 - Summary: Work sequence.

1.03 REFERENCE STANDARDS

A. AGC (CPSM) - Construction Planning and Scheduling Manual; 2004.

B. M-H (CPM) - CPM in Construction Management - Project Management with CPM;

O'Brien; 2006.

1.04 SUBMITTALS

A. Within 10 days after date of Agreement, submit preliminary schedule.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

1.05 QUALITY ASSURANCE

A. Scheduler: Contractor's personnel or specialist Consultant specializing in CPM scheduling with one years minimum experience in scheduling construction work of a complexity comparable to this Project, and having use of computer facilities capable of delivering a detailed graphic printout within 48 hours of request.

1.06 SCHEDULE FORMAT

A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRELIMINARY SCHEDULE

A. Prepare preliminary schedule in the form of a horizontal bar chart.

3.02 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Identify work of separate stages and other logically grouped activities.

D. Provide sub-schedules to define critical portions of the entire schedule.

E. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

F. Provide separate schedule of submittal dates for shop drawings, product data, and samples, owner-furnished products, products identified under Allowances, and dates reviewed submittals

01 3216 - 2

DALLIS STREET REROOF

SECTION 013216 –

will be required from Architect. Indicate decision dates for selection of finishes.

G. Provide legend for symbols and abbreviations used.

01 3216 - 3

DALLIS STREET REROOF

SECTION 013216 –

3.03 NETWORK ANALYSIS

A. Prepare network analysis diagrams and supporting mathematical analyses using the Critical

Path Method.

B. Illustrate order and interdependence of activities and sequence of work; how start of a given activity depends on completion of preceding activities, and how completion of the activity may restrain start of subsequent activities.

C. Mathematical Analysis: Tabulate each activity of detailed network diagrams, using calendar dates, and identify for each activity:

1. Preceding and following event numbers.

2. Activity description.

3. Estimated duration of activity, in maximum 15 day intervals.

4. Earliest start date.

5. Earliest finish date.

6. Actual start date.

7. Actual finish date.

8. Latest start date.

9. Latest finish date.

10. Total and free float; float time shall accrue to Owner and to Owner's benefit.

11. Monetary value of activity, keyed to Schedule of Values.

12. Percentage of activity completed.

13. Responsibility.

D. Analysis Program: Capable of compiling monetary value of completed and partially completed activities, accepting revised completion dates, and recomputation of all dates and float.

E. Required Reports: List activities in sorts or groups:

1. By preceding work item or event number from lowest to highest.

2. By amount of float, then in order of early start.

3.04 REVIEW AND EVALUATION OF SCHEDULE

A. Participate in joint review and evaluation of schedule with Architect at each submittal.

B. Evaluate project status to determine work behind schedule and work ahead of schedule.

C. After review, revise as necessary as result of review, and resubmit within 10 days.

3.05 UPDATING SCHEDULE

A. Maintain schedules to record actual start and finish dates of completed activities.

B. Indicate progress of each activity to date of revision, with projected completion date of each activity.

C. Annotate diagrams to graphically depict current status of Work.

D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.

E. Indicate changes required to maintain Date of Substantial Completion.

F. Submit reports required to support recommended changes.

G. Provide narrative report to define problem areas, anticipated delays, and impact on the schedule. Report corrective action taken or proposed and its effect.

3.06 DISTRIBUTION OF SCHEDULE

A. Distribute copies of updated schedules to Contractor's project site file, to subcontractors, suppliers, Architect, Owner, and other concerned parties.

01 3216 - 4

DALLIS STREET REROOF

SECTION 013216 –

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

SECTION 014000 – QUALITY

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for

SECTION 01 4000 QUALITY REQUIREMENTS

1.01 SECTION INCLUDES

A. Submittals.

B. Testing and inspection agencies and services.

C. Control of installation.

D. Mock-ups.

E. Tolerances.

F. Manufacturers' field services.

G. Defect Assessment.

1.02 RELATED REQUIREMENTS

A. Section 01 3000 - Administrative Requirements: Submittal procedures.

B. Section 01 4219 - Reference Standards.

C. Section 01 6000 - Product Requirements: Requirements for material and product quality.

1.03 REFERENCE STANDARDS

A. ASTM C1021 - Standard Practice for Laboratories Engaged in Testing of Building Sealants;

2008 (Reapproved 2014).

