TECHNICAL SPECIFICATIONS ARFQ DEP24-47 Grow Multi-Well Plugging Package.pdf

PDF 1 MB Posted

Attached to
GROW MULTI-WELL PLUGGING PACKAGE
Solicitation number
ARFQ 0313 DEP2400000047 2
Issued by
Wirt County, West Virginia

About this file

Technical Specifications Summary: GROW Multi-Well Plugging Package

This is a Technical Specifications document prepared by the West Virginia Department of Environmental Protection (DEP), Office of Oil and Gas, for the plugging and remediation of two abandoned oil and natural gas wells located in Wirt County, West Virginia. The project involves the plugging of wells API# 47-105-01416 and API# 47-105-01417, both situated near Freeport, WV along Route 47. The scope of work encompasses site preparation, well plugging operations, and site reclamation in accordance with West Virginia Code 22-6-23 and 22-6-24. Site preparation activities include clearing and grubbing vegetation, installing erosion and sediment controls, constructing service roads (approximately 757 feet for API# 47-105-01416 and 3,200 feet for API# 47-105-01417), installing silt fence, and establishing cellars around wellheads. Both wells require complete plugging to total depth (estimated at 250 feet), with well-specific considerations including gas and oil leakage at API# 47-105-01416 and gas, oil, and saltwater leakage at API# 47-105-01417. The document provides comprehensive technical specifications for thirty-seven line items, including rig and crew requirements (minimum three-person crew), mobilization and demobilization, equipment rentals, materials, and disposal services.

The technical specifications establish detailed functional and performance requirements for all equipment, materials, and services necessary to complete the project. Payment terms are structured as hourly rates for rig and crew operations, vacuum trucks, heavy equipment, power swivels, mud/mixing pumps, and welder services; per-day rates for power tongs; per-foot pricing for casing, tubing, and drill pipe; per-barrel rates for disposal services; per-ton pricing for gravel, topsoil, and solid waste; and lump-sum amounts for site preparation and site reclamation per well. The DEP will obtain and pay for all local, state, and federal permits necessary for contract completion, with the responsible party designated as "UNKNOWN - DEP PAID PLUGGING CONTRACT." Work is restricted to Monday through Friday, with a maximum ten-hour workday unless emergency situations or departmental approval warrant extended hours. A Project Coordinator will oversee the contract and serve as the primary point of contact for the contractor. All work must comply with the West Virginia Erosion and Sediment Control Field Manual (May 2012) and applicable environmental regulations. The document does not specify contract award dates, response deadlines, or funding sources within the technical specifications section.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GROW MULTI-WELL PLUGGING PACKAGE

WEST VIRGINIA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

OFFICE OF OIL AND GAS

COUNTY

OF

WIRT

API# 47-105-01416

API# 47-105-01417

TECHNICAL SPECIFICATIONS

Table of Contents

Table of Contents

I. PROJECT DESCRIPTION

1.0 Location/Site Description

1.1 API# 47-105-01416

1.2 API# 47-105-01417

2.0 Directions to site:

II. SCOPE OF WORK

III. GENERAL CONDITIONS

1.0 Administrative

2.0 Permitting

3.0 Work

IV. PROJECT DESCRIPTION

1.0 Site-based considerations:

1.1 API# 47-105-01416

1.2 API# 47-105-01417

2.0 Well-specific considerations:

2.1 API# 47-105-01416

2.2 API# 47-105-01417

V. PROJECT WORK PLAN

Site Preparation Plan

1.1 API# 47-105-01416

1.2 API# 47-105-01417

Proposed Plugging Work Plan:

