Technical Requirements Document.docx
DOCX document 97 KB Posted
- Attached to
- Light Interference Filter (LIF)-support the Enhanced Night Vision Goggles (ENVG PSQ-20B)
- Solicitation number
- SPRBL1-26-R-A003
About this file
This is a Technical Specifications and Instructions document for contract SPRBL1-26-R-A003, establishing requirements for the production and delivery of Light Interference Filters (LIF) for the AN/PSQ-20B Enhanced Night Vision Goggles system. The LIF is a critical optical component that enhances night vision by amplifying ambient light. The contractor must ensure all delivered units are form, fit, and function interchangeable with previously fielded configurations per drawing OFM-2021-A1 (NSN 5855-01-611-2113). The document mandates compliance with military standards including MIL-PRF-49257 for coated optical components, MIL-STD-2073-1E for packaging at Military Level of Protection, and MIL-STD-129R for marking. Wood packaging materials must comply with International Standards for Phytosanitary Measures (ISPM) Number 15 with ALSC certification, and all materials must include proper heat treatment or kiln-dried heat treatment markings.
The contractor must establish and maintain an ISO 9001-2015 certified Quality Management System with Government access rights to facilities, quality documentation, and test hardware. Configuration management must follow EIA-649-1 standards with all changes submitted via Engineering Change Proposals, Requests for Variance, or Notices of Revision for Government approval. An Integrated Product and Process Team (IPPT) with Government participation is required, including post-award orientation within 30 days of contract award and as-needed informal reviews. The contractor requires a SECRET facility clearance with SIPRNET access, must develop an Operations Security (OPSEC) Plan within 90 days of award, and must ensure all employees complete DoD Information Assurance Awareness and Level I OPSEC training. The Government reserves the right to conduct independent testing at any time to verify interchangeability and performance. Five Contract Data Requirements (CDRL) items are specified: Engineering Change Proposals, Requests for Variance, Notices of Revision, Failure Analysis and Corrective Action Reports (due within 10-15 working days of failure), and the OPSEC Plan, all to be submitted electronically in Microsoft Office formats.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPRBL126RA003 DD 254-signed.pdf | ||
| Solicitation - SPRBL126RA003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS AND INSTRUCTIONS
SPRBL1-26-R-A003
Light Interference Filter for PSQ-20B
Prepared By: Reviewed By:
| X | X | |
| Matthew Eberhardt | Tim Langan |
TABLE OF CONTENTS
| SCOPE | 3 |
| APPLICABLE DOCUMENTS | 3 |
| CONFIGURATION BASELINE | 4 |
| REQUIREMENTS | 4 |
| INTERCHANGEABILITY, INTERFACE, AND PERFORMANCE CHARACTERISTICS . 5 PACKAGING | 5 |
| ENGINEERING | 7 |
| PROGRAM MANAGEMENT REQUIREMENTS | 7 |
| QUALITY MANAGEMENT | 8 |
| GOVERNMENT TESTING | 9 |
| SECURITY REQUIREMENTS | 9 |
| CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1 | 10 |
| ENGINEERING CHANGE PROPOSAL | 10 |
| REQUEST FOR VARIANCE | 12 |
| NOTICE OF REVISION | 14 |
| FAILURE ANALYSIS AND CORRECTIVE ACTION REPORT | 16 |
| OPERATIONS SECURITY (OPSEC) PLAN | 18 |
SCOPE
This document specifies the tasks and efforts the contractor shall perform during this production contract of the Light Interference Filter (herein LIF) for the AN/PSQ-20B Enhanced Night Vision Goggles. The LIF is a critical component of the Enhanced Night Vision Goggles (ENVG: PSQ- 20B). The ENVG is a night vision system that amplifies ambient light and provides improved night vision. The LIF is an important component that contributes to the improved night vision.
This document provides the technical, safety, and interchangeability requirements for the items being sought under this procurement. The contractor shall ensure that the delivered LIFs comply with the requirements listed in the Requirements section. The offeror is encouraged to use commercial/industrial processes and practices that will reduce design, production, and operational support costs while meeting the requirements of this contract.
