DASHIELDS LOCKS AND DAM
SCOPE OF WORK AND SPECIFICATIONS TO REPLACE MIDDLE AND RIVER WALL
BUILDINGS’ EPDM SHEET ROOFS
Table of Contents
SCOPE OF WORK
1. GENERAL REQUIREMENTS
General
1.1.1. Middle Wall Building Roof
1.1.2. River Wall Building Roof
1.1.3. Labor and materials
1.1.4. Existing items
1.1.5. Protection
1.1.6. Existing roofs
Safety Requirements
1.2.1. Accident Prevention Plan (APP)
1.2.2. Risk Management
1.2.3. Implementation of Safety and Occupational Health (SOH) Program
1.2.4. Mishap Reporting
1.2.5. Hazardous Material Exclusion
1.2.6. Unforeseen Hazardous Material
1.2.7. Damage Reports
1.2.8. Minimum Personal Protective Equipment
1.2.9. Designated Persons
Project Government personnel contacts Certification of Compliance Project/Site Conditions
1.5.1. Reference Drawings
1.5.2. Verification of Field Conditions
1.5.3. Work Areas
1.5.4. Time of Performance
1.5.5. Period of Performance (PoP)
1.5.6. Permits
Protection of Government Property Inspections and Acceptance of Work Points of Contact (POCs) Security Requirements-AT/OPSEC
1.9.1. Anti-Terrorism (AT) Level I Training
1.9.2. 2. Access and General Protection and Security Policy and Procedures
1.9.3. 2b. For contractors who do not require Common Access Card (CAC), but require access to a DOD facility or installation
1.9.4. 4. Suspicious Activity Reporting Training
1.9.5. 15. Pre-screen candidates using E-Verify Program
1.9.6. Employee Identification and Background Check
SPECIFICATIONS- ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
2. DETAILED REQUIREMENTS
References Description of Roof Membrane System Submittals Quality Assurance
2.4.1. Pre-roofing Conference
2.4.2. Fire Resistance
Delivery, Storage, and Handling
2.5.1. Delivery
2.5.2. Storage
2.5.3. Handling
Environmental Requirements Sequencing Warranty
2.8.1. Roofing System Installer Warranty
2.8.2. Roof Membrane Manufacturer Warranty
2.8.3. Continuance of Warranty
Operations and Maintenance manual/data Conformance and Compatibility
3. Products
Materials
3.1.1. EPDM Sheet
3.1.2. Energy Performance
3.1.3. Seam Tape
3.1.4. Lap Splice Adhesive
3.1.5. Bonding Adhesive
3.1.6. Lap Cleaner, Lap Sealant, and Edge Treatment
3.1.7. Water Cutoff Mastic/Water Block
3.1.8. Membrane Fasteners and Plates
3.1.9. Stress Plates for Fasteners
3.1.10. Auxiliary Fasteners
3.1.11. Powder-Driven Fasteners
3.1.12. Metal Disks
3.1.13. Roof Insulation below EPDM Sheet
3.1.14. Wood Products
3.1.15. Membrane Liner
3.1.16. Flashing Cement
3.1.17. Roof Joists
3.1.18. Uplift Clips
3.1.19. Roof Sheathing
3.1.20. Continuous Nailer
3.1.21. Fall Protection Rooftop Anchors
3.1.22. Flashings
3.1.23. Roof Drains
4. Execution
Examination Application
4.2.1. Special Precautions
4.2.2. EPDM Sheet Roofing
4.2.3. Application Method
Substrate Preparation Application of Insulation
4.4.1. Protection of Aluminum
4.4.2. Connections and Jointing
4.4.3. Reglets
Coordination Requirements Fully Adhered Membrane Application
4.6.1. Tape Seams / Lap Splices
4.6.2. Adhesive Seams / Lap Splices
4.6.3. Perimeter Attachment
4.6.4. Securement at Base Tie-In Conditions
4.6.5. Wooden Elevated Cover
Isolated Paver Blocks Set-On Accessories Correction of Deficiencies
Clean Up Protection of Applied Roofing
4.11.1. Temporary Flashing for Permanent Roofing
4.11.2. Temporary Walkways, Runways, and Platforms
Field Quality Control
4.12.1. Construction Monitoring
4.12.2. Roof Drain Test
Information Card
5. Measurement and Payment
6. Attachments:
Attachment 1 – Reference Drawings Attachment 2 - Photos Attachment 3 – Accident Prevention Plan Template Attachment 4 – Quality Control Plan Template Attachment 5 - SK-1.1 and SK 1.2 Dashields Fall Protection Locations Attachment 6 - SK-2 Wooden Elevated Cover Attachment 7 - Submittal Register
SCOPE OF WORK
1. GENERAL REQUIREMENTS
General
The work is located at 100 Dashields Lock Road, Coraopolis, PA 15108-5417. The site of the work may be reached from state and local roads and streets. The purpose of this contract is to replace the EPDM sheet roof systems of two Lock buildings. One building is located on the Middle Wall and one building is located on the River Wall of the Lock. All work shall be done in a professional manner and in accordance with industry standards. The roof systems shall be replaced as specified herein and provide a water tight seal upon completion of the work.
