This document provides details on a Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) solicitation for the Galena Region in Alaska. The solicitation seeks contractors to provide environmental remediation and long-term monitoring services at 38 active sites on Galena Air Force Base. Required services include operation and maintenance of existing remediation systems, groundwater monitoring, land use control inspections, and five-year reviews. Projected completion dates for ongoing remedial actions range from fiscal year 2026 to fiscal year 2043. The solicitation is being issued by the Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency. An Indefinite Delivery Indefinite Quantity (IDIQ) multiple award contract structure will be utilized, with individual task orders issued on both a fixed price and cost reimbursement basis.
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Galena
| Region | Base | Site ID | Site Name | Site Alias | Operable Unit (OU) | Regulatory Program | Site Phase | Current Remedy | Notes | Projected | |
| RC Date | Projected |
SC Date Galena Galena CG001 Million Gallon Hill ADEC RA-O Horizontal well air sparging system for CG001 and CG002 installed in 2017 and one small vertical well air sparging system (CG001 only) installed in 2018 will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews
| CG001 and CG002 have been combined into one Cleanup Plan | FY40 | FY40 | |||||||
| Galena | Galena | CG002 | Missile Storage Area | ADEC | RA-O | Horizontal well air sparging system for CG001 and CG002 installed in 2017 will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews | CG001 and CG002 have been combined into one Cleanup Plan. Note that AF is pursuing administrative closure for the CG002 source area. | FY40 | FY40 |
| Galena | Galena | CB001 | Galena Aviation Vocation Technical Center | ADEC | RA-O | Horizontal well air sparging system for ST005 and CB001 installed in 2017 will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews |
| Sub slab depressurization/ SVE system at GAVTC building (CB001) and vapor mitigation system at Building 191 (ST005) operate when horizontal well system is on and will also require O&M | ST005 and CB001 have been combined into one Cleanup Plan. Note that AF is pursuing administrative closure for CB001. | FY35 | FY35 | ||||
| Galena | Galena | ST005 | POL Tank Farm | ADEC | RA-O | Horizontal well air sparging system for ST005 and CB001 installed in 2017 and one small SVE system (ST005 Area C) installed in 2018 will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews |
Sub slab depressurization/ SVE system at GAVTC building (CB001) and vapor mitigation system at Building 191 (ST005) operate when horizontal well system is on and will also require O&M ST005 and CB001 have been combined into one Cleanup Plan.
| Current PBR contractor is closing ST005 Area D. | FY35 | FY35 | |||||||||
| Galena | Galena | ST009 | West Unit JP-4 Fuel Stands | ADEC | RA-O | Ongoing O&M of SVE system installed in 2016, GW monitoring, LUC inspections, and Five-Year Reviews. Sulfate injections conducted in 2017 | FY33 | FY33 | |||
| Galena | Galena | ST010 | Southeast Runway Fuel Spill | ADEC | RA-O | Ongoing O&M of bioventing system installed in 2017 and expanded in 2018, GW monitoring, LUC inspections, and Five-Year Reviews | FY35 | FY35 | |||
| Galena | Galena | SS005 | Wilderness Hall (Bldg 1872) | ADEC | RA-O | Ongoing O&M of SVE installed in 2016, GW monitoring, LUC inspections, and Five-Year Reviews | FY28 | FY28 | |||
| Galena | Galena | SS016 | Building 2541 – Former POL Fuel Lab | ADEC | RA-O | Ongoing O&M of bioventing system installed in 2017, GW monitoring, LUC inspections, and Five-Year Reviews | FY36 | FY36 | |||
| Galena | Galena | SS017 | Former Truck Fillstands | ADEC | RA-O | Ongoing O&M of bioventing system installed in 2017 and expanded in 2018, GW monitoring, LUC inspections, and Five-Year Reviews. Sulfate injections conducted in 2017. | SS014 and SS017 have been combined into one Cleanup Plan. Closure of SS014 source area recommended in 2018 Construction Completion Report and is in process. | FY43 | FY43 | ||