1.1 API# 47-105-01416

1.2 API# 47-105-01417

Site Reclamation Plan

1.1 API# 47-105-01416

1.2 API# 47-105-01417

VI. TECHNICAL SPECIFICATIONS

1.0 Rig and Crew -Three (3) Man Crew (minimum)

2.0 Mobilization & Demobilization

2.5 Field Move

3.0 Site Preparation

4.0 Vacuum Water Truck

5.0 Heavy Equipment

6.0 Power Tongs

7.0 Casing Knife/Ripper

8.0 Casing and Tubing Purchase

9.0 Casing, Tubing, and Pipe Rentals

10.0 Tri-Cone Drill Bit

11.0 Trash Pump

12.0 On-Site Water Storage Container(s)

13.0 Disposal of Gel

14.0 Disposal of Liquid Waste

15.0 Disposal of Solid Waste

16.0 Aqua Gel

17.0 Cement

18.0 Gravel

19.0 Steel Mud Pit

20.0 Site Reclamation

21.0 Silt Fence

22.0 Monument

23.0 Welder/Cutting Torch

24.0 Oil Absorbent Supplies

25.0 Sand Pump

26.0 Cherry Picker

27.0 Casing/Tubing Spear

28.0 Overshot

29.0 Impression Block

30.0 Subs

31.0 Power Swivel

32.0 Concave Mill

33.0 Mud/mixing pump

34.0 Logging, Bond with CCL

34.5 Wireline Shot/Perforation, Collar Buster

35.0 Tie Mats

36.0 Topsoil

37.0 Culvert

I. PROJECT DESCRIPTION

This project involves the plugging and/or remediation of abandoned oil and/or natural gas wells and sites at the location described below.

1.0 Location/Site Description

1.1 API# 47-105-01416

Physical Address: Rt. 47

Freeport, WV 26337

Parcel Description: MARSHALL SHAWN PAUL

ID: 53-02-0006-0027-0009

DESC: 21.62 ACRES SUR; HUGHES RIVER

Well Location: 39.128292 °N, -81.310072 °W

1.2 API# 47-105-01417

Physical Address: Rt. 47

Freeport, WV 26337

Parcel Description: EDCO MINERALS LLC

ID: 53-02-0006-0027-0000

DESC: 2/3 OF 42.54 SUR HUGHES RIVER

Well Location: 39.131736 °N, -81.317619 °W

Note: DEP strongly advises using only the provided turn-by-turn directions listed below to navigate to the pre-bid meeting site and not the GPS coordinates of the well site itself.

Failure to arrive at the determined pre-bid location due to navigation errors will not warrant rescheduling another meeting.

2.0 Directions to site:

Directions from the Charleston Area:

From Charleston, take I-77 N toward Parkersburg for 59 miles. Take Exit 174 - Staunton

Avenue. Turn left on Rt 47-E. Continue 17 miles and turn right on dirt road, no sign.

Continue 480 feet to the well site on the left. Pre-bid will be held at well site.

Directions from the Parkersburg Area:

Take I-79 S to Exit 174 – Staunton Avenue. Turn left on Rt 47-E. Continue 17 miles and turn right on dirt road, no sign. Continue 480 feet to the well site on the left. Pre-bid will be held at well site.

II. SCOPE OF WORK

The Contractor, the Contractor’s agents, representatives, and subcontractors (“Contractor”) shall provide all equipment, materials, labor, and professional services for the plugging of the oil and/or natural gas well(s) identified herein, and the reclaiming of all land disturbed in association with those plugging operations in accordance with West Virginia Code §§ 22-6-23, 22-6-24, and all rules promulgated thereunder.

This project is defined by, and subject to, the following documents attached hereto or included as part of supplemental documentation made available as part of the solicitation request (“Contract”):

I. Project Description

II. Scope of Work

III. General Conditions

IV. Well Description

V. Remediation and Plugging Work Plan

VI. Technical Specifications

VII. Appendix A – Well Records

III. GENERAL CONDITIONS

In addition to the Standard Terms & Conditions for Construction and Reclamation, the following conditions govern this Contract:

1.0 Administrative

A. The Contract shall be overseen by DEP by an inspector specialist/project coordinator from the Abandoned Well Plugging Program. DEP may, situationally, assign alternate or assistant coordinators as staffing needs vary.

B. The Project Coordinator for the contract will be designated at the time of the issuance of the Notice to Proceed.

C. The Project Coordinator shall serve as the first point of contact for the Contractor in all matters related to the Contract.

D. The Contractor shall notify the Project Coordinator of any work stoppages or changes to planned operators at soon as practically possible.

E. All change order requests shall be submitted to the Project Coordinator for approval prior to the initiation of any work related to that change order request.