APPLICABLE DOCUMENTS
The documents in the table below can be obtained directly from the publisher. The equipment on contract will be produced in accordance with these documents.
The offeror is responsible for reviewing the entire solicitation/contract to identify all directly cited and subsequently referenced documents. Immediately upon completion of this review, the offeror will notify the Procuring Contract Officer (PCO) of any conflicts and/or misunderstandings between this provision and other contractual requirements.
Notes for Government-furnished drawings:
The drawings specified in this solicitation are for reference only and shall be used for interchangeability purposes. They do not contain complete details of all intervening processes, from raw material to finished products, which are necessary to fabricate, control, test, adjust, assemble and inspect the items on order.
Military and Federal Standards
| MIL-STD-129R |
| Military Marking for Shipment and Storage |
| MIL-STD-2073-1E w/Chg. 1 |
| Standard Practice for Military Packaging |
Military and Federal Specifications
| MIL-PRF-49257 |
| Coated Optical Component (COC) (SECRET) |
Other Documents
| 5009737 |
| Light Interference Filter Assembly |
Commercial Documents
| ISPM Number 15 |
| Regulation of Wood Packaging in International Trade |
| ISO/9001-2015 |
| Quality Management Systems Requirements |
| EIA-649-1 |
| Configuration Management Requirements For Defense |
Contracts
Security Documents
| SCG |
| Security Classification Guide for Image Intensifier Devices |
(31 October 2013)
CONFIGURATION BASELINE
The applicable Configuration Baselines (CB), for the listed Configuration Item (CI) and/or Computer Software Configuration Item (CSCI), are as listed in the table below.
| NSN |
| Nomenclature |
| Part Numbers/Drawings |
| 5855-01-611-2113 |
| Filter, Infrared Light |
| OFM-2021-A1 |
The Contractor shall establish a Configuration Management Program in accordance with EIA- 649-1.
No changes or departures from the CB are acceptable except for changes or departures which are submitted in accordance with EIA-649-1, DI-SESS-80639, DI-SESS-80640, and DI-SESS- 80642, and are approved by the Government Configuration Manager (C Mgr.) or Configuration Management Officer (CMO) and which are made applicable to the contract by the PCO.
REQUIREMENTS
The purpose of the LIF is to enhance night vision via the ENVG and is intended for worldwide combat and non-combat field use by the U.S. Military. The Government expects the products to be delivered within the required timeframe, fit for the purpose for which it is intended, and without defects or early life failures (beyond normal wear and tear). In the event of a conflict between the requirements of this document and any other documents specified within, the requirements of this document shall govern.
INTERCHANGEABILITY, INTERFACE, AND PERFORMANCE CHARACTERISTICS
All LIFs delivered under this contract shall be form, fit, and function interchangeable and without degradation of performance with previously fielded LIFs of the same kind as established by the current maintenance concept of the U.S. Army. The U.S. Army maintenance concepts for the LIFs are detailed in the drawings, OFM-2021-A1. The Government may independently verify hardware compliance to the drawing and Product Description at any time during the life of the contract. The contractor shall be required to justify and/or rectify, at no cost to the Government, any identified discrepancies between the hardware performance/configuration and these documents when such discrepancies are identified.
PACKAGING
Preservation, packing and marking for shipment shall be in accordance with Section "D" of the contract. Packaging/packing shall be in accordance with MIL-STD-2073-1E w/Chg 1, Level of Protection (LOP): Military, Level of Pack, (LPK): Quantity Unit Pack (QUP): 001. Marking shall be accordance with MIL-STD-129R.
Marking All unit packs, intermediate packs, and exterior shipping containers shall be legibly and durably marked in accordance with MIL-STD-129R.
Wood Packing Material Wood Packaging Materials (WPM) shall meet the following requirements:
Wood packaging material (WPM) includes but is not limited to pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames and cleats. This requirement excludes materials that have under gone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSB).
All WPM shall meet the requirements of the International Standards for Phytosanitary Measures (ISPM) Number 15, “Regulation of Wood Packaging Material in International Trade”. DoD shipments inside and outside of the United States shall meet the requirements of ISPM 15 whenever WPM is used to ship DoD cargo.