The contractor shall install anchor points for use in a personal fall arrest system to permit safe personnel access to the entire roof surfaces. The contractor shall install two roof-mounted, fall protection rooftop anchorages, tie-off points on the main Middle Wall roof and two more on the River Wall roof. Each anchorage shall be rated for one person. These tie-off points shall be mounted on top of the membrane for ease of inspection. The four locations are shown on SK-1.1 and SK-1.2 within Attachment 5. These anchorage points can be utilized during performance of the work and must be left permanently installed upon completion of the roof replacement.
The only direct access from the Land Wall to the Middle and River Walls are the walkways over the lock gates, which are Aluminum grating. The Contractor is responsible for getting materials and equipment over to the buildings. All instances where Government materials, supplies, property, and/or equipment are damaged, shall be reported immediately to the Contracting Officer (KO) and Lockmaster. All damage to existing government property as a result of the Contractor’s work shall be repaired or replaced to the satisfaction of the Contracting Officer.
1.1.1. Middle Wall Building Roof
The main roof is approximately 30 feet by 18 feet, or 540 square feet. There is also a small roof, above the 1st floor entrance door, with approximate dimensions of 4 feet by 5.5 feet, which shall also be replaced. New flashing, vent covers, and caps shall be installed on pipe vents protruding from roof surface. The existing roof ventilator shall be removed and reinstalled. The antennas shall be supported in place and remain functional during the roof replacement. Project personnel will designate a laydown area next to the worksite which can be used to store materials. All debris to include existing roofing materials must be removed from the lock walls daily.
Removal and or abatement of lead based paint (LBP)/lead dust is anticipated. The building shall be tested for lead (LBP/lead dust) prior to the commencement of demolition activities. If sampling confirms the presence of LBP/lead dust, a written lead compliance plan shall be required.
1.1.2. River Wall Building Roof
This roof is approximately 61 feet by 18 feet, or 1100 square feet. New flashing, vent covers, and caps shall be installed on pipe vents protruding from the roof surfaces. The wooden elevated cover with approximate dimensions of 9 feet by 16 feet shall be removed and replaced with wooden joists and sheeting. The two roof ventilators shall be removed and disposed of by the contractor. The antennas shall be supported in place and remain functional during the roof replacement. Project personnel will designate a laydown area next to the worksite which can be used to store materials. All debris to include existing roofing materials must be removed from the lock walls daily.
1.1.3. Labor and materials
The contractor shall provide all labor and materials necessary to replace the existing built up roof, roof drains, and associated items. Details of the building construction are shown on the attached reference drawings. The work shall include removal and disposal of all roofing materials over the entire roof down to its substrates of existing concrete, steel decking, or wood deck, including all flashing, roof drains, flashing around base of the stack, and installation of new tapered insulation, flashing, roof drains, and all other work to furnish all equipment, labor, layout of work, supervision, and materials necessary to complete the work as shown and as specified. The Contractor shall be responsible for transport of materials to the site and to prevent demolished materials from entering the river. All material provided in the performance of this contract shall be unused and meet the requirements of the specifications. The antennas on the existing roofs shall be temporarily supported during replacement of the roofs. They shall remain connected and functional during the performance of the work.
1.1.4. Existing items
The EPDM shall have a proper waterproof seal around all existing items that protrude thru or from the roof.
1.1.5. Protection
The antennas shall be cribbed so the contractor can work underneath, removing roofing material and installing the new roofing. The antennas, and any other surface bearing items, shall have paver blocks on a layer of reinforced membrane or walkpad applied over the completed roof membrane to protect the new roof, as discussed in Isolated Paver Blocks.
Electric or communication lines will stay in place and should not be disturbed.
