This is a combined synopsis CGC HAMILTON FIRE PUMP.docx

DOCX document 34 KB Posted

Attached to
USCGC HAMILTON FIRE PUMP REQUEST Federal contract opportunity
Solicitation number
70Z08525Q0029251
Issued by
Department of Homeland Security US Coast Guard

About this file

This is a combined synopsis/solicitation for a United States Coast Guard (USCG) contract to replace a fire pump on the USCGC HAMILTON. The solicitation (RFQ 70Z08525Q0029251) is a small business set-aside for a firm-fixed-price commercial item procurement, with an estimated unit cost of $50,500 for a fire pump assembly. The specific requirements include removing the existing fire pump, preparing the foundation, installing a government-furnished fire pump assembly (5x4x10 Carver Pump Co. model), reconnecting electrical and piping systems, and performing operational testing.

The contract will be executed during a 14-day availability period from September 14-28, 2025, with work to be performed at the Federal Law Enforcement Training Center in Charleston, SC. Contractors must have a valid US driver's license, no felony convictions, and will be sponsored and escorted by a Coast Guard representative. Responses are due by 0800 Pacific Time on August 21, 2025, with work to be coordinated with the Cutter's Engineering Officer and performed in conjunction with a cofferdam installation.

View the file

Other files for this federal contract opportunity

Other files attached to USCGC HAMILTON FIRE PUMP REQUEST, newest first.
File Type Posted
SOW-70Z08525Q0029251-UPDATED AUG18 2025.doc DOC document
SOW.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This is a combined synopsis/solicitation for commercial items/services prepared in accordance with the format in FAR Subpart 12.6 as supplemented with additional information included in this notice. Request for Quotations number is 70Z08525Q0029251 and is issued as a request for quotations (RFQ). This announcement constitutes the only solicitation; quotations are being requested, and a written solicitation will not be issued. This Request for Quotations incorporates provisions and clauses in effect through Federal Acquisition Circular 2005-65 dated January 29, 2013. The NAICS Code is 336611. The small business size standard is 1250. This is a totally small business set aside. All responsible sources may submit proposals that will be considered by the agency. The contract will be awarded on a firm-fixed-price basis using simplified acquisition procedures in accordance with FAR Part 13.5. All responses from interested vendors must be received on/before 0800 Pacific Time, Augusth 21st, 2025 and will be reviewed by the Government.

The United States Coast Guard Surface Force Logistics Center has a requirement for the following:

The CTR shall provide parts requested for USCGC HAMILTON a fire Pump Purchase

CTR shall provide the following:

nt. This work item describes the requirements for the Contractor to renew Fire Pump Assembly listed in Table 1.

table 1: Fire pump data

EQUIPMENT
model number/MANUFACTURER
Location

Fire Pump No. 5 Assembly (51 Inch X 33 Inch X 27 Inch) Approximate Weight 2450 Lbs. (Figure 2 For Reference)

5 X 4 -10 / Carver Pumps Co.
Pump Room #2,

(5-70-01-E)

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST\($/UNIT)
Y
Fire Pump Assembly with Suction Assembly (5X4X10 Pump), Carver Pump Co. and 125 HP, 1760 RPM, 450 Volt AC, Three Phase, 60 Hz, Totally Enclosed Fan Cooled, Manufacturer Reliance Electric Co.
01-561-8775
1
$50,500.00

2. REFERENCES

Coast Guard Drawings Coast Guard Drawing 418A-WMSL-100-001, Rev L, General Arrangements Coast Guard Drawing 418A-WMSL-801-004, Rev B, Booklet of General Plans Coast Guard Drawing 750-WMSL-101-027, Rev -, Equipment Removal Route Drawing NSC3 & Follow (AS3101009) Coast Guard Drawing 750-WMSL-320-041, Rev C, Electrical One Line Diagram (NSC4 - SRD) (ASC320001D) (UNSIGNED) Coast Guard Drawing 750-WMSL-521-047, Rev -, Firemain Diagram NSC4 (ASC521001D) Coast Guard Drawing 750-WMSL-180-012, Rev H, Foundation Arrangement Drawing Design Unit 2110 BKLT No.1 Coast Guard Drawing 750-WMSL-521-26, Rev D, Firemain Unit 3110 (ASC521311-FM) (UNSIGNED) Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Coast Guard Technical Publication (TP) 7013, 04-OCT-07, Self-Priming Centrifugal Pumps (Close Coupled) Other References Naval Sea Systems Command (NAVSEA) S0400-AD-URM-010/TUM, 5/23/2007, Tag-Out User’s Manual The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

None.

Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):

System fluid in the pump and associated piping.

Piping.

Electrical Cables.

Coderdam Required

3.1.5 Work coordination. The Contractor shall perform work in conjunction with the following Work Item:

Cofferdam Install

3.1.6 Fire Pump Overboard Connection. Provide diver services and plug the fire pump overboard connection. Provide diver services and remove the plug from the overboard connection upon completion of work.

3.1.6.1 The contractor shall install blank connections to isolate the fire pump from the sea as described below and as required by NAVSEA S0400-AD-URM-010/TUM Navy Tag-Out User’s Manual.

3.1.6.2 After installation of the overboard plug, break the fire main on the inboard side of the overboard valve and install a blank flange with gasket on the inboard side of the fire main overboard valve, protecting against flooding through the overboard valve.