All WPM shall comply with the official quality control program for heat treatment (HT) or kiln dried heat treatment (KDHT) in accordance with American Lumber Standard Committee (ALSC), Incorporated, Wood Packaging Material Program and WPM Enforcement Regulations (see http://www.alsc.org/).
All WPM shall include certification/quality markings IAW the ALSC standard. Markings shall be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides of the pallet and be contrasting and clearly visible. All containers shall be marked on a side other than the top or bottom, contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp.
Failure to comply with these requirements may result in refusal, destruction, or treatment of materials at the point of entry. The Government reserves the right to recoup from the contractor any remediation costs incurred by the Government.
Military Packaging DS7029 Preservation, Packing and Marking Instructions The contractor shall establish, maintain, control and be responsible for the handling, storage, preservation, packaging and shipping to protect the quality of the materials and to prevent damage from loss, deterioration, degradation, or substitution of products.
LEGEND
| Qty |
| Quantity |
| Prot Req |
| Protection Required |
| PGE-REF |
| Packaging Reference (Military Standard) |
| LPK |
| Level of Packing |
| QUP |
| Quantity per Unit Pack |
| ICQ |
| Intermediate Container Quantity |
| Pkg Reqmt Codes |
| Packaging Requirement Codes when PKG-REF cites MIL-STD-2073 |
The below codes are for special markings:
| PC |
| Project Code |
| WG |
| Warranty/Guarantee |
| SL |
| Shelf Life |
| BC |
| Bar Code |
| FMS |
| Foreign Military Sales |
NSN
| Prot Req |
| PKG- REF |
LPK
QUP
ICQ
Special Markings
| Pkg |
| J. |
| J |
| J |
| J |
| J |
| J |
| J |
| J |
| J |
| J |
| Reqmt |
| I. |
| II. |
| III. |
| IV. |
| V. |
| VI. |
| VII. |
| VII.a |
| IX |
| X |
| Codes |
| (MP) |
| (CD) |
| (PM) |
| (WM) |
| (CD) |
| (CT) |
| (UC) |
| (IC) |
| (PK) |
| (SM) |
MIL-
5855-
STD-
01-611-
2073-1E
| 2113 |
| Military |
| w/Chg 1 |
| B |
| 001 |
| - |
| 10 |
| 1 |
| 00 |
| DA |
| NA |
| B |
| D4 |
BC
ENGINEERING
The contractor shall assign, empower and emplace the engineering and production personnel necessary for successful contract performance. The contractor shall design and implement production processes that ensure successful production of all items required under this solicitation/contract. The contractor shall use commercial products, processes and practices whenever practical, to reduce production and operational costs.
PROGRAM MANAGEMENT REQUIREMENTS
The objective of program management is to provide both the contractor and Government with management information and tools required to effectively manage work performed under this contract, minimize system performance risk, and ensure adherence to established program schedule.
Integrated Product and Process Team (IPPT). The Government and contractor shall incorporate an IPPT discipline into the LIF program. The objective of the IPPT is to implement an open shared data/information environment with results oriented objectives of on-schedule delivery of specification- compliant units, continuously improving the various Government/contractor processes, and reducing the system life cycle cost. The IPPT shall also complete the following additional actions throughout the life of the contract, as necessary:
· Hold IPPT reviews
· Use risk management techniques to document, track, and manage program areas of risk
· Review/concur in program documentation
· Review/concur on all Failed Item Analysis Reports (FIARs), ECPs, Variances, and Trade studies.
The IPPT process as described is solely to facilitate communications between the Government and contractor during contract administration. Responsibility for dealing with issues raised and for meeting all contract requirements remains with the contractor. No communication made during the IPPT process may be construed as a change unless specifically designated by the contracting officer.
Reports, Reviews, Meetings. Reports, reviews and meetings shall be required on an as-needed basis for this contract. Where such reviews occur, the contractor is responsible for generating meeting minutes for the Government to review and comment if necessary.