2.0 Permitting

A. Upon award of the Contract to the successful bidder, the Department shall transfer the well to and issue the plugging permit under the responsible party name, UNKNOWN

- DEP PAID PLUGGING CONTRACT.

B. The plugging portion of the Remediation and Plugging Work Plan included herein

(Section V) shall be incorporated as part of the plugging permit. This plan is developed based on best available information. Should field observations during plugging operations necessitate deviations from this plan, the Department and Contractor shall cooperate to develop alternate plans in full compliance with all applicable rules and regulations.

C. All work performed under the Contract must be completed in accordance with the most current version of the Erosion and Sediment Control Field Manual.

D. Unless otherwise specified in the Technical Specifications and/or Bid Sheet, the

Department will obtain and pay for all Local, State, and Federal permits necessary for the completion of the Contract. Any permit conditions contained within said permits shall become mandatory inclusions in the Contract.

3.0 Work

A. Contractor shall perform Contract work (i.e., site preparation and permitted well work) during the days of Monday through Friday. Work will not be conducted on weekends or state/national holidays except with Department approval or during emergency situations. A workday is defined as a maximum of ten (10) hours; however, additional hours may be worked with Department approval or during emergency situations.

B. Contractor is responsible for tracking daily time and material utilization for the purpose of invoicing. The Department shall confirm daily expenditures at the conclusion of each workday. Any disputes related to time and/or material usage determinations should be made in writing to the Project Coordinator.

C. All in-stream work required in association with the project shall be performed in accordance with all applicable local, state, and federal requirements.

D. Toilet facilities will be provided by the vendor but will not be a separate line item in the contract.

IV. PROJECT DESCRIPTION

1.0 Site-based considerations:

The well site is flat and covered with brush and trees and will need to be brushed and cleared of all vegetation. The well is currently open at the surface and is leaking gas and oil. There is a wooden oil tank at the well site which the landowner has requested to keep, so it will not be moved.

A cellar will be installed around the well head for well control during the plugging process, minimum size 24”. OOG will contact Locate 811 to have all subsurface utilities marked.

The well site is flat and covered with brush and trees and will need to be brushed and cleared of all vegetation. A service road will need to be constructed to the well site with an estimated length of 3200’. All trees and brush from the well site and service road can be piled and left on location.

The well is currently open at the surface and is leaking gas, oil, and saltwater. A cellar will be installed around the well head for well control during the plugging process, minimum size 24”.

OOG will contact Locate 811 to have all subsurface utilities marked.

2.0 Well-specific considerations:

2.1 API# 47-105-01416

The Office of Oil and Gas does not have a well record for the subject well API# 47-105-01416.

Reference well API# 47-105-00275 will be used for downhole conditions. The well record shows total depth (TD) at 250’. Additionally, the record shows 57’ of 8 ¼” surface casing, 132’ of 6 ⅝” freshwater casing and 228’ of 2” tubing. Packer location is unknown. Cemented casing locations are unknown. The record shows freshwater at 45’ and 56’. No coal or saltwater was reported. Well site elevation is 631’.

2.2 API# 47-105-01417

The Office of Oil and Gas does not have a well record for the subject well API# 47-105-01417.

Reference well API# 47-105-00275 will be used for downhole conditions. The well record shows total depth (TD) at 250’. Additionally, the record shows 57’ of 8 ¼” surface casing, 132’ of 6 ⅝” freshwater casing and 228’ of 2” tubing. Packer location is unknown. Cemented casing locations are unknown. The record shows freshwater at 45’ and 56’. No coal or saltwater was reported.

Well site elevation is 633’.

V. PROJECT WORK PLAN

Contract work may require site remediation of the well site prior to the commencement of plugging operations.