1.1.6. Existing roofs
Refer to photos within Attachment 2 for existing roof conditions. The Middle Wall roof is 540 square feet and its substrate consists of steel decking on steel C joints. The River Wall roof is 1100 square feet and its substrate consists of concrete, except an area, consisting of wood, of approximately 144 square feet. The Contractor shall verify dimensions and clearances in the field before beginning work. This includes a lip of approximately 18 inches around the perimeter of each roof. Roof elevation is approximately 20 feet above each lock wall. The existing roof system is about 4 inches thick and consists of the following layers over the concrete substrate:
o Mopped asphalt o 2 ply built up roof o 0.5-inch wood fiber board o 3.5 to 1.5-inches of tapered insulation
Safety Requirements
In addition to the detailed requirements included in the provisions of this contract, all work shall comply with the most recent edition of the USACE Engineering Manual (EM) 385-1-1, “Safety and Health Requirements Manual”, and all applicable federal, state, and local laws, ordinances, criteria, rules, and regulations. If there are any standards that require interpretation, submit matters to the appropriate administrative agency for resolution before the commencement of work. Where the requirements herein, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
The Superintendent, QC Manager, and SSHO are subject to dismissal if any of the required regulatory requirements are not being effectively carried out. If dismissal occurs, project work will be stopped and no work shall proceed until a suitable replacement is approved and the appropriate requirements are assured to be effectively carried out.
The latest version of the EM 385-1-1 is available online at:
https://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385- 1-1.pdf?ver=2015-04-09-142531-467.
1.2.1. Accident Prevention Plan (APP)
An Accident Prevention Plan (APP) is a safety and health policy and program document that shall be contract- and/or job-specific. The APP shall be developed by the Contractor and shall interface with the Contractor's overall Safety and Health Program, such that any portions of the Contractor's overall program referenced in the APP shall be included as appropriate.
The Contractor shall develop the APP in accordance with EM 385-1-1, Appendix A, and shall address each of the elements/sub-elements in the outline contained in the appendix in the order that they are provided in the manual, and as supplemented herein. If an item is not applicable because of the nature of the work to be performed, the Contractor shall state this exception and provide a justification. The APP shall be written in English by the Prime Contractor and shall articulate the specific work, work processes, equipment to be used, and hazards pertaining to the contract. The non-mandatory APP Checklist, Form A-2 of the EM 385-1-1, may be used to ensure each area of required information has been provided as part of the APP to the Contracting Officer.
The Contractor's APP shall be job-specific and must include work to be performed by subcontractors. It is understood that the APP is submitted prior to work starting and some of the project-specific information is not yet known. If sub-contractors and/or suppliers are not known at the time of initial APP submission, the Contractor shall include the following statement in their APP: "The subcontractors for the following defined features of work (DFOW)/activities are not known at this time, but additional information will be submitted to the APP for acceptance prior to the start of any activities listed." All known information shall be provided and additional information submitted to the Contracting Officer for acceptance as it becomes known.
Once accepted by the Contracting Officer, the APP and all attachments will be enforced as part of the contract. Disregarding provisions of this contract or the accepted APP is a cause for stopping of that portion of the work at the direction of the Contracting Officer until the matter has been rectified.
A copy of the accepted APP shall be available on the worksite at all times, and each sub-contractor shall be provided a copy to comply with. A signature log shall be completed by each sub-contractor foreman attesting that they have read and understand the APP.
The Contractor shall provide on-going evaluations of the APP throughout the life of the project. Changes, revisions, and updates to the APP shall be reviewed and accepted by the Contracting Officer, project superintendent, SSHO, and Quality Control Manger. An APP template is provided in Attachment 3.
1.2.2. Risk Management
Risk management is a business process that includes the identification, assessment, and prioritization of risks, followed by coordinated and economical application of resources to minimize, monitor, and control the probability and/or impact of unfortunate events to an acceptable level. A risk management assessment tool, such as activity hazard analysis (AHA), job safety analysis (JSA), or job hazard analysis (JHA) shall be developed by the contractor performing the work for each activity, task, or defined feature of work (DFOW).
The assessment shall identify the work sequence, specific anticipated hazards, site conditions, equipment, materials, personnel, and the control measures to be implemented to control the hazards. A Risk Assessment Code (RAC) shall be assigned to each job step based on the residual risk remaining after controls are implemented. A RAC shall then be assigned to the overall activity consistent with the highest RAC identified for the job steps. If developed by a subcontractor, the Prime Contractor shall review and approve the assessment before submission to the Contracting Officer. The Risk Assessment shall be signed by the SSHO, Superintendent, QC Manager, and any subcontracting Foreman's performing the work. If Qualified or Competent Persons are required for a particular activity, they shall be identified and included in the assessment, and their competency/qualification identified. Work shall not begin until the assessment has been accepted by the Contracting Officer and discussed with all engaged in the activity.
These risk assessment tools are considered living documents and shall be updated as needed. If the RAC increases from what was originally accepted by the Contracting Officer, the assessment shall be re-submitted for acceptance prior to work proceeding. Changes that do not increase the RAC are not required to be resubmitted for acceptance.
The risk assessment shall be developed in accordance with EM 385-1-1 Section 1, or as specified by the Contracting Officer. Risk assessments shall be submitted for review at least 15 working days prior to the start of the activity, task, or defined feature of work is set to begin. The Government reserves the right to require the Contractor to revise and resubmit any documents if they fail to effectively identify the work sequence, specific anticipated hazards, site conditions, equipment, materials, personnel, and the control measures to be implemented.