Post Award Conference. The Procuring or Administrative Contracting Officer (PCO or ACO) shall schedule a post award orientation to be held NLT 30 days after contract award. The purpose of the orientation is to ensure mutual understanding of the contract and all obligations and responsibilities of the contractor and the Government. Location of this meeting will be at the contractor’s facility or shall be conducted by telephone.
Informal Reviews. The contractor shall be available for informal reviews and Government visits in addition to the IPPT reviews. The contractor shall participate in an informal meeting, to identify, discuss, and resolve issues on an as-needed basis.
Correspondence Transmission. The contractor shall submit, as a minimum, written program correspondence or documentation via electronic submittal. The preferred method of file submission is via e-mail. Deviations from this requirement are allowed on a case by case basis, with Government verbal concurrence (either Government IPPT chairpersons or Government Contracting Officer).
QUALITY MANAGEMENT
The contractor shall establish, maintain, operate, and continually improve a Quality Management System in accordance with ANSI/ISO/ASQ (E) Q9001-2015.
The government shall have access to the contractor's quality manual at the contractor's facility at any time.
The Government has the right to examine the contractor’s quality management system, inspection system and quality management system documentation including documented statements of a quality policy, documented quality objectives, quality manual, documented procedures and records required by the quality management system standard, documents including records determined by the contractor to be necessary to ensure the effective planning, operation and control of its processes. The documentation can be in any form or type of medium and software. Government has the right to examine and test hardware used for quality management, test or inspection. The Government's examination shall be on the premises of the contractor or supplier, to the extent practicable, at all places and times. The Government’s examination of the contractor’s quality management system, inspection system and quality management system documentation will be conducted in a manner that will not unduly delay the contract work. The Government's examination, whether exercised or not, does not relieve the Contractor of the obligations under the contract.
If the Government performs examinations of the contractor’s quality management system, inspection system, quality management system documentation and test hardware used for quality management, test or inspection on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties.
The Government’s right to examine the contractor’s quality management system, inspection system and quality management system documentation including documented statements of a quality policy, documented quality objectives, quality manual, documented procedures and records required by the quality management system standard, documents including records determined by the contractor to be necessary to ensure the effective planning, operation and control of its processes will be limited to the contractor’s facility and also to suppliers facilities that provide products and/or services valued over 20% of the contract total cost.
GOVERNMENT TESTING
The Government reserves the right to conduct independent testing at any time during the life of the contract to demonstrate the LIF meets the interchangeability and performance requirements outlined in the associated product description. Additional testing may be performed in an operational environment when operated by Soldiers under potential battlefield conditions.
Testing shall verify the LIF will be form, fit, functional, and 100% interchangeable with the previously fielded LIF configuration. Failures during Government testing will be brought to the contractor’s attention for root cause analysis and corrective action.
ENGINEERING AND CONFIGURATION CONTROL DOCUMENTS
When an engineering change is proposed, the contactor shall be required to submit an Engineering Change Proposal (ECP) or a Value Engineering Change Proposal (VECP). ECPs shall be used to document any changes made to the original HMA configuration by the contractor including, but not limited to, design, material or manufacturing process changes. This is to ensure configuration management is maintained throughout the life of the contract.
SECURITY REQUIREMENTS
In performing this contract the contractor will have access to classified information, and will receive and generate classified material. The contractor shall have a SECRET facility clearance with a SECRET safeguarding capability. Contractor will have access to classified information only at the contractor facility. The contractor will require access to FOUO information, Security/Program Classification Guide(s), and the SIPRNET.
The contractor shall refer to the “Security Classification Guide for Image Intensifier Devices” published 31 October 2013, for additional instructions and guidance on the security classification of information and material pertaining to this contract.
The contractor shall have access to classified information and SIPRNET only at the Contractor’s facility. All contractor employees with access to a government info system must be registered in the ATCTS (Army Training Certification Tracking System) at commencement of services, and must successfully complete the DOD Information Assurance Awareness prior to access to the IS and then annually thereafter. All contractor employees and associated sub-contractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DOD and Army training requirements in DoD 8570.01, DoD 8570.01-M and AR 25-2 within six months of appointment to IA/IT functions.