Project will commence, generally, as follows:

1. Pre-mobilization site remediation, if necessary,

2. Site preparation,

3. Connect rig to well,

4. Clean out well to total depth,

5. Set prescribed plugs and monument,

6. Reclaim site including removal of stream crossings, and

7. Submit invoice to DEP.

Site Preparation Plan

Two hundred (200) feet of silt fence will be installed around the well site to isolate the disturbed area from Hughes River. The area around the well 50’ x 100’ shall be cleared of all brush, leveled and smoothed. All trees and brushes can be stacked and left on location. The service road will need to be widened and stoned to accommodate plugging equipment. Two 16” x 12’ culvers will be installed in the service road. The service road shall be ditched with erosion and sediment (E&S) controls. The estimated length of the service road is 757’. All production equipment shall be dismantled and removed from the well site. Stone or tie mats will be placed around the well head to stabilize the rig. A minimum 24” cellar will be installed around the well head.

One hundred-fifty (150) feet of silt fence will be installed around the well site to isolate the disturbed area from the river. The area around the well 50’ x 100’ shall be cleared of all brush, trees leveled and smoothed. All trees and brushes can be stacked and left on location. The estimated length of the service road is 3200’. The service road will need to be brushed and widened. Tie mats and/or stone may be used to accommodate plugging equipment. The service road shall be ditched with erosion and sediment (E&S) controls. All production equipment shall be dismantled and removed from the well site. Stone or tie mats will be placed around the well head to stabilize the rig. A minimum 24” cellar will be installed around the well head.

Proposed Plugging Work Plan:

1. Notify Project Coordinator (PC) within 24 hours of plugging commencement.

2. Move in and rig up to existing 6” casing.

3. Trip in hole (TIH). Pull rods, tubing, and packer if found.

4. TIH to total depth (TD) at or below 250’ with tubing, spot 6% gel followed by cement from

TD to surface.

5. Rig down and install monument. Reclaim site.

1. Notify Project Coordinator (PC) within 24 hours of plugging commencement.

2. Move in and rig up to existing 8 ¼” casing.

3. TIH. Pull rods, tubing, and packer if found.

4. TIH to freshwater depth at 50’. Perforate casing if found. Squeeze cement to shut off water flowing up around the outside of the 8 ¼” casing. If cement fails to shut off water, 12” casing will be driven over the 8 ¼” casing to isolate and contain the water.

5. TIH with bit and drill out cement plug. Continue to clean out hole to TD at or below 250’.

6. TIH to TD with tubing. Spot 6% gel followed by cement from TD to surface.

7. Rig down and install monument. Reclaim site.

NOTE.. Any casing found in the well without cement in the annulus that cannot be retrieved must be perforated and cemented at all saltwater, freshwater, coal, oil, gas, casing shoe and elevation points.

Site Reclamation Plan

All production equipment shall be removed and disposed of. All silt fences shall be removed. All tie mats and/or stone shall be removed from the well site. The cellar shall be removed from around the well head. All disturbed areas will be smoothed, seeded and mulched per DEP code. A well monument will be installed at the well head, minimum 6” diameter and 42” above final grade. The service road shall be topped with #57 stone (two track).

All production equipment shall be removed and disposed of. All silt fences shall be removed. All tie mats and/or stone shall be removed from the well site. The cellar shall be removed from around the well head. All disturbed areas will be smoothed, seeded and mulched per DEP code. A well monument will be installed at the well head, minimum 6” diameter and 42” above final grade. The service road shall be topped with #57 stone (two track).

VI. TECHNICAL SPECIFICATIONS

1.0 Rig and Crew -Three (3) Man Crew (minimum)

Description:

The rig is a mobile platform from which well work is performed. The rig crew are the persons needed to adequately operate the rig.

Functional/performance requirements:

The rig must be a mobile rig, capable of pulling 150 percent of the heaviest hook load anticipated. Rig shall have the ability to use both cable tools and rotary type equipment.

Rig will be equipped with a walking beam and cable tools such as stinger, drill stem, jars, bailers of various sizes, an assortment of cable tool bits, a sinker bar, and well control devices. The rig crew will consist of, at a minimum, three persons – a rig operator, two hands, and a pickup truck.

Measurement and Payment:

Item is bid per hour of operation. Hours charged will be for on-site work only. Daily transportation to and from the job site is not included and will not otherwise be charged separately. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Heavy Equipment.’)

Hours for Rig and Crew are payable only after the point in time in which the rig has been set up and connected to the well. Rig set up prior to well connection is considered under the line item for “Site Preparation.”

