SOW.doc

DOC document 1 MB Posted

Attached to
USCGC HAMILTON FIRE PUMP REQUEST Federal contract opportunity
Solicitation number
70Z08525Q0029251
Issued by
Department of Homeland Security US Coast Guard

About this file

This Statement of Work (SOW) details a fire pump renewal project for the USCGC HAMILTON at the Federal Law Enforcement Training Center in Charleston, SC. The United States Coast Guard is seeking a contractor to remove and replace Fire Pump No. 5, a Carver Pumps Co. 5x4-10 assembly with a 125 HP electric motor, located in Pump Room #2. The government-furnished fire pump is valued at $50,500, and the work is scheduled for September 14-28, 2025, with specific requirements including disconnecting electrical cables, removing and rigging the existing pump, preserving the foundation, installing the new pump, and performing operational tests.

The solicitation (70Z08525Q0029251) is a small business set-aside using simplified acquisition procedures, with quotations due by August 21, 2025, at 0800 Pacific Time. Contractors must have valid U.S. driver's licenses, no felony convictions, and will be escorted by a Coast Guard representative. The project involves complex maritime engineering tasks such as diver services, overboard connection plugging, sea chest valve management, and precise rigging and installation procedures following multiple Coast Guard and naval technical specifications.

View the file

Other files for this federal contract opportunity

Other files attached to USCGC HAMILTON FIRE PUMP REQUEST, newest first.
File Type Posted
SOW-70Z08525Q0029251-UPDATED AUG18 2025.doc DOC document
This is a combined synopsis CGC HAMILTON FIRE PUMP.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

52100_TAB_0825_753

WORK ITEM 1: Fire Pump, Renew

1.1 Intent. This work item describes the requirements for the Contractor to renew Fire Pump Assembly listed in Table 1.

table 1: Fire pump data

EQUIPMENT
model number/MANUFACTURER
Location

Fire Pump No. 5 Assembly

(51 Inch X 33 Inch X 27 Inch) Approximate Weight 2450 Lbs. (Figure 2 For Reference)

5 X 4 -10 / Carver Pumps Co.
Pump Room #2,

(5-70-01-E)

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST\($/UNIT)
Y
Fire Pump Assembly with Suction Assembly (5X4X10 Pump), Carver Pump Co. and 125 HP, 1760 RPM, 450 Volt AC, Three Phase, 60 Hz, Totally Enclosed Fan Cooled, Manufacturer Reliance Electric Co.
01-561-8775
1
$50,500.00

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 418A-WMSL-100-001, Rev L, General Arrangements

Coast Guard Drawing 418A-WMSL-801-004, Rev B, Booklet of General Plans

Coast Guard Drawing 750-WMSL-101-027, Rev -, Equipment Removal Route Drawing NSC3 & Follow (AS3101009)

Coast Guard Drawing 750-WMSL-320-041, Rev C, Electrical One Line Diagram (NSC4 - SRD) (ASC320001D) (UNSIGNED) Coast Guard Drawing 750-WMSL-521-047, Rev -, Firemain Diagram NSC4 (ASC521001D)

Coast Guard Drawing 750-WMSL-180-012, Rev H, Foundation Arrangement Drawing Design Unit 2110 BKLT No.1 Coast Guard Drawing 750-WMSL-521-26, Rev D, Firemain Unit 3110 (ASC521311-FM) (UNSIGNED)

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Coast Guard Technical Publication (TP) 7013, 04-OCT-07, Self-Priming Centrifugal Pumps (Close Coupled)

Other References

Naval Sea Systems Command (NAVSEA) S0400-AD-URM-010/TUM, 5/23/2007, Tag-Out User’s Manual The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2004, Power Tool Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

None.

Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor shall be aware that interferences in way of work include, but are not limited to the below-listed. Handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences):

· System fluid in the pump and associated piping.

· Piping.

· Electrical Cables.

· Coderdam Required

3.1.5 Work coordination. The Contractor shall perform work in conjunction with the following Work Item:

· Cofferdam Install

3.1.6 Fire Pump Overboard Connection. Provide diver services and plug the fire pump overboard connection. Provide diver services and remove the plug from the overboard connection upon completion of work.

3.1.6.1 The contractor shall install blank connections to isolate the fire pump from the sea as described below and as required by NAVSEA S0400-AD-URM-010/TUM Navy Tag-Out User’s Manual.

3.1.6.2 After installation of the overboard plug, break the fire main on the inboard side of the overboard valve and install a blank flange with gasket on the inboard side of the fire main overboard valve, protecting against flooding through the overboard valve.

3.1.6.3 Remove the blank upon completion of work and prior to removal of the plug in the overboard connection.

3.1.7 Fire pump suction connection. Temporarily close both the port and starboard sea chest suction valves and the fire pump suction from the sea chest. Break the fire pump suction connection on the downstream side of the valve and install a blank flange to allow continued use of the port and starboard sea chests.