TEMPEST requirements apply.
The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan within 90 calendar days of contract award, to be reviewed and approved by the responsible Government
OPSEC officer. This plan will include a process to identify critical information, where it is located, who is responsible for it, how to protect it and why it needs to be protected. The contractor shall implement OPSEC measures as ordered by the commander. In addition, the contractor shall have an identified certified Level II OPSEC coordinator per AR 530-1.
Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter. Level I OPSEC training is available at the following website: http://cdse.edu/catalog/elearning/GS130.html (Duration: 45 minutes).
Contractor shall comply with FAR 52.204-2, Security Requirements. This clause involves access to information classified “Confidential,” “Secret,” or “Top Secret” and requires contractors to comply with— (1) The Security Agreement (DD Form 441), including the National Industrial Security Program Operating Manual (DoD 5220.22-M); (2) any revisions to DOD 5220.22-M, notice of which has been furnished to the contractor.
Per AR 381-12 Threat Awareness and Reporting Program (TARP), contractor employees must receive annual TARP training by a CI agent or other trainer as specified in 2-4b.
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
Each CDRL is assigned an Exhibit Number in Section J.
CDRL List
CDRL
Data Line No.
DID Identification
Title
| A001 |
| DI-SESS- |
| 80639 |
| Engineering Change Proposal |
| A002 |
| DI-SESS- |
| 80640D |
| Request for Variance |
| A003 |
| DI-SESS- |
| 80642D |
| Notice of Revision |
| A004 |
| DI-RELI- |
| 81315 |
| Failure Analysis and Corrective Action Report |
| A005 |
| DI-MGMT- |
| 80934C |
| Operations Security (OPSEC) Plan |
ENGINEERING CHANGE PROPOSAL
An Engineering Change Proposal (ECP) describes the changes to be made to the CI/CSCI and all associated Government documents and data that are affected by the proposed engineering change.
ECP should be prepared in accordance with EIA-649-1, Section 3.3.1, and DI-SESS-80639.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item) Original Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
A001
TDP X TM OTHER
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
| Light Interference Filter |
| SPRBL126RA003 |
| TBD |
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
Engineering Change Proposal
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED TOTAL PRICE
DI-SESS-80639
AMSEL-LCE-INV
INSERT
| 7. DD 250 REQ | |
| 9.DIST STATEMENT REQUIRED | |
| 10. FREQUENCY | |
| 12. DATE OF FIRST SUBMISSION | |
| 14. | DISTRIBUTION |
IN
LT
| ASREQ |
| SEE ITEM 16 |
b. COPIES
SECT. B
| 8. APP CODE |
| N/A |
| 11. AS OF DATE |
| 13. DATE OF SUBSEQUENT |
SUBMISSION
a. ADDRESSEE
Draft Final
SEE ITEM 16
Reg
Repro
16. REMARKS:
The contractor shall prepare and submit Engineering Change Proposal in accordance with EIA-649-1 and this DID when a change to a contractual baseline document is deemed necessary.
The Government will have 30 days to review, accept, and/or comment on the draft submission. The contractor shall incorporate changes into the electronic deliverable within 30 days after receipt of Government comments. The Government will have 30 days to review, accept, and/or comment on the final submission.
Data shall be submitted and exchanged electronically in Microsoft Office suite of applications (MS Word, Excel, Power Point, Access, and Project). Alternate formats may be allowed subject to Government review and approval.
E-mail notification is required with any electronic submission.
AMSEL-LCE-INV
FCDD-ISE-HDD
QAR
PCO
ACO
| 15. TOTAL |
| 0 |
| 5 |
| 0 |
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
Matthew Eberhardt
FCDD-ISE-HDD
General Engineer
Timothy Langan
FCDD-ISE-HDD
Branch Chief
REQUEST FOR VARIANCE
A Request for Variance (RFV) is a specific written authorization to depart from a particular requirement(s) of an item’s approved configuration documentation for a specific number of units or a specified period of time, either as an advance request or after the fact. The contractor shall identify the impact of the RFV on performance, operational readiness and logistics support of the affected CIs. The Government may require consideration for any RFV.