2.0 Mobilization & Demobilization

Mobilization and demobilization, collectively, encompasses the labor and equipment necessary to transport all contract equipment, tools, and materials to and from the project site. Mobilization and demobilization pricing includes all equipment on the contract at the time of the bid. Transportation costs for any other unanticipated equipment needs that may arise will be resolved through the Change Order process, if necessary.

Functional requirements:

All necessary trucking must include operator with a valid Commercial Driver’s License

(CDL).

Item is bid as a service, with half the total bid amount payable after mobilization has occurred (50.0%), and the remainder payable with the final invoice.

2.5 Field Move

A field move is the complete relocation of field equipment and/or materials between successive project sites contained within the same contract. The field move includes all the labor, equipment, and materials necessary to demobilize from one site, transport all equipment and/or materials to the next location, and setup the rig to the point that the rig is connected to the next well.

All necessary trucking must include operator with a valid Commercial Driver’s License

(CDL).

Measurement and payment:

Item is bid per well and is inclusive of all labor, equipment, and materials.

3.0 Site Preparation

Site preparation is the process of readying the well site location for plugging activities.

Site preparation may include clearing and grubbing, tree-cutting, construction, installation of erosion and sediment controls, tie-mat installation, cellar installation, and roadbuilding and maintenance thereof. Site preparation includes all setup up and staging of well plugging equipment to the point that the rig is connected to the well and plugging operations are ready to commence.

3.1 Site Preparation – API# 47-105-01416

3.2 Site Preparation – API# 47-105-01417

Any heavy equipment used during site preparation must meet the functional requirements identified in Item 5. Heavy Equipment.

Performance Requirements:

Any construction activities conducted during site preparation shall be completed in accordance with the provisions described in the West Virginia Erosion and Sediment

Control Field Manual – May 2012. Note that Section A of this manual establishes relevant criteria for road construction.

https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf.

This item is bid as a lump sum per well for all labor, equipment, and tools needed to complete site preparation, as described in the ‘Site Preparation’ project description in

Section V. Any materials needed will be bid separately under their respective line items.

(e.g., stone, silt fence, tie mats, culverts).

4.0 Vacuum Water Truck

https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf

A vacuum truck is a tank truck that has a pump and a tank designed to pneumatically suck liquids, sludges, slurries, or similar fluids into the tank of the truck for the purposes of transporting that material to another location. In this contract, the vacuum water truck will be used to deliver water to site, dispose of plugging fluids and may assist in controlling fluid returns from the well bore site.

Vacuum water truck must include all hoses and connections needed as well as operator.

This item is bid per hour of operation and includes operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or ‘Heavy

Equipment.’)

5.0 Heavy Equipment

In addition to site preparation, heavy equipment may be used during well plugging operations for purposes including the movement of tools and equipment. The use of heavy equipment requires a qualified operator.

Bulldozer must have winches and tilt blades and will be used for grading and the spotting of equipment. Excavator must be a tracked machine. Note: horsepower and weight will be verified by reviewing the specifications of the model(s) selected by the vendor.

1. Bulldozer (minimum 85 horsepower and minimum weight 16,000 pounds.)

2. Excavator (minimum 85 horsepower and minimum weight 25,000 pounds.)

3. Skid Steer (minimum 24 HP, 700# rated capacity or equivalent.)

This item is bid per hour of operation and includes labor by a qualified operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and

Crew).

6.0 Power Tongs

Power tongs are large-capacity self-locking wrenches used to grip drill string components and apply torque. Power tongs are used to assemble and disassemble tubulars and casings.

The following sizes may be needed for this project.

1. Up to 4 ½ inches

2. Over 4 ½ inches up to 8 ⅝ inches

3. Over 8 ⅝ inches up to 10 ¾ inches

This item is bid per day of use.

7.0 Casing Knife/Ripper

A casing knife/ripper is a cable tool used in association with jars to affect the separation or severance of tubing or casing found in the well bore.

Knife block assembly size will be determined by the well bore. All assembly components will be provided by the contractor.

The following sizes may be required:

1. Up to 3 ½”

2. Up to 8 ⅝”

This item is bid per knife per day.

