Tentative Cable-Design-Build Schedule.xlsx

XLSX spreadsheet 10 KB Posted

Attached to
New Building IT Design and Build
Solicitation number
49100426K0003
Issued by

About this file

This is a tentative project schedule for a cable replacement and network equipment installation project spanning May through December. The schedule is organized into three phases coordinated across multiple floors of a facility, with cable replacement and network design/topology work occurring in parallel with equipment installation activities.

The cable replacement phase is divided into three stages: Phase 1 covers Floors 4 and 8th-10th; Phase 2 addresses Floors 5th-7th; and Phase 3 encompasses Floors Concourse through 3rd. Network design and topology work precedes the installation of network equipment, which is similarly phased across the facility with Phase 1 covering Floors Concourse, 4, and 8th-10th; Phase 2 addressing Floors 5th-7th; and Phase 3 covering Floors 1st-3rd. The timeline suggests overlapping activities across the three phases to optimize project completion, with the entire project expected to conclude by December.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

MAYJUNJULAUGSEPOCTNOVDEC
CABLE REPLACEMENT
PHASE 1 (Floors 4, 8th - 10th)
PHASE 2 (Floors 5th - 7th)
PHASE 3 (Floors Concourse - 3rd)
NETWORK DESIGN/TOPOLOGY
INSTALLATION OF NETWORK EQUIPMENT
PHASE 1 (Floors Concourse, 4, 8th - 10th)
PHASE 2 (Floors 5th - 7th)
PHASE 3 (Floors 1st - 3rd)