RFV should be prepared in accordance with EIA-649-1, Section 3.3.2, and DI-SESS-80640.
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item) Original Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
A002
TDP X TM OTHER
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
| Light Interference Filter |
| SPRBL126RA003 |
| TBD |
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
Request For Variance
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED TOTAL PRICE
DI-SESS-80640
AMSEL-LCE-INV
INSERT
| 7. DD 250 REQ | |
| 9.DIST STATEMENT REQUIRED | |
| 10. FREQUENCY | |
| 12. DATE OF FIRST SUBMISSION | |
| 14. | DISTRIBUTION |
IN
LT
| ASREQ |
| SEE ITEM 16 |
b. COPIES
SECT. B
| 8. APP CODE |
| N/A |
| 11. AS OF DATE |
| 13. DATE OF SUBSEQUENT |
SUBMISSION
a. ADDRESSEE
Final
SEE ITEM 16
16. REMARKS: The contractor shall prepare and submit Request For Variance in accordance with EIA-649-1 and this DID when a departure from a contractual baseline document is deemed necessary.
The Government will have 30 days to review, accept, and/or comment on the draft submission. The contractor shall incorporate changes into the electronic deliverable within 30 days after receipt of Government comments. The Government will have 30 days to review, accept, and/or comment on the final submission.
Data shall be submitted and exchanged electronically in Microsoft Office suite of applications (MS Word, Excel, Power Point, Access, and Project). Alternate formats may be allowed subject to Government review and approval.
E-mail notification is required with any electronic submission.
AMSEL-LCE-INV
FCDD-ISE-HDD
QAR
PCO
ACO
| 15. TOTAL |
| 0 |
| 5 |
| 0 |
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
Matthew Eberhardt
FCDD-ISE-HDD
General Engineer
Timothy Langan
NOTICE OF REVISION
A Notice of Revision (NOR) shows the detailed changes that must be made to technical documentation, except specifications, following approval of an ECP. A NOR shall be submitted for each document affected by an ECP.
NOR should be prepared in accordance with EIA-649-1, Section 3.3.4, and DI-SESS-80642.
CONTRACT DATA REQUIREMENTS LIST
Original Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
A003
TDP X TM OTHER
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
| Image Intensifier Tube |
| SPRBL126RA003 |
| TBD |
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
Notice of Revision
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED TOTAL PRICE
DI-SESS-80642
AMSEL-LCE-INV
INSERT
| 7. DD 250 REQ | |
| 9.DIST STATEMENT REQUIRED | |
| 10. FREQUENCY | |
| 12. DATE OF FIRST SUBMISSION | |
| 14. | DISTRIBUTION |
IN
LT
| ASREQ |
| SEE ITEM 16 |
b. COPIES
SECT. B
| 8. APP CODE |
| N/A |
| 11. AS OF DATE |
| 13. DATE OF SUBSEQUENT |
SUBMISSION
a. ADDRESSEE
Final
SEE ITEM 16
16. REMARKS: The contractor shall prepare and submit Notice of Revision in accordance with EIA-649-1 and this DID when a change to a contractual baseline document is deemed necessary.
The Government will have 30 days to review, accept, and/or comment on the draft submission. The contractor shall incorporate changes into the electronic deliverable within 30 days after receipt of Government comments. The Government will have 30 days to review, accept, and/or comment on the final submission.
Data shall be submitted and exchanged electronically in Microsoft Office suite of applications (MS Word, Excel, Power Point, Access, and Project). Alternate formats may be allowed subject to Government review and approval.
E-mail notification is required with any electronic submission.