8.0 Casing and Tubing Purchase

Casing and tubing are pipes of a specified diameter lowered into the borehole to serve as a conduit for fluids or to provide borehole structural stability. The casing and tubing purchase is necessary when casing and tubing must be left in the well bore, and when casings need to be lengthened to nipple up for physical connection to the rig. Slips and elevators will be provided by the contractor.

The following sizes may be needed:

1. 24” Casing

2. 12” Casing

3. 5 3/16” Casing

This item is bid per foot.

9.0 Casing, Tubing, and Pipe Rentals

Casing and tubing are pipes of a specified diameter lowered into the borehole to serve as a conduit for fluids or to provide borehole structural stability. The casing, tubing, drill pipe, and drill collar rentals are needed when tubing and casings may be used in the well bore and recovered in such instances.

This will include various sizes that will be determined by the well bore. Slips and elevators will be provided by the contractor.

1. Tubing: 1 ½ inches to 2 ⅜ inches

2. Drill Collar: 2 ⅞ inches

3. Drill Pipe: PAC 50 or equivalent

This item is bid per foot.

10.0 Tri-Cone Drill Bit

The drill bit is the tool used to cut or crush rock during well drilling. A Tri-cone bit will be used to drill out fill-up found in the well bore.

Tri-cone bit include bit sub and a float.

1. 2 ¾ inches up to 4 ¾ inches

2. 4 ¾ inches up to 6 ¼ inches

3. 6 ½ inches up to 8 ¼ inches

Drill bit shall be in used condition.

This item is bid per bit.

11.0 Trash Pump

The trash pump is used to transfer water and other plugging fluids between locations.

Functional and Performance requirements:

The trash pump must be a minimum three (3) inches and shall be of industrial grade with all hoses and fittings included.

This item is bid per hour of use.

12.0 On-Site Water Storage Container(s)

The water storage container(s) must hold at a minimum one hundred (100) barrels and will be used for the storage of fresh water for use in the plugging operation.

This item is bid per container.

13.0 Disposal of Gel

There are instances where gel fluids from the plugging operations may need to be disposed of, in which case they shall be hauled to an approved solid waste facility.

This item is bid per barrel and does not include trucking cost. Copies of scale tickets from an approved solid waste facility shall be provided to the Department.

14.0 Disposal of Liquid Waste

There are instances where saltwater or other Class II fluids are returned to the surface due to the plugging operations and must be disposed of at an Underground Injection Control

(UIC) well. The contactor will transport the saltwater or other Class II fluids to a UIC well for disposal.

This item is bid per barrel and does not include trucking cost. Manifest and invoice from an approved disposal facility shall be provided to the Department.

15.0 Disposal of Solid Waste

Solid waste, including contaminated soil, disposal will be the responsibility of the contractor.

This item is bid per ton and does include trucking cost. Copies of scale tickets from an approved solid waste facility shall be provided to the Department.

16.0 Aqua Gel

Gel is a mixture of water and bentonite clay mixed to desired weight. Aqua gel will have dual use, it will be used to increase the viscosity of the drill fluid and as spacers between the cement plugs.

This item is bid per fifty (50) pound sack delivered to site. Pricing is to include mixing and pumping. Larger unit sizes of aqua gel may be used on-site (i.e., “Super Sacks”), but bid prices and payment shall be standardized to the fifty-pound sack equivalent. The use of any heavy equipment to assist in the mixing and pumping of aqua gel (i.e., excavator to lift a super sack) shall be considered in this line item.

17.0 Cement

Portland Class A Cement shall be used to cement casings and tubulars in the well bore and for cement plugs. Class L cement may be used in place of Class A if explicitly allowed by permit.

Performance requirements:

Cement will be a Portland Class A or L cement, as identified in the permit, with no other additives.

This item is bid per standard ninety-four (94) pound sack delivered to site. Pricing is to include mixing and pumping. Larger unit sizes of cement may be used on-site (i.e., “Super

Sacks”), but bid prices and payment shall be standardized to the ninety-four-pound sack equivalent. The use of any heavy equipment to assist in the mixing and pumping of cement

(i.e., excavator to lift a super sack) shall be considered in this line item.

