Telfair ES Reno Addendum _5 11_2_23.pdf
PDF 58 KB Posted
- Attached to
- TCES Renovations & Modifications
- Solicitation number
- PE-55390-NONST-2024-000000001
- Issued by
- Treutlen County, Georgia
About this file
This document is Addendum No. 5 related to the renovation and modifications to the Telfair County Elementary School in McRae, Georgia. The addendum makes changes to the contract for construction, including increasing the liquidated damages from $3,000 per day for delays in achieving substantial completion and final completion of the project. Additionally, the addendum adds a new manufacturer, Robbins Sports Surfaces, for the resilient athletic flooring specification.
The document outlines the liquidated damages and the process for withholding and releasing funds related to any delays in the project. It does not provide any additional details about the overall project scope, timeline, or other salient information beyond the changes made in this addendum.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Telfair ES Reno Addendum _4 10_30_23.pdf | ||
| TCES Advertisement for Bids.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 5
November 2, 2023
RENOVATION AND MODIFICATIONS
to the
TELFAIR COUNTY ELEMENTARY SCHOOL
McRae, Georgia
CHANGES TO SPECIFICATIONS:
SECTION 00400 – THE CONTRACT FOR CONSTRUCTION AND INCORPORATED
GENERAL CONDITIONS
Page 00400-6 / Paragraph 3.1.2
CHANGE TO READ:
[3.1.2 The Contractor shall pay the Owner the sum of Three
Thousand Dollars ($3,000.00) per day for each and every calendar day of the unexcused delay in achieving Substantial Completion beyond the date set forth herein for Substantial Completion of the Work (the total amount of Liquidated Damages shall be Three Thousand Dollars ($3,000.00) per calendar day). Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the Owner, estimated at or before the time of executing this Contract. When the Owner reasonably believes that Substantial Completion will be inexcusably delayed, the Owner shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the Owner to be adequate to recover liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving Substantial Completion, or any part thereof, for which the Owner has withheld payment, the Owner shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.]
Page 00400-13 / Paragraph 5.6.1.1
CHANGE TO READ:
[5.6.1.1 If the Contractor fails to achieve final completion within the time fixed therefore by the Architect in its Certificate of Substantial Completion, the Contractor shall pay the Owner the sum of Three Thousand Dollars ($3,000.00) per day for each and every calendar day of unexcused delay in
November 2, 2023 achieving final completion beyond the date set forth herein for final completion of the Work. Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the Owner, estimated at or before the time of executing this Contract. When the Owner reasonably believes that final completion will be unexcusably delayed, the Owner shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the Owner to be adequate to recover, liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving final completion, or any part thereof, for which the Owner has withheld payment, the Owner shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.
SECTION 09622 – RESILIENT ATHLETIC FLOORING
Page 09622-2 / Paragraph 2.1.A
ADD THE FOLLOWING MANUFACTURER:
[Robbins Sports Surfaces]
END OF ADDENDUM NO. 5