IDIQ PWS Attch 3 Central South Del Rev Process BECOS vf2.docx
DOCX document 42 KB Posted
- Attached to
- BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region Federal contract opportunity
- Solicitation number
- FA890320R0010
About this file
This document outlines a deliverable review process for a federal contract. It details the review tasks, timeframes, and scope for contractor-prepared documents related to Base Realignment and Closure environmental construction and optimization services in the Central South region. The Air Force and regulatory agencies will review working drafts and provide comments within 30 days or 7 days as specified. The contractor will incorporate comments, obtain additional regulatory review, and submit final documents for regulatory acceptance. Actual review times may vary based on other agreements and workload.
View the file
Other files for this federal contract opportunity
Show all 50
BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8903-20-R-0010
Central South Region Attachment 3 5 December 2019
Deliverable Review Process Air Force Contractor Regulators Task: Prepare working copy document.
Timeframe: Dependent on task Scope: Dependent on task Task: Review working copy document.
Timeframe: 30 calendar days (max) Scope: Comments will focus on regulatory, factual, technical, and legal issues and should not conflict with the terms and conditions of the contract (e.g., directing the contractor on approach).
Tasks: Incorporate review comments. Prepare submittal letter.
Timeframe: Dependent on task Scope: Evaluate and incorporate all regulatory, factual, technical, and legal Air Force comments that do not conflict with the terms and conditions of the contract.
Task: Review draft document and sign submittal letter if document is acceptable. Return for further revisions if required.
Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.
Task: Obtain regulatory review of draft document.
Timeframe: TBD Scope: Distribute submittal letter and document to regulators. Provide copies to the Air Force.
Task: Provide regulatory review.
Timeframe: FFA/DSMOA/Circumstantial Scope: Provide regulatory review of submitted document.
Tasks: Resolve comments and revise document. Prepare submittal letter.
Timeframe: TBD Scope: Provide timely evaluation and resolution of regulatory comments with a goal of meeting predetermined objectives.
Task: Submit final document.
Timeframe: TBD Scope: Submit final document for regulatory acceptance/concurrence.
Task: Review final document and sign submittal letter if document is acceptable. Return for further revisions if required.
Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.
Task: Accept final document.
Timeframe: FFA/DSMOA/Circumstantial Scope: Accept final document and provide written notice.
Note: This is a generic document review process for this contract. Actual review times will be based on the Federal Facility Agreement (FFA) where applicable or the Joint Execution Plan (JEP) and associated schedules developed under the Defense State Memorandum of Agreement (DSMOA). Agencies reviewing the document may make specific requests based on complexity of the deliverable or work load of their technical review team that impact review timelines. Depending on the document, there may or may not be a draft version or there may be multiple draft versions.
File details come from the government source that posted it. Updated .