18.0 Gravel

Gravel is used for a variety of applications including roadbuilding and site stabilization.

Functional requirement:

Gravel will be limestone and size will be determined by the application for which it is being used.

This item is bid per ton delivered to site. This price will include trucking to site.

19.0 Steel Mud Pit

The mud pit is a large tank that contains drilling fluids on-site. Mud pits may also be used to store plugging fluids from the well.

Functional requirement:

The mud pit shall be constructed of steel and have a divider to expedite the settling of cuttings and debris flushed from the well bore.

This item is bid per mud pit.

20.0 Site Reclamation

Site reclamation is the process of restoring the well site area back to original condition.

Site reclamation generally requires earth work and seeding of grass utilizing a combination of lime, fertilizer, seed, and mulch, as appropriate. The minimum quantities of these materials are specified in the reclamation plan. Site reclamation also includes the removal of any well production equipment, installed erosion and sediment controls, and tie mats.

20.1 Site Reclamation – API# 47-105-01416

20.2 Site Reclamation – API# 47-105-01417

Any heavy equipment used during site preparation must meet the functional requirements identified in Item 5. Heavy Equipment.

Performance Requirements:

Site reclamation shall be completed in accordance with the provisions described in the

West Virginia Erosion and Sediment Control Field Manual – May 2012. Note that Section

III of this manual establishes minimum quantities for reclamation materials including lime, fertilizer, seed, and mulch based on site acreage. Site reclamation performance will be evaluated against these parameters.

https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf.

This item is bid as a lump sum per well for all labor, equipment, tools, and materials including lime, fertilizer, seed, and mulch needed to complete site reclamation of the well site (including the soil borrow area, if necessary), as described in the ‘Site Reclamation’ project description in Section V. Topsoil, where necessary, shall be bid separately;

however, all labor associated with that soil will be considered in this bid item. Site reclamation shall also include the removal of all production equipment, installed erosion and sediment controls, and tie mats.

21.0 Silt Fence

A silt fence is a temporary sediment control device used on construction sites to protect water quality in nearby streams, rivers, lakes, and seas from sediment in stormwater runoff.

Silt fence shall be supplied with stakes pre-attached and will be installed during site preparation. Silt fence will also be removed at the completion of reclamation.

https://dep.wv.gov/oil-and-gas/Documents/Erosion%20Manual%2004.pdf

This item is bid per foot. Installation and removal of silt fence shall be included in the site preparation and reclamation line items, respectively.

22.0 Monument

The monument is the permanent marker indicating the location of the plugged well.

Monument and its installation will meet all the requirements in 35 CSR 4 – 5.5.b, including:

● The monument will be a minimum of six (6) inches in outside diameter.

● The monument will extend minimum of thirty (30) inches above final grade and not less than ten (10) feet below the surface.

● The monument will have the well’s API Number permanently attached.

http://apps.sos.wv.gov/adlaw/csr/readfile.aspx?DocId=16899&Format=PDF.

This item is bid per monument installed.

23.0 Welder/Cutting Torch

A welder/cutting torch is necessary for the fusing or cutting of metal components.

This item is bid per hour of use and includes operator. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Heavy Equipment.’)

24.0 Oil Absorbent Supplies

Oil Absorbent Supplies are used to absorb and contain oil as directed by the DEP.

1. Booms will be bid per boom and must be a minimum of ten (10) feet in length.

2. Absorbent pads will be bid by the bundle; pads must be a minimum of two

(2) feet by two (2) feet.

3. Peat sorb will be bid per fifty (50) pond bag.

4. Plastic roll – (100 feet by 50 feet), twenty (20) mil (0.02 inch) minimum thickness, bid per roll.

Items are bid as described above, and shall include installation or deployment costs.

25.0 Sand Pump

A sand pump is a syringe-type cable tool typically between four (4) and six (6) inches in diameter used to pump sand and cuttings from the well bore.

The well bore size will determine the size of the sand pump used.

Item is bid per pump.

26.0 Cherry Picker

A cherry picker is a tool used to retrieve items from the well bore and drill out wooden plugs. This tool is run on the stem and is used in conjunction with jars.