3.1.6.3 Remove the blank upon completion of work and prior to removal of the plug in the overboard connection.

3.1.7 Fire pump suction connection. Temporarily close both the port and starboard sea chest suction valves and the fire pump suction from the sea chest. Break the fire pump suction connection on the downstream side of the valve and install a blank flange to allow continued use of the port and starboard sea chests.

3.1.7.1 Upon completion of repairs, temporarily close both the port and starboard sea chest suction valves and the fire pump suction from the sea chest. Remove the blank connection and reassemble the fire pump suction valve flange connections.

3.1.7.2 Fire pump discharge connection. Temporarily install a blank flange and gasket on the fire pump discharge piping flange as soon as the fire pump is disconnected to allow continued operation of the firemain in an emergency. Remove the blank flange and reconnect the fire pump upon completion of repairs.

3.1.7.3 Firemain pump piping connection is shown on the Coast Guard Drawing 750-WMSL-521-026.

3.1.8 Carne and rigging services. The Contractor shall provide crane and rigging services to renew GFP Fire Pump No.2. The Contractor shall provide rigging plan at the arrival conference.

3.1.8.1 If required, the Contractor must provide and install lifting pad eyes for removal and installation of Fire Pumpin accordance with SFLC Std Spec 0740. Remove lifting pad eyes after completion of the work item.

3.1.8.2 Maximum working load for various size pad eye is listed in the Table 2.The following Table 2 lists the maximum working loads for various sized pad eyes. Expected working loads may be considerably less than maximum working load, i.e. a 1” padeye used in the rigging plan will have an “expected working load” of only 6,000 lbs (not the maximum 9,800 lbs) and pull tested to 9,000 lbs.

TABLE 1 - PAD EYE MAXIMUM WORKING LOADS

PADEYE SIZE
MAX WORKING LOAD
1/2”
2,400 lbs
3/4”
5,800 lbs
1”
9,800 lbs
1-1/8”
12,100 lbs
1-3/16”
13,300 lbs

3.1.9 Work locations. The concerned work area is identified in Tables 1. See the applicable drawings in section 2 for guidance, locations, and details.

3.1.10 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041.

3.1.10.1 Disconnect the electrical cables to Fire Pump in accordance with SFLC Std Spec 3042 and record wiring information for later re-connection. Insulate the removed cable ends with electrical tape for safety. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.1.10 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.2 Fire removal. After all piping and electrical connections are removed, the Contractor shall remove Fire Pump Assembly from its foundation.

3.2.1 The Contractor shall rig Fire Pump Assembly from the cutter (Pump Room #2): 5-72-01-E) to Pier as per rigging route shown on Coast Guard Drawing 750-WMSL-101-027.

3.2.2 Foundation Preservation. While Fire Pump Assembly is removed, wire brush or power tool clean the pump foundations and the area under the pump foundations to approximately 1 ft. away from the foundations to remove loose paint and rust. Feather all edges. Clean the areas in accordance with SSPC SP-3. Solvent wipe the areas in accordance with SSPC SP-1. Paint the prepared areas with two coats of epoxy paint to match the existing system as described in SFLC Std Spec 6310.

3.3 GFP Fire Pump installation. The Contractor shall rig GFP Fire Pump Assembly from Pier to the cutter (Pump Room #2, 5-70-01-E) as per rigging route shown on Coast Guard Drawing 750-WMSL-101-027.

3.3.1 The Contractor shall mount GFP Fire Pump to its foundation as shown on Coast Guard Drawing 750-WMSL-180-012 with new fasteners.

3.3.2 Clean piping gasket surfaces before installing new gaskets. Provide and install new gaskets at all piping connection. Renew all mounting fasteners.

3.3.3 The Contractor shall make all piping connection to Fire Pump to its original operating condition as shown on Coast Guard Drawing 750-WMSL-521-026 and TP 7013.

3.3.4 The Contractor shall re-connect electrical cables with previously recorded wiring information in accordance with SFLC Std Spec 3041/3042 and TP 7013.

3.4 Installation checkout. Perform installation checkout in accordance with TP 7013 and submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test – post repairs. After completion of work, the Contractor shall perform an operational test (by Coast Guard personnel) of the Fire Pump to prove satisfactory operating condition, with no leakage. Operate the Fire Pump for ½ Hour. Verify that the direction of pump rotation is correct. Submit a CFR.

3.6 Touch-up preservation. The Contractor shall prepare and touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures)

4.0 Period of Performance: Availability is 14SEP25- 28SEP25. Contractor can coordinate time during period with Cutters Engineering Officer LCDR Andrew Britton: Andrew.A.Britton@uscg.mil or CWO Matt Temple: matthew.temple@uscg.mil..

4.1 Location. The Contractor must perform the work while the USCGC HAMILTON is alongside the pier at the Federal Law Enforcement Training Center (corner of S. Hobson Ave and Chaffe St), Charleston, SC 29405.

4.2 FLETC Base access is required. Vendors must have a valid US driver’s license and show identification. Contractors working on this project must not have felony convictions. Forms will be provided for base access. A CG representative from the cutter will sponsor and escort vendor to the cutter.

File details come from the government source that posted it. Updated .