3.1.7.1 Upon completion of repairs, temporarily close both the port and starboard sea chest suction valves and the fire pump suction from the sea chest. Remove the blank connection and reassemble the fire pump suction valve flange connections.

3.1.7.2 Fire pump discharge connection. Temporarily install a blank flange and gasket on the fire pump discharge piping flange as soon as the fire pump is disconnected to allow continued operation of the firemain in an emergency. Remove the blank flange and reconnect the fire pump upon completion of repairs.

3.1.7.3 Firemain pump piping connection is shown on the Coast Guard Drawing 750-WMSL-521-026.

3.1.8 Carne and rigging services. The Contractor shall provide crane and rigging services to renew GFP Fire Pump No.2. The Contractor shall provide rigging plan at the arrival conference.

3.1.8.1 If required, the Contractor must provide and install lifting pad eyes for removal and installation of Fire Pumpin accordance with SFLC Std Spec 0740. Remove lifting pad eyes after completion of the work item.

3.1.8.2 Maximum working load for various size pad eye is listed in the Table 2.The following Table 2 lists the maximum working loads for various sized pad eyes. Expected working loads may be considerably less than maximum working load, i.e. a 1” padeye used in the rigging plan will have an “expected working load” of only 6,000 lbs (not the maximum 9,800 lbs) and pull tested to 9,000 lbs.

TABLE 1 - PAD EYE MAXIMUM WORKING LOADS

PADEYE SIZE
MAX WORKING LOAD
1/2”
2,400 lbs
3/4”
5,800 lbs
1”
9,800 lbs
1-1/8”
12,100 lbs
1-3/16”
13,300 lbs

3.1.9 Work locations. The concerned work area is identified in Tables 1. See the applicable drawings in section 2 for guidance, locations, and details.

3.1.10 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041.

3.1.10.1 Disconnect the electrical cables to Fire Pump in accordance with SFLC Std Spec 3042 and record wiring information for later re-connection. Insulate the removed cable ends with electrical tape for safety. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.1.10 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.2 Fire removal. After all piping and electrical connections are removed, the Contractor shall remove Fire Pump Assembly from its foundation.

3.2.1 The Contractor shall rig Fire Pump Assembly from the cutter (Pump Room #2): 5-72-01-E) to Pier as per rigging route shown on Coast Guard Drawing 750-WMSL-101-027.

3.2.2 Foundation Preservation. While Fire Pump Assembly is removed, wire brush or power tool clean the pump foundations and the area under the pump foundations to approximately 1 ft. away from the foundations to remove loose paint and rust. Feather all edges. Clean the areas in accordance with SSPC SP-3. Solvent wipe the areas in accordance with SSPC SP-1. Paint the prepared areas with two coats of epoxy paint to match the existing system as described in SFLC Std Spec 6310.

3.3 GFP Fire Pump installation. The Contractor shall rig GFP Fire Pump Assembly from Pier to the cutter (Pump Room #2, 5-70-01-E) as per rigging route shown on Coast Guard Drawing 750-WMSL-101-027.

3.3.1 The Contractor shall mount GFP Fire Pump to its foundation as shown on Coast Guard Drawing 750-WMSL-180-012 with new fasteners.

3.3.2 Clean piping gasket surfaces before installing new gaskets. Provide and install new gaskets at all piping connection. Renew all mounting fasteners.

3.3.3 The Contractor shall make all piping connection to Fire Pump to its original operating condition as shown on Coast Guard Drawing 750-WMSL-521-026 and TP 7013.

3.3.4 The Contractor shall re-connect electrical cables with previously recorded wiring information in accordance with SFLC Std Spec 3041/3042 and TP 7013.

3.4 Installation checkout. Perform installation checkout in accordance with TP 7013 and submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test – post repairs. After completion of work, the Contractor shall perform an operational test (by Coast Guard personnel) of the Fire Pump to prove satisfactory operating condition, with no leakage. Operate the Fire Pump for ½ Hour. Verify that the direction of pump rotation is correct. Submit a CFR.

3.6 Touch-up preservation. The Contractor shall prepare and touch-up coat all disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems). Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures)

4.0 Period of Performance: Availability is 14SEP25- 28SEP25. Contractor can coordinate time during period with Cutters Engineering Officer LCDR Andrew Britton: Andrew.A.Britton@uscg.mil or CWO Matt Temple: matthew.temple@uscg.mil..

4.1 Location. The Contractor must perform the work while the USCGC HAMILTON is alongside the pier at the Federal Law Enforcement Training Center (corner of S. Hobson Ave and Chaffe St), Charleston, SC 29405.

4.2 FLETC Base access is required. Vendors must have a valid US driver’s license and show identification. Contractors working on this project must not have felony convictions. Forms will be provided for base access. A CG representative from the cutter will sponsor and escort vendor to the cutter.

5. NOTES

FIGURE 1: FIRE INSTALLATION (CGC MUNRO) FOR REFERENCE ONLY

FIGURE 2: GFP FIRE PUMP ASSEMBLY

File details come from the government source that posted it. Updated .