Each employee performing work as part of an activity, task, or defined feature of work shall review the risk assessment for the activity and sign the signature log designated for the assessment prior to beginning work. A signature log shall be maintained for each risk assessment.
Completed risk assessments need not be submitted at the time of the APP submission, but the Contractor shall identify each activity, task, or DFOW that will require a risk assessment to be completed at the time of submission.
1.2.3. Implementation of Safety and Occupational Health (SOH) Program The Contractor shall employ a minimum of one Competent Person at each project site to function as the primary Site Safety and Health Officer (SSHO) to implement and administer the Contractor’s safety program and the Government-accepted Accident Prevention Plan
(APP). The SSHO is a full-time responsibility and shall be an employee other than the supervisor [unless specified differently in the contract and coordinated with the local SOH Office], that reports directly to a senior project, or corporate, official. The SSHO shall be present at the project site and be located so they have full mobility and reasonable access to all major work operations during the shift. The SSHO shall meet all training and experience qualifications as outlined in EM 385-1-1 Section 01, Paragraph A.17.
For projects with multiple shifts, or in instances where the SSHO is off-site for a period longer than 24 hours, an Alternate SSHO shall be assigned to ensure coverage for the project at all times work activities are conducted. The alternate SSHO shall meet the same requirements and assume the responsibilities of the primary SSHO. The alternate SSHO shall be identified in the applicable AHAs for the activities they are responsible for overseeing.
When the primary SSHO is temporarily, up to 24 hours, off-site, a Designated Representative (DR) may be used in lieu of an Alternate SSHO. The DR shall be on the project site at all times when work is being performed in the absence of the primary SSHO.
DRs can be collateral duty safety personnel, with safety duties assigned in addition to their full-time occupation. DRs shall perform safety program tasks as designated by the SSHO, and report all findings to the SSHO. DRs shall also be appointed when activities, tasks, or DFOWs contain multiple sites and are more than 45 minutes travel time from the primary SSHO's duty location. The DR shall be identified in the applicable AHAs for the activities they are responsible for overseeing.
Note: DRs may not be assigned to projects or activities that have a risk assessment code (RAC), as identified on the AHA for the activity, level of high or extremely high.
The SSHO may also serve as the Quality Control Manager. The SSHO may not serve as the Superintendent.
SSHOs shall attend the pre-construction conference, pre-work meetings, including preparatory and periodic in-progress meetings.
1.2.4. Mishap Reporting
A mishap is any unplanned, undesired event that occurs during the course of work being performed, to include, accidents, incidents, and near misses. All mishaps shall be reported to the Contracting Officer within 24-hours after notification from the affected employee(s).
Contractors are responsible for maintaining an OSHA Log of Work Related Injuries and Illnesses (Form 300) and complying with all reporting and recordkeeping requirements specified in 29 Code of Federal Regulations (CFR) 1904.
1.2.5. Hazardous Material Exclusion
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with EM 385-1-1 such as, nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury, polychlorinated biphenyls (PCBs), Diisocyanates, lead, lead-based paint (LBP), and hexavalent chromium, are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. Low mercury lamps used within fluorescent lighting fixtures are allowed as an exception without further Contracting Officer approval.
Notify the Radiation Safety Officer (RSO), Safety Office, and the Contracting Officer prior to excepted items of radioactive material and devices being brought on site.
1.2.6. Unforeseen Hazardous Material
USACE shall identify and communicate all known hazardous materials such as Polychlorinated biphenyls (PCBs), lead paint, asbestos, and other OSHA regulated chemicals (i.e. 29 CFR 1910.1000) in which the Contractor may come into contact during the course of activities. If material is encountered that was not indicated, but may be hazardous to human health upon disturbance, that portion of the work shall stop and the Contracting Officer immediately notified. The Government will determine within 14 days of notification if the material is or is not considered hazardous. If the material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If the material is determined to be hazardous or dangerous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to FAR 52.243-4, Changes and FAR 52.236-2, Differing Site Conditions.
1.2.7. Damage Reports
All instances where Government materials, supplies, property, and/or equipment are damaged, shall be reported immediately to the Contracting Officer and Lockmaster.
1.2.8. Minimum Personal Protective Equipment
Personal Protective Equipment (PPE) is governed in all areas by the nature of work personnel are performing based on conducted hazard evaluations. AHAs shall detail the PPE to be used that will provide appropriate protection for the work to be performed when required. All PPE shall be provided by the Contractor, used, and maintained in a sanitary and reliable condition whenever the hazard dictates use.
Mandatory PPE, at minimum, shall include: hard hat (construction sites), long pants, short sleeve shirts, and leather or protective work shoes or boots. Personal Floatation Devices (PFDs) shall be worn at all times when beyond the yellow line on the Land Wall.