| Galena | Galena | CSS002 | Building 1812 Former Hazardous Waste Satellite Accumulation Point | B1812 | ADEC | RA-O | Ongoing O&M of bioventing system installed in 2017, GW monitoring, LUC inspections, and Five-Year Reviews. Excavation conducted in 2015. Sulfate injections conducted in 2017. | FY35 | FY35 | ||
| Galena | Galena | TU001 | Power Plant Tank 49 | ADEC | RA-O | Ongoing O&M of vertical well air sparging system and SVE system installed in 2016, GW monitoring, LUC inspections, and Five-Year Reviews | FY32 | FY32 | |||
| Galena | Galena | CPL006 | Old Abandoned Pipeline | OAP | ADEC | RA-O | Ongoing O&M of bioventing system at Area 3 installed in 2017 and expanded in 2018, GW monitoring, LUC inspections, and Five-Year Reviews | Current PBR contractor will complete remediation at Area 2 and no further action is required at Areas 1 and 4. Current PBR contractor evaluating options to recover NAPL in one well during low groundwater. | FY36 | FY36 | |
| Galena | Galena | CST011 | Combat Alert Cell USTs | UST1428 | ADEC | RA-O | Ongoing GW monitoring at Area 2, LUC inspections, and Five-Year Reviews | FY28 | FY28 | ||
| Galena | Galena | CST014 | Dining Facility UST | UST1859 | ADEC | RA-O | Ongoing O&M of vertical well air sparging system and SVE system installed in 2016, GW monitoring, LUC inspections, and Five-Year Reviews | FY33 | FY33 | ||
| Galena | Galena | FT001 | Fire Protection Training Area | CERCLA | RA-O | Bioventing system installed in 2018 with plastic liner/soil cover over former fire training pit will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews | Remedy is under an interim ROD. ADEC will not close site until PFAS are addressed. | FY36 | FY36 | ||
| Galena | Galena | SS006 | TCE Area (Bldg 1845) | CERCLA | RA-O | SVE system installed in 2018 with startup and operation in summer 2019 will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews. Enhanced bioremediation injections conducted in 2018. | SS006, SS019, and solvent-contamination previously associated with S1850 have been combined into one Cleanup Plan. Solvent contamination in groundwater associated with SS006 has migrated beneath SS019, SS018, and CSS002, and is included in SS006. | FY38 | FY38 | ||
| Galena | Galena | SS015 | South Apron Maintenance Area | CERCLA | RA-O | SVE system installed in 2018 will require O&M, GW monitoring, LUC inspections, and Five-Year Reviews. Enhanced bioremediation injections conducted in 2018. | FY35 | FY35 | |||
| Galena | Galena | SS018 | Waste Accumulation Area - South of Bldg 1499 | AOC023 | CERCLA | RA-O | Monitoring well installation completed in 2018. Post-excavation requirements include GW monitoring, LUC inspections, and Five-Year Reviews | FY27 | FY27 | ||
| Galena | Galena | SS019 | Building 1700 – Refueler Maintenance Shop | CERCLA | RA-O | Pilot test SVE system installed in 2015 is final remedy and requires O&M, GW monitoring, LUC inspections, and Five-Year Reviews. Primary contamination is petroleum and small area of solvents at former dry well. | SS006, SS019, and solvent-contamination previously associated with S1850 have been combined into one Cleanup Plan. Solvent contamination in groundwater associated with SS006 has migrated beneath SS019, SS018, and CSS002, and is included in SS006. |
| Closure of drywell to be completed by the current PBR contractor. | FY31 | FY31 | ||||||||
| Galena | Galena | SS022 | Building 400 Former CAA- Air Force Weather Station | B400 | CERCLA | RA-O | Pilot test SVE system installed in 2015 and expanded in 2017 is final remedy and requires O&M, GW monitoring, LUC inspections, and Five-Year Reviews | FY26 | FY26 | |
| Galena | Galena | DP023 | Former Disposal Site West of Dike | DSWD | CERCLA | RA-O | GW monitoring, LUC inspections, and Five-Year Reviews. |
| Excavation conducted in 2019. Results are pending. | FY39 | FY39 | ||||
| Galena | Galena | FT001 | Fire Protection Training Area | PFAS Site | ||
| Galena | Galena | CG109 | AFFF Release Areas | PFAS Site | ||
| Galena | Kulis | CAT56P | PFC Research Site | PFAS Site | ||
| Galena | Galena | CS001 | Contaminated Sediments (Soils) | TBD | ||
| Galena | Galena | SS025 | West Perimeter Road TCE Spill | TBD | ||
| Galena | Galena | SS107 | Northern Tar Area | TBD | ||
| Galena | Galena | SS108 | Southern Tar Area | TBD | ||
| Galena | Galena | DP106 | Disposal Site | TBD |