AMSEL-LCE-INV
FCDD-ISE-HDD
QAR
PCO
ACO
| 15. TOTAL |
| 0 |
| 5 |
| 0 |
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
Matthew Eberhardt
FCDD-ISE-HDD
General Engineer
Timothy Langan
FAILURE ANALYSIS AND CORRECTIVE ACTION REPORT
The contractor shall report each conformance test failure verbally to the Government Quality Assurance Representative (QAR) and the Technical Activity (see Block 16 of DD Form 1423 for DI-RELI-81315 for phone number) within one working day. Within fifteen working days of failure occurrence, the contractor shall submit a written failure report through the cognizant QAR to the Technical Activity as required by the DD Form 1423 for DI-RELI-81315. In addition to the information required by DI-RELI-81315, the report shall include:
a) Contractor's name, address and applicable contract number.
b) Number of units in sample and number of failed units subjected to test.
c) Root cause of failure.
d) Environmental re-inspection plan to validate the corrective action, consisting of all applicable environmental test and examinations. The plan shall include identification of previous functional, environmental and reliability tests, if any, invalidated by the corrective action changes and recommendations of those tests which should be repeated to prove the corrective action.
e) Proposed disposition of items in the inspection lot at time of failure of any and all inspections during environmental test and of items manufactured under the same conditions and which the Government considers subject to the same failure mechanism.
Failure Analysis and Corrective Action Report
CONTRACT DATA REQUIREMENTS LIST
Original Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
A004
| B. EXHIBIT |
| C. CATEGORY: |
TDP TM OTHER SESS
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
SPRBL126RA003
F. CONTRACTOR
TBD
Light Interference Filter
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE
17. PRICE GROUP
Failure Analysis and Corrective Action Report
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
DI-SESS-81315B
AMSEL-LCE-INV
INSERT
| 7. DD 250 REQ |
| 9.DIST STATEMENT |
REQUIRED
| 10. FREQUENCY |
| 12. DATE OF FIRST |
SUBMISSION
14. DISTRIBUTION
IN
LT
| ASREQ |
| SEE ITEM 16 |
a. ADDRESSEE
b. COPIES
SECT. B
8. APP CODE
| N/A |
| 11. AS OF DATE |
| 13. DATE OF SUBSEQUENT SUBMISSION |
Final
16. REMARKS: Data Item Description (DID) reference to MIL specs/stds is for guidance only.
Failure reports shall be submitted within 10 days of failure occurrence.
Technical Activity Representative is Dolapo Junaid.
Each draft and the final submissions shall be delivered in a format, compatible with Microsoft Office software delivered by e-mail.
Alternative delivery methods may be discussed and agreed upon with the Contracting Officer prior to delivery. E-mail notification is required with any electronic submission.
AMSEL-LCE-INV RDER-PRA-CA PCO
ACO
QAR
| 15. TOTAL |
| 4 |
| 4 |
| 0 |
G. PREPARED BY
| H. DATE |
| I. APPROVED BY |
J. DATE
Matthew Eberhardt
General Engineer
Matthew Eberhardt
OPERATIONS SECURITY (OPSEC) PLAN
CONTRACT DATA REQUIREMENTS LIST
Original Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
A005
B. EXHIBIT
C. CATEGORY:
TDP TM OTHER MGMT
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
SPRBL126RA003
F. CONTRACTOR
TBD
Light Interference Filter
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE
17. PRICE GROUP
Operations Security (OPSEC) Plan
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE
18. ESTIMATED
TOTAL PRICE
DI-MGMT-80934C
AMSEL-LCE-I
INSERT
7. DD 250 REQ
9.DIST STATEMENT
REQUIRED
10. FREQUENCY
12. DATE OF FIRST
SUBMISSION
14. DISTRIBUTION
IN
LT
ASREQ
90 DAC
a. ADDRESSEE
b. COPIES
SECT. B
8. APP CODE
N/A
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
Final
A
SEE ITEM 16
16. REMARKS: Submit OPSEC Plan within 90 Days After Contract Award.
All deliveries shall be delivered in a format, compatible with Microsoft Office software delivered by e-mail and by CD-R, CD+R Compact Disc, DVD-R or DVD+R 4.7GB Digital Versatile Disc.
Alternative delivery media may be discussed with the Contracting Officer prior to delivery.
E-mail notification is required with any electronic submission.
AMSEL-LCE-I PCO
ACO
15. TOTAL
G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
Matthew Eberhardt
Timothy Langan image1.wmf