B. ASTM C1077 - Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation; 2014.

1.04 DELEGATED DESIGN

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.

1.05 QUALITY ASSURANCE

A. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

B. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927) manufacturer's products that are similar in material, design, and extent to those indicated for this

Project.

C. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

D. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance.

E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.

F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirement for specialists shall not supersede building codes and similar regulations governing the Work, nor interfere with local trade-union jurisdictional settlements and similar conventions.

1.06 SUBMITTALS

A. See Section 01 3000 - Administrative Requirements, for submittal procedures.

B. Design Data: Submit for Architect's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the contract documents, or for Owner's information.

C. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional, indicating that the products and systems are in compliance with performance and design criteria indicated. Include list of codes, loads, and other factors used in performing these services.

D. Schedule of Tests and Inspections: Prepare in tabular form and include the following:

1. Specification Section number and title.

2. Description of test and inspection.

3. Identification of applicable standards.

4. Identification of test and inspection methods.

5. Number of tests and inspections required.

6. Time schedule or time span for tests and inspections.

7. Entity responsible for performing tests and inspections.

8. Requirements for obtaining samples.

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

9. Unique characteristics of each quality-control service.

E. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

F. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Architect, in quantities specified for Product Data.

1. Indicate material or product complies with or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

2. Certificates may be recent or previous test results on material or product, but must be acceptable to Architect.

G. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the

Owner's information. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.

H. Manufacturer's Field Reports: Submit reports for Architect's benefit as contract administrator or for Owner.

1. Submit report in duplicate within 30 days of observation to Architect for information.

2. Submit for information for the limited purpose of assessing compliance with information given and the design concept expressed in the contract documents.

I. Erection Drawings: Submit drawings for Architect's benefit as contract administrator or for

Owner.

1. Submit for information for the limited purpose of assessing compliance with information given and the design concept expressed in the contract documents.

2. Data indicating inappropriate or unacceptable Work may be subject to action by Architect or Owner.

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

1.07 REFERENCES AND STANDARDS

A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.

C. Obtain copies of standards where required by product specification sections.

D. Maintain copy at project site during submittals, planning, and progress of the specific work, until

Substantial Completion.

E. Should specified reference standards conflict with Contract Documents, request clarification from Architect before proceeding.

F. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Architect shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.08 TESTING AND INSPECTION AGENCIES AND SERVICES

A. Owner will employ and pay for services of an independent testing agency to perform other specified testing.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

PART 2 PRODUCTS - NOT USED PART 3 EXECUTION

3.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from

Architect before proceeding.

D. Comply with specified standards as minimum quality for the work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.02 MOCK-UPS

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

A. Tests shall be performed under provisions identified in this section and identified in the respective product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Architect and is specified in product specification sections to be removed, protect mock-up throughout construction, remove mock-up and clear area when directed to do so by Architect.

3.03 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work.

Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract

Documents, request clarification from Architect before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

3.04 TESTING AND INSPECTION

A. See individual specification sections for testing required.

B. Testing Agency Duties:

1. Test samples of mixes submitted by Contractor.

2. Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services.

3. Perform specified sampling and testing of products in accordance with specified standards.

4. Ascertain compliance of materials and mixes with requirements of Contract Documents.

5. Promptly notify Architect and Contractor of observed irregularities or non-compliance of

Work or products.

6. Perform additional tests and inspections required by Architect.

7. Attend preconstruction meetings and progress meetings as requested.

8. Submit reports of all tests/inspections specified.

C. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

D. Contractor Responsibilities:

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Architect and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Arrange with Owner's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

E. Re-testing required because of non-compliance with specified requirements shall be performed by the same agency on instructions by Architect.

