TO 2 PWS Attch 2 Homestead Base Spec Req Central South vf2.docx
DOCX document 51 KB Posted
- Attached to
- BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region Federal contract opportunity
- Solicitation number
- FA890320R0010
About this file
This document provides the performance work statement for the Base Realignment and Closure Environmental Construction and Optimization Services Central South Region contract opportunity. The contractor will be required to conduct cleanup activities at the former Homestead Air Force Base in Homestead, Florida, including investigating and removing an oil water separator, preparing completion reports, and submitting quarterly and annual reports. The contractor must also attend Base Cleanup Team meetings, participate in monthly teleconferences, and conduct annual land use control monitoring and five-year review reports. Relevant documents include the Federal Facility Agreement and records of decision for various sites. No additional computer systems or site access requirements are specified beyond the performance work statement.
View the file
Other files for this federal contract opportunity
Show all 50
BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4890-06-R-9999
Attachment 1
APRIL XX, 2009
- final – fa8903-20-r-0010 to 2 Attachment 2 Central South Region - Homestead 5 December 2019
1.1 Scope
The former Homestead Air Force Base (AFB) is located in Homestead, Florida. Homestead AFB was closed on 31 March 1994. Whole-base transfer completed in 2006. A total of 1,962 acres were retained by the Department of Defense for operation of Homestead Air Reserve Base and some acreage was transferred to other federal agencies. The remainder of the property was transferred to Miami-Dade County.
The former Homestead AFB is listed on the National Priorities List.
In addition to the requirements presented in this PWS, this scope includes the following:
· The Contractor shall investigate and remove/dispose of the Oil Water Separator (OWS) discovered at OU-28 in accordance with Chapter 62-780 of the Florida Administrative Code and/or other applicable regulations. The Contractor shall prepare a Remedial Action Completion for OWS at OU-28.
· The Contractor shall prepare and submit Quarterly Progress Reports for all sites, in accordance with Section XII of Federal Facility Agreement between United States Environmental Protection Agency – Region IV, State of Florida, and the United States Department of the Air Force for Homestead AFB, Homestead, FL.
· The Contactor shall prepare and submit an annual Site Management Plan for all sites, in accordance with Section XXIII of the Federal Facility Agreement between United States Environmental Protection Agency – Region IV, State of Florida, and the United States Department of the Air Force for Homestead AFB, Homestead, FL.
Contractors are not responsible for the following:
· No base-specific requirements in addition to those in the PWS.
1.3 Applicable Documents
Key Documents
| Entry No. |
| Document Title |
| Location |
| Date Issued |
| 1. |
| Federal Facility Agreement Between United States Environmental Protection Agency – Region IV, State of Florida, and the United States Department of the Air Force for Homestead AFB, Homestead, FL |
| AR# 1158 |
| May 1990 |
| 2. |
| Final Record of Decision for OU-18, OU-26, OU-28, and OU-29, Former Homestead AFB, FL |
| AR#1280 |
| October 1998 |
| 3. |
| Final Record of Decision for OUs 20/21, OU-30, and OU-31, Former Homestead AFB, FL |
| AR#4071 |
| May 2006 |
| 4. |
| Final Explanation of Significant Differences, OT022/OU-26, OT024/OU-28, and OT026/OU-29, Former Homestead AFB, Homestead, FL |
| AR#4179 |
| September 2013 |
| 5. |
| Hazardous and Solid Waste Amendment |
Corrective Action Permit Number 72438-HH-002, Homestead Air Reserve Base, FL
| AR# 577039 |
| September 2016 |
| 6. |
| Final Proposed Plan for SS026/Operable Unit-14, Former Homestead AFB |
| AR# 569436 |
| January 2018 |
| 7. |
| Final Focused Feasibility Study for SS026/OU-14, Former Homestead AFB, Miami-Dade County, FL |
| AR# 573954 |
| June 2018 |
| 8. |
| Final Record of Decision for SS026/Operable Unit 14, Former Homestead AFB, FL |
| AR#589068 |
| June 2019 |
| 9. |
| Final Site Management Plan for Fiscal Year 2020, Former Homestead AFB, Homestead, FL |
| Google Drive |
| August 2019 |
| 10. |
| Conditional Site Rehabilitation Completion Order for COW006, Former Homestead AFB, FL |
| Google Drive |
| October 2019 |
1.4 Work Ramp-Up and Transition
Transition of Work
| Contract No. |
| Project Name |
| Field Support |
Complete Reporting Complete
| FA8903-09-D-8565-0007 |
| Performance-Based Remediation at Former Bergstrom AFB, TX, Former Carswell AFB, TX, Former Eaker AFB, AR, Former Homestead AFB, FL, Former Richards-Gebaur AFB, MO |
| 9/24/2020 |
| 9/24/2020 |
2.6.1 Meeting/Teleconference Support
· The Contractor shall attend and participate in the Base Cleanup Team (BCT) Meeting for Former Homestead AFB. The Homestead BCT is typically held at Homestead Air Reserve Base, FL, on a semi-annual basis.
· The Contractor participate in Teleconferences with the United States Air Force (USAF) representatives to discuss the progress toward accomplishing project objectives. Currently, teleconferences are held on a monthly basis.
2.6.2 Public Meetings and Hearings
· No base-specific requirements in addition to those in the PWS.
2.6.5 Site Access: Permits, Easements, and Work Site Access
· No base-specific requirements in addition to those in the PWS.
3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates
· No base-specific requirements in addition to those in the PWS.
6.14 Land Use Controls (LUC)
· The Contractor shall conduct LUC/IC monitoring for sites identified in Attachment 1 and prepare a report. Currently, LUC/IC monitoring is held on an annual basis.
6.15 Five-Year Reviews
· The Contractor shall prepare a Five-Year Review Report for sites identified in Attachment 1. The next Five-Year Review Report is due September 2021.