About this file
Summary of Technical Specifications for Dark Optical Fiber Service
This document is a Technical Specifications file for a Request for Quote (RFQ) issued by the State of Maine's Office of Information Technology (OIT) for dark optical fiber services in Augusta, Maine. The State seeks a turnkey solution providing a point-to-point dark fiber connection between two endpoints: the Maine OIT Main Distribution Frame (MDF) at Cross Office Building, 111 Sewall Street, Augusta, and an MDF at 85 Leighton Road, Augusta. The service involves four strands (two pairs) of 9/125 micron single-mode optical fiber compliant with G.652D standards, suitable for both aerial and underground deployment. The project must be completed within five weeks of agreement signature, with service initiation expected within 45 business days. The contract term is five years with three optional one-year renewal periods. All preliminary construction and preparatory work is anticipated to be completed prior to service initiation, with the cable cut and splice date determined by OIT in coordination with the vendor.
Vendors must provide complete fiber splice maps upon completion of splice work and submit final test results in both PDF and trace file formats at 1310 nm and 1550 nm wavelengths. Testing must meet industry-recognized tolerances: no more than 0.1 dB per splice point, no more than 0.5 dB per connector mating point, and cable loss within manufacturer specifications. The cost structure requires vendors to identify any one-time start-up fees and provide level annual service payments due at the beginning of each service year. The first payment is contingent upon fiber service being tested and accepted by the Department. The vendor is responsible for fiber maintenance and repair throughout the agreement term. Bidders must agree to all technical requirements, provide a complete cost table with one-time fees and annual service fees for all five years, and submit a detailed project statement of work with installation timetables and service level agreements for maintenance and support.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HowtoSearchBidsandRespond.pdf | ||
| RFQ Specifications.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation for Dark Optical Fiber Service – Augusta, Maine
State of Maine/Office of Information Technology
Summary:
The State of Maine/Office of Information Technology (OIT) is issuing a Request for Quote (RFQ) for lease/rent of a dark/unmeasured optical fiber point-to-point connection in Augusta, Maine. The terminating endpoints for service are: A) The Maine OIT MDF at either Cross Office Building, 111 Sewall Street, Augusta ME 04330 and Z) 85 Leighton Road, Telecommunications Room (MDF), Augusta. 5-year Service with 3 one-year renewal options. OIT seeks a “turnkey” solution where the fiber is tested and provided. Cost must include fiber maintenance/repair (as needed) over the term of the agreement.
General Technical Requirements:
The optical fiber cable plant will consist of 4 strands (2 pair) of 9/125 micron G.652D-compliant single-mode fiber, loose tube, rated for outdoor aerial and underground applications; whichever has most cost advantage for State of Maine.
The 85 Leighton Road endpoint shall be within Maine OIT’s designated MDF. The OSP optical fiber cable will be brought into the MDF room, with an adequate slack coil affixed to the backboard per OIT instructions. The end of the cable will then be dressed into the OIT-provided backboard-mounted splice enclosure and fusion-spliced to the OIT-installed interior optical fiber cable within the splice enclosure, using the OIT-provided splice trays. OIT will develop and implement fiber labeling at the terminating patch panels at each endpoint. The Vendor shall be responsible for documenting and providing a complete fiber splice map to OIT immediately upon completion of all splice work.
The OSP cable plant will be delivered in accordance with all applicable telecommunications industry standards and best practices, and in accordance with all applicable laws, regulations, codes and ordinances.
Once the cable build is complete and spliced, the Vendor will test all terminated fibers, bidirectionally, at the endpoint patch panels and correct all deficiencies in that portion of the cable plant installed by the Vendor. Once satisfactory test results on all terminated fibers have been completed, they will be submitted to OIT for review and determination of acceptance. Acceptable test results will be based upon industry recognized tolerances for cable, splice and connector losses. Typically, this will be no more than 0.1 dB per splice point, no more than 0.5 dB per connector mating point, and cable loss within manufacturer material specifications. Testing will be conducted using both calibrated optical power meter/light source and a calibrated OTDR at wavelengths of 1310 nm and 1550 nm. Final test results, including power meter and OTDR traces will be provided to the Customer in both individual .pdf and trace (*.trc/*.sor) files for each fiber.
The specific OIT provided and installed hardware and materials shall include:
· Rack-mounted optical fiber patch panel fitted with LC-APC connectors.
· Indoor-rated 9/125 micron single-mode optical fiber, tight-buffered, pre-terminated in the patch panel, dressed into the backboard-mounted splice enclosure and ready for final splice preparation and splicing by the Vendor. Backboard-mounted optical fiber splice enclosure will be a Corning #WSH-11SPT-F. Splice trays will be Corning #M67-076-C.
· Bidders may utilize existing facilities in either Cross Office Building MDF termination point is already in place or chose to install a new termination point.
· If facilities are already in place the bidder will test and label delivery fibers and termination points.
· If bidder must build the bidder will utilize the following materials:
· Rack-mounted optical fiber patch panel fitted with LC-APC connectors.
· Indoor-rated 9/125 micron single-mode optical fiber, tight-buffered, pre-terminated in the patch panel, dressed into the backboard-mounted splice enclosure and ready for final splice preparation and splicing by the Vendor. Backboard-mounted optical fiber splice enclosure will be a Corning #WSH-11SPT-F. Splice trays will be Corning #M67-076-C.
· The end of the cable will then be dressed into the OIT-provided backboard-mounted splice enclosure and fusion-spliced to the OIT-installed interior optical fiber cable within the splice enclosure, using the OIT-provided splice trays. OIT will develop and implement fiber labeling at the terminating patch panels at each endpoint. The Vendor shall be responsible for documenting and providing a complete fiber splice map to OIT immediately upon completion of all splice work.
It is anticipated that all non-disruptive preliminary construction and preparatory work will be completed prior to service initiation. The cable cut and splice date/time will be determined by OIT and coordinated with the Vendor.
Schedule:
Project must be completed within 5 weeks of agreement signature and approval. Bidder shall supply State of Maine project status reports.
Payment:
Vendor to identify any one-time start-up fees. Level annual (or quarterly/monthly) payments to vendor at beginning of each service-year. Initiation of service and first payment(s) will occur after fiber service is tested and accepted by the Department.
Bid Submission:
| Requirement |
| Bidder Agrees to Requirement (Yes or No) |
Dark fiber 4 Strand (two-pair) service with support provided per specifications
5-year level-cost dark fiber service with renewal options
Project statement of work and install timetable with any project assumptions/dependencies document attached
Install/service ready within 45-business days
SLA for maintenance/support/repair service attached
Cost table fully completed
Cost: Option 1: 4 Strand (2 Pair)
| One-time Fee, if-any: | ______________ | ||
| Year-1 Service Fee: | ______________ | ||
| Year-2 Service Fee: | ______________ | ||
| Year-3 Service Fee: | ______________ | ||
| Year-4 Service Fee: | ______________ | ||
| Year-5 Service Fee: | ______________ |
| Total One-time Fee | ___________ (enter value in cost response) | |
| Total All Service Fees: | ____________ (enter value in cost response) |