TO 2 CDRLs Exhibit A B Galena BECOS vf1.docx
DOCX document 15 KB Posted
- Solicitation number
- FA8903-20-R-0012
About this file
This document outlines the contract data requirements list (CDRL) for Technical Order 2 under the Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) Galena Region contract opportunity. The contractor will be required to provide various scientific and technical reports, management plans, progress reports, technical data packages, presentation materials, and meeting minutes on a recurring basis throughout contract performance. Key deliverables include an initial project management plan with annual revisions, monthly progress reports, environmental sampling and analysis plans, quality system plans, and technical and management work plans. The CDRL specifies the paragraph references in the performance work statement that relate to each required deliverable and outlines the required submission frequency.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8903-20-R-0012 TO 2
Galena REGION 5 December 2019
| CDRL |
| Title |
| PWS Paragraphs |
| Frequency |
| A001 |
| SCIENTIFIC AND TECHNICAL REPORTS |
| 1.5, 2.2, 2.3, 2.6.2-2.6.5, 2.9, 2.10, 3.1.2, 3.3.1, 4.1-4.3, 4.5, 5.1, 5.3, 5.6, 5.6.1, 6.11, 6.13 |
| TBD |
| A003 |
| REPORT, PRODUCTION OR DELIVERY PROBLEMS |
| 2.6.4 |
| As required |
| A004 |
| SCIENTIFIC AND TECHNICAL REPORTS – OSHA REPORTS |
| 2.7 |
| As required |
| A005 |
| TECHNICAL DATA PACKAGE - GIS |
| 3.4 |
| TBD |
| A006 |
| TECHNICAL DATA PACKAGE – CADD |
| 3.4 |
| TBD |
| A007 |
| ENVIRONMENTAL CLEANUP PLAN - PROJECT ACTIVITIES (WP, QAPP, OPTIMIZATION PLANS, etc.) |
| 3.1.1, 3.2.1, 3.3 |
| TBD |
| A008 |
| ENVIRONMENTAL HEALTH AND SAFETY PLAN - QUALITY PROGRAM PLAN - PART 1 |
| 3.2.2, 3.3, 5.6, 5.6.1 |
| TBD |
| A009 |
| ENVIRONMENTAL SAMPLING AND ANALYSIS PLAN - QUALITY PROGRAM PLAN - PART 2 |
| 3.2.3, 3.3 |
| TBD |
| A010 |
| QUALITY SYSTEM PLAN - CONSTRUCTION QUALITY PLAN |
| 3.2.4 |
| TBD |
| A012 |
| TECHNICAL AND MANAGEMENT WORK PLAN – WORK PLAN |
| 3.3.3 |
| TBD |
| A013 |
| AS BUILT DRAWINGS |
| 3.1.1, 3.2.1, 5.1, 5.3 |
| TBD |
| B002 |
| MANAGEMENT PLAN - PROJECT MANAGEMENT PLAN |
| 2.2 |
| Initially w/ annual revisions thereafter |
| B003 |
| CONTRACTOR PROGRESS, STATUS AND MANAGEMENT REPORT |
| 2.4 |
| Monthly |
| B004A |
| TECHNICAL DATA PACKAGE – ERPIMS (SCHEDULE) |
| 3.3.4 |
| TBD |
| B004B |
| TECHNICAL DATA PACKAGE – ERPIMS (DATA PACKAGE) |
| 3.3.4 |
| Per B004A and as required |
| B005 |
| PRESENTATION MATERIALS |
| 2.6.1, 2.6.2, 2.6.3 |
| As required |
| B006 |
| CONFERENCE AGENDA |
| 2.6.1, 2.6.2, 2.6.3 |
| As required |
| B007 |
| CONFERENCE MINUTES |
| 2.6.1, 2.6.2, 2.6.3 |
| As required |
File details come from the government source that posted it. Updated .