1.2.9. Designated Persons
The Contractor shall provide Qualified and/or Competent Persons in accordance with EM 385-1-1, OSHA, ANSI, and where specified herein. All Qualified and Competent Persons shall be designated in writing and shall meet the requirements for the specific activity for which they are designated.
Competent Persons identified in the Contractor’s Safety and Health Program and Government-accepted APP shall be onsite at all times when the work that presents the hazards associated with the competency is being performed.
Certificates of Qualification/Competency shall be provided to the Contracting Officer for review and provided as part of the applicable AHAs and appendices of the APP.
Project Government personnel contacts
A pre-quote site visit will be arranged by the KO. Participation is highly encouraged. Pre-work notifications are required. Coordination with the projects for early planning and tentative schedule compilation purposes and schedule submission is expected. Advance notice to the Lock and Dam personnel at least 30 days prior to the inspection visits is required. The appropriate Government contact is listed by location, along with their telephone number, as shown in section POCs.
Certification of Compliance
For all proposed equipment or materials to be furnished under this contract, the Contractor shall furnish a statement signed by an official authorized to certify on behalf of the manufacturer of a product, system, or material, attesting that the product, system, or material meets the specified requirements. The statement must be dated after the award of the contract, must state the Contractor's name and address, must name the project and location, and must list the specific requirements which are being certified. The Certificate of Compliance shall be submitted prior to shipment of equipment or materials or the incorporation of equipment or materials into the finished work. In no case shall the Government’s right to inspect supplies under the inspection provisions of this contract be prejudiced. The Government has the right to reject defective supplies or services within a reasonable time after delivery by written notification to the Contractor. The Contractor shall in such event promptly replace, correct, or repair the rejected supplies or services at the Contractor’s expense.
Project/Site Conditions
1.5.1. Reference Drawings
Reference Drawings provided in Attachment 1 show existing conditions to the best knowledge of the Government. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on reference drawings, and it shall be the responsibility of the Contractor, whenever necessary, to verify all elevations and the dimensions by measurements in the field. All elevations are referenced to the local datum used for the original construction of the structure. The Contractor shall verify elevations and dimensions before laying out the work. The Contracting Officer shall be notified of any discrepancies prior to commencing work.
1.5.2. Verification of Field Conditions
The Contractor shall verify all dimensions and conditions in the field and shall advise the Contracting Officer of any discrepancy before performing any work.
1.5.3. Work Areas
Neither the contractor nor the contractor’s employees will be permitted inside of the building for any reason. Transport of materials and equipment shall be the responsibility of the Contractor. The Contractor shall be fully responsible for determining the methods used to transport materials and equipment to and from the areas as well as the removal of waste materials from such spaces. The Contractor shall ensure that his operations will not interfere with the operation of the project or the duties of project personnel. Work area will be coordinated and agreed on with the Lockmaster, dependent on other contracts being carried out at the time. (See POCs)
1.5.4. Time of Performance
The Contractor shall notify the Points of Contact (See POCs) prior to start of work. The Contractor shall schedule work through the POCs. The Contractor shall coordinate work with the POCs NLT 3 days before starting work. Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work. The Contractor shall confine all operations at the work site between the hours of 7:30 AM and 4:00 PM, Monday through Friday, unless otherwise approved. Work will not be permitted on weekends or Federal holidays unless otherwise approved. Work shall be scheduled so that all work shall be completed in one construction season.
1.5.5. Period of Performance (PoP)
The Contractor shall complete the work at all locations within 180 calendar days after written notice to proceed is issued.
1.5.6. Permits
The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required federally and by the State of Pennsylvania.
Protection of Government Property
The contractor shall protect all government property during the performance of this contract.
All damage to existing government property as a result of the Contractor’s work shall be repaired or replaced to the satisfaction of the Contracting Officer. Exposed roof and building interior shall be protected at all times. At areas where existing roofing materials have been removed, the contractor shall install and maintain temporary protection from the weather until permanent installation of roofing materials can be made. The Contractor shall coordinate roof demolition with the Contracting Officer. Work area shall be cleaned by the contractor after construction is complete.
Inspections and Acceptance of Work
Notwithstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer. The Contracting Officer shall be the individuals solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.
Points of Contact (POCs)
Prior to commencement of any work being performed on site, the contractor shall participate in a Pre-work Meeting with the Administrative Contacting Officer (ACO) and the Lockmaster on-site.
