This file is a Task Group Instruction (TGI) for providing SRF-JRMC support work for service line on the USS JOHN FINN (DDG-113). The document details requirements for temporary containment enclosure installation, maintenance, and removal services at various weather deck locations including 01 Level, 02 Level, and Main Deck on both port and starboard sides.

The work scope includes installation of temporary containment enclosures for hatch, scuttle, and door openings with maximum dimensions of 7' x 6' x 6', temporary life rail installation for hatch and scuttle openings, and bridge installation with 4-foot maximum width. The period of performance is April 21, 2025 through May 12, 2025. The work will be performed at multiple locations shown in the attached sketches, with protection covers required where enclosures contact deck and bulkhead surfaces. SRF-JRMC will provide supporting services including crane operations, electrical utilities, air/water/steam supply, ventilation, safety inspections, and QA inspections. The document includes detailed location drawings showing installation points across multiple deck levels of the vessel.

View the file

Other files

File Type Posted
Attachment III Request for Information Form.docx DOCX document
TGI 38BCA63404A01 c0v0.pdf PDF
Attachment II Price Proposal Form N6264925RA029.xlsx XLSX spreadsheet
TGI 38BCA63405A01 c0v0.pdf PDF
N6264925RA029.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

21-JAN-2025 1618

20.14.15.2.9020 (September 2024) ICN: 38BCA86301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPRT SRF SVCE LINE AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BCA

CU PHASE TITLE: F/O – PROVIDE SRF-JRMC SUPPORT WORK FOR SERVICE LINE

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 4

EX00L029

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

NAKAGAWA, DAICHI 231A 3152430969 15-JAN-2025

APPROVED BY: CODE: PHONE: DATE:

NAKAMURA, YUUJI 231A 3152436041 15-JAN-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EX00-L029

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

KONDO, SHINYA

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

863A5201

1. SCOPE/PURPOSE:

1.1 Title: SRF-JRMC Support Work for Service Line; provide

1.2 Location of Work:

1.2.1 01 Level Weather, Port and Starboard (Stbd)

1.2.2 02 Level Weather, Port and Stbd

1.2.3 Main Deck Weather, Port and Stbd

1.3 Identification:

1.3.1 Quantity (One Lot), Installation, Maintenance, and Removal Service of Temporary Containment Enclosure of Hatch, Scuttle, and Door Opening for Service Line Work by SRF-JRMC

TGI Short Form

21-JAN-2025 1618

20.14.15.2.9020 (September 2024) (Continued) ICN: 38BCA86301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPRT SRF SVCE LINE AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BCA

CU PHASE TITLE: F/O – PROVIDE SRF-JRMC SUPPORT WORK FOR SERVICE LINE

FOUO Pg 2 of 4

CU PHASE DESCRIPTION (Cont.)

Maximum Enclosure Size: 7 Feet Hight x 6 Feet Wide x 6 Feet Long Remarks: Modification of the temporary containment enclosure up to 5 times.

Maintenance of the cover of temporary containment enclosure up to 5 times.

See Sketch Enclosure-01 for location and details.

1.3.2 Quantity (One Lot), Installation and Removal Service of Temporary Life Rail of Hatch and Scuttle Opening for Service Line Work by SRF-JRMC

Remarks: See Sketch Enclosure-01 for locations.

1.3.3 Quantity (One Lot), Installation and Removal Service of Bridge for Service Line Work by SRF-JRMC

Maximum Bridge Width Size: 4 Feet Remarks: Modification of the bridge up to 5 times.

See Sketch Enclosure-01 for location and details.

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor work start date:

1.7 Contractor work completion date:

2. PROCEDURE:

2.1 Provide support work listed in 1.3.1 through 1.3.3. See 2.2.3.

2.1.1 The protection cover must be installed where the enclosure and bridge contact the deck and bulkhead for preventing damage.

2.2 Notes:

2.2.1 Planner: Code 231A D. Nakagawa, 243-0969

2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.2.3 Exact installation locations, details, and work dates for enclosure, life rail, and bridge will be provided by SRF-JRMC WIM, Code 333.

2.2.4 JCN EX00-L029 is related to this TGI.

2.3 Government Furnished Material (GFM): None.

2.4 SRF-JRMC will provide the following service work: (TGI No. 38BCA86301S02)

2.4.1 [C740] Crane and crane rigging service.

2.4.2 [X99E] Utility service, electrical.

4/21/2025

5/12/2025

21-JAN-2025 1618

20.14.15.2.9020 (September 2024) (Continued) ICN: 38BCA86301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPRT SRF SVCE LINE AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BCA

CU PHASE TITLE: F/O – PROVIDE SRF-JRMC SUPPORT WORK FOR SERVICE LINE

FOUO Pg 3 of 4

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.4.4 [X99V] Temporary ventilation service.

2.4.5 [C106.1] Safety inspection for SRF-JRMC employees.

2.4.6 [C106.2] Gas free inspection for SRF-JRMC employees.

2.4.7 [C133] QA inspection for (G) symbol(s).

21-JAN-2025 1618

20.14.15.2.9020 (September 2024) (Continued) ICN: 38BCA86301 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: SPRT SRF SVCE LINE AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BCA

CU PHASE TITLE: F/O – PROVIDE SRF-JRMC SUPPORT WORK FOR SERVICE LINE

FOUO Pg 4 of 4

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - 1 N 2 LI FY-25 Local Standard Items - ORG N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

22/KE PC N

22/MQ CS N

Process Funding Document 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 38BCA86301A01-Sketch.pdf 15-JAN-2025 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38BCA86301 KEY OP: A01

SKETCH

ENCLOSURE-0138BCA86301A01 SHEET 1 OF 4

Temporary Containment Enclosure and Bridge Location *Bridge installation aligned with the harbor position.

ENCLOSURE-0138BCA86301A01 SHEET 2 OF 4

ENCLOSURE-0138BCA86301A01 SHEET 3 OF 4

ENCLOSURE-0138BCA86301A01 SHEET 4 OF 4

File details come from the government source that posted it. Updated .