This document is a Craft Information Book volume detailing towing procedures for a YRBM (Yard Repair Boat Modular) vessel. The document provides comprehensive instructions for preparing the craft for towing, including critical pre-towing steps such as disconnecting all shore station connections, securing various onboard systems (HVAC, chilled water, refrigeration, potable water, sewage, communications, and electrical systems), and installing transit covers on windows, doors, and ventilators.

The towing procedures outline specific technical requirements, including inspecting towing equipment for damage, removing chain gates that interfere with towing, connecting towing bridle and cable according to NAVSEA drawing 582-8921104, establishing communications between towing personnel, and hoisting day shapes and towing lights. The document emphasizes critical warnings about proper equipment preparation to prevent mission effectiveness loss or equipment damage, and references the U.S. Navy Towing Manual for final towing guidance. The procedures are designed to ensure the vessel's stability, directional control, and compliance with ABS (American Bureau of Shipping) directives during offshore towing operations.

View the file

Other files for this federal contract opportunity

Other files attached to TUGCON Voyage Charter, newest first.
File Type Posted
Mooring_Towing Foundation.pdf PDF
Mooring_Towing Arrangement.pdf PDF
Topside Arrangement.pdf PDF
General Arrangement.pdf PDF
25R4075 RFP.pdf PDF
2015-0213 Rev. 37.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CRAFT INFORMATION BOOK VOLUME 1 OF 2

1-3 OUTFITTINGS

1-3.7. TOWING PROCEDURES. The YRBM was designed with towing resistance, intact/damage stability, draft and trim requirements and directional stability in mind.

The Transit Covers on the Windows, Doors and Ventilators must be installed and remain in place when the vessel is being towed offshore to conform to ABS requirements. Portable Temporary Transit Covers use stainless steel type 316 bolting hardware. Refer to NAVSEA drawing 167-8921130 Structural Closures for Transit in CIB Volume 2, for further information of the Transit Covers.

Refer to NAVSEA Drawing 582-8921104, Mooring and Towing Equipment Arrangement and Details, for further details and the preparation and arrangement of the Craft’s towing lines.

TOWING THE CRAFT

Ensure all systems are disconnected from the shore connections prior to towing the Craft.

Failure to remove shore station connections can result in equipment damage or loss of mission effectiveness.

Ensure all Doors, Windows, and Portable Temporary Transit Covers are in place prior to the Craft being towed. Failure to place the covers prior to getting underway can result in equipment damage or loss of the Craft.

Ensure the Navigational Lights are energized prior to towing the Craft in accordance with ABS directives.

Prepare the craft for towing in accordance with the following procedures:

1. Secure the HVAC system in accordance with paragraph 2-1.3.

2. Secure the Chilled Water System in accordance with paragraph 2-2.3.

3. Secure the Refrigeration System in accordance with paragraph 2-3.3.

4. Secure the Potable Water System and disconnect shore station line in accordance with paragraph 2-4.3.

5. Secure the Sewage System and disconnect shore station line in accordance with paragraph 2-5.3.

6. Secure the Firemain System and disconnect shore station line in accordance with paragraph 2-6.3.

7. De-energize Telephone System and disconnect shore station line in accordance with paragraph 4-1.3.

8. De-energize General Announcing System in accordance with paragraph 4-2.3.

9. De-energize Computer Network LAN and disconnect shore station in accordance with paragraph 4-4.3.

10. De-energize Entertainment System and disconnect shore station line in accordance with paragraph 4-5.3.

11. De-energize Video Surveillance System in accordance with paragraph 4-6.3.

12. De-energize Centralized Alarm System in accordance with paragraph 4-7.3.

13. De-energize Fire Alarm/Detection System in accordance with paragraph 4-8.3.

14. De-energize the Main Switchboard in accordance with paragraph 3-2.1.

15. De-energize and disconnect the Shore Power Cables in accordance with paragraph 3-2.1.

16. Install all Transit Covers.

17. Raise the brow from the quarterdeck to pier and stow.

18. Rig all stanchions, chain gates and lifelines.

Tow the craft in accordance with the following procedures:

1. Inspect towing cable and towing bridle prior to each use for signs of damage.

2. Inspect all Bitts, Chocks and Towing Padeyes for signs of corrosion and cracks.

3. Remove chain gates that interfere with any towing equipment and fittings.

4. Connect towing bridle flounder plate and towing cable in accordance with 582-8921104, Mooring and Towing Equipment Arrangement and Details.

5. Connect towing bridle to towing padeye in accordance with 582-8921104, Mooring and Towing Equipment Arrangement and Details.

6. Establish communications between designated towing personnel.

7. Hoist day shapes and energize towing lights as required.

8. Tow craft in accordance with latest revision of NAVSEA Drawing 582-8921104, Mooring and Towing Equipment Arrangement and Details, and U.S. Navy Towing Manual, NAVSEA SL740-AA-MAN-010.