Dashields Lockmaster – Mark Eberle 412-457-2254 Mark.A.Eberle@usace.army.mil ACO – Kevin Cannon 412-395-7658 Kevin.P.Cannon@usace.army.mil Operations - Joe Ostrosky 412-395-7191 Michael.J.Ostrosky@usace.army.mil
Security Requirements-AT/OPSEC
1.9.1. Anti-Terrorism (AT) Level I Training
All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the contracting officer, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: https://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the Requesting Activity Anti-Terrorism Officer (RA ATO) in presentation form which shall be documented via memorandum.
1.9.2. 2. Access and General Protection and Security Policy and Procedures The contractor and all associated subcontractors' employees shall comply with applicable installation, facility, and area commander installation and facility access and local security policies and procedures (provided by the Government Representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation the USACE Security Office. The contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The contractor must submit the full name, Social Security Number/or/ valid driver’s license number with state of issue, Date of Birth, and Place of Birth/Citizenship for all associated contractor or subcontractor employees to the USACE Security Office, Stephen Davidson, 412-395-7504, stephen.davidson@usace.army.mil, or Joseph M. Bali, 412-395-7162, joseph.m.bali@usace.army.mil. The email name check request must contain the USACE Pittsburgh District contract number and location. The required information may be faxed to 412-395-7173 with a coversheet which identifies the USACE Pittsburgh District contract number and location and an email address for the requesting contractor. The District retains the right to deny any contractor and subcontractor employee from working on one of its contracts based on final background investigation results.
1.9.3. 2b. For contractors who do not require Common Access Card (CAC), but require access to a DOD facility or installation
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.9.4. 4. Suspicious Activity Reporting Training The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Administrative Contracting Officer no later than 5 calendar days after the completion of the training.
1.9.5. 15. Pre-screen candidates using E-Verify Program The Contractor must pre‐screen Candidates using the E‐verify Program (http://www.uscis.gov/e-verify ) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E‐ verify system. An initial list of verified/eligible Candidates must be provided to the KO no later than 3 business days after the initial contract award.
1.9.6. Employee Identification and Background Check
The Contractor shall be responsible for furnishing an identification badge/card to each employee prior to the employee working on-site and for requiring each employee engaged on the work to display identification. Identification shall consist of name tags with the name of the Contractor and the employee's name. Additionally, a valid state driver's license or other Government-issued photo identification card is required for positive identification. Each employee shall be subject to a background check in accordance with "Homeland Security Presidential Directive (HSPD) 12: Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD- 12). Only those individual employees that were specifically identified and approved shall be cleared to work on Government property.
SPECIFICATIONS- ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
2. DETAILED REQUIREMENTS
References
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. Latest reference version should always be used.
o American Society of Civil Engineers (ASCE) o ASCE 7 - Minimum Design Loads for Buildings and Other Structures o ASTM International (ASTM) o ASTM D4637/D4637M - EPDM Sheet Used in Single-Ply Roof Membrane o ASTM D4811/D4811M - Standard Specification for Non-vulcanized
(Uncured) Rubber Sheet Used as Roof Flashing o ASTM D6369 - Design of Standard Flashing Details for EPDM Roof
Membranes o ASTM E108 - Fire Tests of Roof Coverings o FM GLOBAL (FM) o FM 4470 - Single-Ply, Polymer-Modified Bitumen Sheet, Built-up Roof
(BUR), and Liquid Applied Roof Assemblies for Use in Class 1 and Noncombustible Roof Deck Construction o FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/ o National Roofing Contractors Association (NRCA) o NRCA RoofMan - The NRCA Roofing Manual Single Ply Roofing Industry
(SPRI)
o ANSI/SPRI RD-1 - Performance Standard for Retrofit Drains o U.S. Department Of Energy (DOE) o Energy Star - Energy Star Energy Efficiency Labeling System (FEMP) o Underwriters Laboratories (UL) o UL 790 - Standard Test Methods for Fire Tests of Roof Coverings o UL RMSD - Roofing Materials and Systems Directory o International Building Code (IBC)
Description of Roof Membrane System
Fully adhered EPDM roof membrane system applied over insulation substrate.
Submittals
The contractor shall provide submittals for Government Approval. Refer to Attachment 7 for the submittal register. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications. It shall not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work.
o Quality Control Plan
The contractor shall complete and submit a Quality Control Plan. A QCP template is provided in Attachment 4. There shall be one qualified Superintendent and one qualified
Quality Control inspector. The Safety person and the Quality Control inspector may be the same person and may be the DR. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. Cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer. The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of theses specifications. Superintendent and QC shall be on site at all times work is being done.
o Project Schedule
Project Schedule must be provided in MS Project or Excel formats. Schedule must be submitted 2 weeks after Notice to Proceed (NTP), at least 2 weeks prior to the proposed start date, and updated at least weekly.
o SD-02 Shop Drawings Roof Plan Drawing
Prepare roof plan drawings depicting all details for each roof replacement. Roof plan drawings shall include, but shall not be limited to, the following:
Fall safety connection points and anchorage details.