F. Re-testing required because of non-compliance with specified requirements shall be paid for by

Contractor.

3.05 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust, and balance equipment as applicable, and to initiate instructions when necessary.

Copyright © 2024 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.

It was created by "2WR" for "TROUP COUNTY GA 900 DALLIS STREET REROOF". A valid, current MasterSpec license is required for editing and use of this document for any other project.(23927)

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

3.06 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not complying with specified requirements.

B. If, in the opinion of Architect, it is not practical to remove and replace the work, Architect will direct an appropriate remedy or adjust payment.

3.07 REPAIR AND PROTECTION

A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Sections of these Specifications. Restore patched areas and extend restoration into adjoining areas in a manner that eliminates evidence of patching.

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

01 5000 - 1 TEMPORARY FACILITIES AND

CONTROLS

TROUP COUNTY GA 900

DALLIS STREET REROOF

SECTION 015000 –

FACILITIES AND CONTROLS

INCLUDES

SECTION 01 5000 TEMPORARY

FACILITIES AND CONTROLS

A. Temporary sanitary facilities.

B. Temporary Controls: Barriers, enclosures, and fencing.

C. Security requirements.

D. Vehicular access and parking.

E. Waste removal facilities and services.

1.02 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.

B. Maintain daily in clean and sanitary condition.

1.03 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Provide barricades and covered walkways required by governing authorities for public rights-of-way and for public access to existing building.

C. Provide protection for plants designated to remain. Replace damaged plants.

D. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.04 VEHICULAR ACCESS AND PARKING

A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.

B. Coordinate access and haul routes with governing authorities and Owner.

C. Provide and maintain access to fire hydrants, free of obstructions.

D. Provide means of removing mud from vehicle wheels before entering streets.

E. Designated existing on-site roads may be used for construction traffic.

F. Existing parking areas located at may be used for construction parking.

1.05 WASTE REMOVAL

A. See Section 01 7419 - Construction Waste Management and Disposal, for additional requirements.

B. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

C. Provide containers with lids. Remove trash from site weekly.

D. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.06 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

01 5000 - 2 TEMPORARY FACILITIES AND

CONTROLS

TROUP COUNTY GA 900

DALLIS STREET REROOF

SECTION 015000 –

FACILITIES AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Date of

Substantial Completion inspection.

B. Clean and repair damage caused by installation or use of temporary work.

C. Restore existing facilities used during construction to original condition.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01 6000 - 1 PRODUCT REQUIREMENTS

DALLIS STREET REROOF

SECTION 016000 – PRODUCT

INCLUDES

SECTION 01 6000

PRODUCT

REQUIREMENTS

A. General product requirements.

B. Re-use of existing products.

C. Transportation, handling, storage and protection.

D. Product option requirements.

E. Substitution limitations.

F. Procedures for Owner-supplied products.

G. Maintenance materials, including extra materials, spare parts, tools, and software.

1.02 RELATED REQUIREMENTS

A. Section 01 2500 - Substitution Procedures: Substitutions made during procurement and/or construction phases.

B. Section 01 4000 - Quality Requirements: Product quality monitoring.

C. Section 01 7419 - Construction Waste Management and Disposal: Waste disposal requirements potentially affecting product selection, packaging and substitutions.

1.03 REFERENCE STANDARDS

A. NFPA 70 - National Electrical Code; Most Recent Edition Adopted by Authority

Having Jurisdiction, Including All Applicable Amendments and Supplements.

1.04 SUBMITTALS

A. Proposed Products List: Submit list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.

1. Submit within 15 days after date of Notice to Proceed.

2. For products specified only by reference standards, list applicable reference standards.

B. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

C. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

D. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.

PART 2 PRODUCTS

2.01 EXISTING PRODUCTS

A. Do not use materials and equipment removed from existing…