Technical Exhibit-1/2

Estimated Workload Data and Record of Service

Following workload has to be done and documented in a as per manufacturer specifications and GUV checklists

Maintenance Work of OSEC-B and OSEC-L Stations as follows:

(Bldg # 5910, 8034, 8150, 5, 5259A, 8206 and 6640)

- Visual control of the complete system and onsite inspection with the operating personnel so that eventual difficulties within the maintenance scope can be considered

- Realization of maintenance instruction before maintenance of each equipment to know definite maintenance requirements

- Take preparation system with hydrochloric acid flushing of complete system according to manufacturer instructions with documentation out of operation

- Cell draining of electrolysis equipment

- Exchange per manufacturer information all attrition and maintenance parts

- Documentation of cell conditions (digital photo)

- Cell exchange if necessary

- Take systems engineering with inspection and control of setting parameter and if necessary new adjustment into operation

- Testing of peripheral equipment in detail

- Ventilator with flow switch

- Function and tightness of brine pump

- Testing floating switch for brine flow

- Testing floating switch for cell standard

- Filling level switch of the product container

- Water dosage equipment

- Adjust cell voltage, cell stream

- Check adjustments PCU-Fuzzy

- Dismantling of the dosage unit for chloride and fluoride (2 times each dosage pump)

- Replacement of fair wear and tear parts at back safety valves and membranes

- Tightness check of hose connections and replacement if necessary

- Visual and tightness check of dosage line and replacement if necessary

- Visual and tightness check of pipe connection lines of the system, overhaul if necessary

- Visual check of the electrical connection lines, repair of damages

- Putting out of operation of the measuring technique, control and plausibility check of adjustment values

- Replacement of the electrolytic agent of the equipment (warning devices, measuring cells) and replacement of fair wear and tear parts according to manufacturer instructions (grinding sand, measuring electrodes, gaskets)

- Zero point adjustment of the measuring amplifier, calibration of the measuring result with new calibration solvents

- Adjustment of the control path

- Documentation of total hand measurements

- Turning over of the broom clean chlorination station

- Re-inspection after two hours of operation

- Hand over completed maintenance check list

- Site inspection with operating personnel and explanation of maintenance complexity

- Including big service Kit material. (Sealings, hoses, Electrolyte, pump service kit, o-rings)

- Including WALLACE + TIERNAN, SIEMENS and ProMinent brand equipment check

Maintenance Work of OSEC-A Stations as follows:

(Bleidorn AFH, Bldg # 5080, 5081, 5082, 5084, 5093, 5094, 5095, 5096, 5099 and 5107) (will changed to Chlor- Diox systems)

- Visual control of the complete system and onsite inspection with the operating personnel so that eventual difficulties within the maintenance scope can be considered

- Prior to the maintenance work the operating instructions for the single equipment must be read to get familiar with the exact maintenance scope

- Putting out of operation of the OSEC-A Station

- Emptying of cells of the electrolytic system

- Replacement of all fair wear and tear and maintenance parts according to manufacturer instructions

- Removal and complete mounting of the electrode component

- Documentation of the cell condition (digital photos)

- Replacement of cell, if necessary

- Putting into operation of the system to include checking and control of the adjusting parameter and re-adjustment if necessary

- Thoroughly testing of peripheral equipment

- Function and tightness of brine pump

- Testing floating switch for brine flow

- Testing floating switch for cell standard

- Filling level switch of the product container

- Water dosage equipment

- Adjust cell voltage, cell stream

- Dismantling of the dosage unit for chloride and fluoride (2 times each dosage pump)

- Replacement of fair wear and tear parts at back safety valves and membranes

- Tightness check of hose connections and replacement if necessary

- Visual and tightness check of dosage line and replacement if necessary

- Visual and tightness check of pipe connection lines of the system, overhaul if necessary

- Visual check of the electrical connection lines, repair of damages

- Putting out of operation of the measuring technique, control and plausibility check of adjustment values

- Replacement of the electrolytic agent of the equipment (warning devices, measuring cells) and replacement of fair wear and tear parts according to manufacturer instructions (grinding sand, measuring electrodes, gaskets)

- Zero point adjustment of the measuring amplifier, calibration of the measuring result with new calibration solvents

- Adjustment of the control path

- Documentation of total hand measurements

- Turning over of the broom clean chlorination station

- Re-inspection after two hours of operation

- Hand over completed maintenance check list

- Site inspection with operating personnel and explanation of maintenance complexity

- Including big service Kit material. (Sealings, hoses, Electrolyte, pump service kit, o-rings)

- Including WALLACE + TIERNAN, SIEMENS and ProMinent brand equipment check.

Maintenance work at DIOX Chlorination stations:

(Bleidorn AFH, Bldg # 5080, 5085, 5986, 5087, 5088, 5089, 5092 and 5097 and after replacement Bleidorn AFH, Bldg # 5080, 5081, 5082, 5084, 5093, 5094, 5095, 5096, 5099 and 5107)

Chloride feed station (sodium chloride) (total 3 ea) storage tank 100 liters. Suction lance chlorine electrolysis-systems, complete (10 piece total) Type: )SEC A with storage containers, operating water equipment complete with solenoid valve, diaphragm metering pumps with quantity proportional control, 500 liter pressure container, water meter, as well as existing E-wiring and so forth are to be checked/inspected as per manufacturer specifications and GUV checklists.

-Including big service Kit material. (Sealings, hoses, Electrolyte, pump service kit, o-rings) -Including WALLACE + TIERNAN, SIEMENS and ProMinent brand equipment.