Details for temporary protection and flashing of each roof after initial demolition.
Plan view of each roof showing new membrane dimensions including splice locations.
Identify flashing and provide call out for each specific flashing detail. Also identify sloping and drainage paths.
Cross-section detail of the new roofing membrane, insulation, and underlying roof substrate. Include all layer thicknesses, material information, and product information.
Connection details for the roofing membrane.
Splicing details for the roofing membrane.
Flashing details, to include separate details for typical spans and corners of each roof perimeter. Include flashing details for parapets and for the wooden elevated cover on the River Wall. Also provide separate flashing details for locations around roof penetrations and drains. Details shall be in accordance with paragraph Flashings included in Section 4.
Joist size, joist spacing, sheathing size, hardware, and connection details for the River Wall elevated cover. Provide material and product information for each item.
Each item shall meet the requirements of the International Building Code, latest revision.
o Access Plan
Submit an Access Plan that displays the layout showing where the contractor’s equipment shall be situated and how the contractor shall keep any materials out of the river.
The Access Plan should include any details on how the Contractor will move equipment and materials onto the Middle and River Walls and how the Contractor will access the roof top from the lock wall and how equipment and materials will be hoisted up to the roof top. If the
Contractor intends to roll equipment and materials across the grating, the Contractor will have to protect the grating, i.e.-laying down plywood.
o Demolition and Disposal
Contractor shall submit demolition plan, per EM 385-1-1, section 23.A.01. All existing roofing materials shall be removed. All existing reglets, metal sealing strips, membranes and other material shall be removed and disposed of, without damaging the underlying concrete deck.
All materials removed in the performance of this contract and not reused shall become the property of the contractor and be disposed of offsite in accordance with Federal, State, and Local regulations. On-site burning will not be permitted, and materials will not be permitted to fall into the river.
o SD-03 Product Data
For evaluation purposes, the bidder shall submit for approval product literature for the roof materials to be used. Product data shall include catalog cuts, specifications, or other descriptive data for materials proposed for use, including copies of Manufacturer’s warranties. Product data for the proposed fall protection rooftop anchorages along with manufactures recommendation for anchorage into the concrete deck shall also be submitted for approval. All appropriate descriptive data shall be clearly indicated on the submittal.
Safety Data Sheets (SDS) for materials
If any hazardous chemicals are to be used and/or brought onto the project site, the Contractor shall submit a written Hazard Communication Program and submit it as an appendix to their overall APP. In addition to the written program, the Contractor shall provide Safety Data Sheets (SDSs) for the applicable hazardous chemicals.
Warranty Certificates
Must include Manufacturer’s warranties and Installer’s warranties.
o SD-07 Certificates
Qualifications of Installer
Roofing system installer shall be approved, authorized, or licensed in writing by the roofing system manufacturer and shall have at least the minimum years’ experience required by the manufacturer as an approved, authorized, or licensed installer with that manufacturer and be approved at a level capable of providing the specified warranty.
o Credentials of Designated Persons to Include: SSHO, DR, CP, Fall Protection
Manufacturer’s Certificate o SD-08 Manufacturer's Instructions Application
Application Method, including pattern and frequency of application
Include detailed application instructions and standard manufacturer drawings altered as required by these specifications. Explicitly identify in writing, differences between manufacturer's printed instructions and the specified requirements.
Accident Prevention Plan
Activity Hazard Analyses (AHAs) Fall Protection Plan Lead Compliance Plan Demo Plan o SD-11 Closeout Submittals Warranty
Information Card Instructions to Government Personnel o Contractor data submission
All contractor data submissions shall be submitted to:
U.S. Army Corps of Engineers Pittsburgh District
Attention: ECC-O (Kevin Cannon) 3510 Grand Ave Main Building
Pittsburgh, PA 15225 Phone: 412-395-7658
Quality Assurance
2.4.1. Pre-roofing Conference
After approval of submittals and before performing roofing system installation work, hold a Pre-roofing conference to review the following:
o Drawings, specifications, and submittals related to the roof work;
o Roof system components installation;
o Contractor's plan for coordination of the work of the various trades involved in providing the roofing system and other components secured to the roofing;
o Quality control plan (QCP) for the roof system installation;
o Safety requirements; and o Proposed schedule.
Coordinate pre-roofing conference scheduling with the Contracting Officer. The conference must be attended by the Contractor, the Contracting Officer's designated personnel, personnel directly responsible for the installation of roofing and sheet metal work, mechanical and electrical work, and other trades interfacing with the roof work. Before beginning roofing work, provide a copy of meeting notes and action items to all attending parties. Note action items requiring resolution prior to start of roof work.