The cherry picker will be a four (4) to eight (8) in diameter tubular four (4) feet in length with a tapered hole and slot. The well bore diameter will determine the precise size of cherry picker.

Item is bid per cherry picker.

27.0 Casing/Tubing Spear

Casing/Tubing Spear is a grapple tool that will go inside of tubing that is inside of the well bore.

Size will be determined by tubing encountered.

1. Tubing Spear 1 inch to 3 ½ inches

2. Casing Spear up to 10 ¾ inches

Item is bid per spear.

28.0 Overshot

Overshot is a grapple tool used to retrieve tubular pipe and casing by going over the outside of item being fished.

Size to be determined by the size of the fish. All grapples and working components must be included.

1. 1 inch to 3 ½ inches

2. Up to 8 ⅝ inches

Item is bid per tool.

29.0 Impression Block

The impression block is a wax block affixed to the bottom of fishing tools to allow for the creation of an impression of hole contents to assist in fishing operations.

Item is bid per impression block.

30.0 Subs

A sub is a short, threaded piece of pipe used to adapt parts of the drilling string that cannot otherwise be screwed together because of differences in thread size or design. Subs may be needed to change over to drill pipe or to retrieve casing from the well bore.

This item is bid per sub.

31.0 Power Swivel

The power swivel is a mechanical device that suspends the weight of the drill string. It is designed to allow rotation of the drill string beneath it, conveying high volumes of high-pressure drilling mud between the rig's circulation system and the drill string.

The power swivel must be a minimum of a twenty-five (25) ton hydraulic unit. The Power

Swivel must include the Power Unit with hoses and connections, also includes two Saver

Subs (one for Drill Pipe and one for Drill Collars).

This item is bid per hour of use.

32.0 Concave Mill

A mill is a tool that grinds metal downhole, typically to remove junk or parts of a casing string.

Mills will include subs needed.

1. 4 ¾ inch mill

2. Up to 8 ⅞ inch mill

Item is bid per mill.

33.0 Mud/mixing pump

A mud pump is a reciprocating piston/plunger pump designed to circulate drilling fluid under high pressure down the drill string and back up the annulus.

This pump must have a minimum of five (5) inch diameter with a seven (7) inch stroke length or larger, and able to supply volumes and pressure as needed. It will include hoses and connections capable of handling the pump output.

Item is bid per hour of use.

34.0 Logging, Bond with CCL

Description

Logging includes all labor, equipment, and material necessary to determine various characteristics of the well and using probative tools suspended from a wire line. Bond logs with casing collar locator (CCL) allows for a determination of the cement bond quality behind the casing and identify the free point of any casing strings present in the well.

Logging includes all labor, equipment, and materials required to complete logging run.

Item is bid per log.

34.5 Wireline Shot/Perforation, Collar Buster

The perforation, severance, or separation of pipe by wireline tools equipped with explosive shots (i.e., collar busters, perf balls) or other wireline mechanical means (i.e., jet-cutter), typically in conjunction with a bond log.

Functional Requirements:

The following sizes may be needed:

1. Up to 3 ½”

2. Up to 8 ⅝”

This item is bid per run.

35.0 Tie Mats

Tie mats are portable structures used to support the weight of heavy equipment.

Minimum size 4’ x 12’. Tie mats may be constructed of natural or synthetic materials.

Item is bid per mat for the duration of the project.

36.0 Topsoil

The excavated area may need to be backfilled with topsoil. The quantity of topsoil will be based on the quantity of soil disposed minus the amount of gravel that is placed along the well.

Item is bid per ton and includes excavation from the borrow area, if applicable, transportation to the site and equipment and labor to level the site. At no time may an individual worker’s hours be billed simultaneously for work completed under this item and any other labor-based item allowing for hourly rate payments (e.g., ‘Rig and Crew’ or ‘Heavy Equipment.’)

37.0 Culvert

A culvert is a pipe intended to channel water.

It is anticipated that culverts of the following size will be needed (diameter x length):

1. 16” x 20’ (sixteen inches by twenty feet)

Culvert may be metal or HDPE.

Item is bid for each culvert.