2.4.2. Fire Resistance
Complete roof covering assembly must:
o Be Class A rated in accordance with ASTM E108, FM 4470, or UL 790; and be listed as part of Fire-Classified roof deck construction in the UL RMSD or Class I roof deck construction in the FM APP GUIDE.
FM or UL approved components of the roof covering assembly must bear the appropriate FM or UL label.
Delivery, Storage, and Handling
2.5.1. Delivery
Deliver materials in their original, unopened containers or wrappings with labels intact and legible. Where materials are covered by a referenced specification number, the labels must bear the specification number, type, class, and shelf life expiration date where applicable.
Deliver materials in sufficient quantity to allow continuity of work.
2.5.2. Storage
Store and protect materials from damage and weather in accordance with manufacturer's printed instructions, except as specified otherwise. Keep materials clean and dry. Store and maintain adhesives, sealants, primers and other liquid materials in accordance with manufacturers’ recommendations. Utilize insulated hot boxes or other enclosed warming devices in cold weather. Mark and remove damaged materials from the site. Use pallets to support and canvas tarps to completely cover material materials stored outdoors. Do not use polyethylene as a covering. Storage of materials on the roof will not be permitted. Locate materials temporarily in approved areas. Remove unused materials from the roof at the end of each day’s work.
2.5.3. Handling
Prevent damage to edges and ends of roll materials. Do not install damaged materials in the work. Select and operate material handling equipment so as not to damage materials or applied roofing. Do not use materials contaminated by exposure or moisture. Remove contaminated materials from the site. When hazardous materials are involved, adhere to the special precautions of the manufacturer. Adhesives may contain petroleum distillates and may be extremely flammable; prevent personnel from breathing vapors, and do not use near sparks or open flame.
Environmental Requirements
The temperature of the roofing materials shall be as required by the manufacturer. Do not install EPDM sheet roofing during high winds or inclement weather, or when there is ice, frost, moisture, or visible dampness on the substrate surface, or when condensation develops on surfaces during application.
Unless recommended otherwise by the EPDM sheet manufacturer and approved by the Contracting Officer, do not install EPDM sheet when air temperature is below 40 degrees F or within 5 degrees F of the dew point. Follow manufacturer's printed instructions for installation during cold weather conditions.
Wind conditions shall be suitable for installation of insulation: Wind chill may affect the proper application temperatures of materials; hot materials may be blown about, creating safety dangers; insulation boards may become difficult and hazardous to handle; wrappers, coverings, and other debris may become airborne, and possibly contaminate laps and seams.
Sequencing
Coordinate the work with other trades to ensure that components which are to be secured to or stripped into the roofing system are available and that permanent flashing and counter-flashing are installed as the work progresses. Ensure temporary protection measures are in place to preclude moisture intrusion or damage to installed materials. The contractor may install the fall protection rooftop anchors prior to demolition work and utilize them during performance of the contract. They shall remain in place and be watertight upon completion of the work.
Warranty
Submit sample certificates for approval.
Provide roof system material and workmanship warranties meeting specified requirements.
Provide revision or amendment to standard membrane manufacturer warranty as required to comply with the specified requirements.
2.8.1. Roofing System Installer Warranty
The roof system installer must warrant for a period of two years the roof system, as installed, is free from defects in installation workmanship, to include the roof membrane, flashing, insulation, accessories, attachments, and sheet metal installation integral to a complete watertight roof system assembly. Write the warranty directly to the Government. The roof system installer is responsible for correction of defective workmanship and replacement of damaged or affected materials. The roof system installer is responsible for all costs associated with the repair or replacement work. The contractor shall provide a warranty walk-thru with Project personnel at nine months and another prior to the two-year period.
2.8.2. Roof Membrane Manufacturer Warranty
Furnish roof membrane manufacturer's 20-year, no dollar limit, full roof system materials, and installation workmanship warranty, including all flashing, insulation, and accessory materials necessary to construct a complete, watertight roof system. Provide warranty directly to the Government and commence warranty effective date at the time of Government's acceptance of the roof work. The warranty shall state that:
If within the warranty period the roof system, as installed for its intended use in the normal climatic and environmental conditions of the facility, becomes non- watertight, shows evidence of moisture intrusion within the assembly, splits, tears, cracks, delaminates, separates at the seams, or shows evidence of excessive weathering due to defective materials or installation workmanship, the repair or replacement of the defective and damaged materials of the roof system assembly and correction of defective workmanship shall be the responsibility of the roof membrane manufacturer. All costs associated with the repair or replacement work shall be the responsibility of the roof membrane manufacturer.
When the manufacturer and his approved applicator fail to perform the repairs within 72 hours of notification, emergency temporary repairs performed by others shall not void the warranty.
2.8.3. Continuance of Warranty
Approve repair or replacement work that becomes necessary within the warranty period and accomplish in a manner so as…