TCSG_419_DP Addendum _1.pdf

PDF 125 KB Posted

Attached to
TCSG-419-DP Hank Aaron Academy Expansion & Renovation
Solicitation number
PE-40900-RFQC-2024-000000073
Issued by
Fulton County, Georgia

About this file

This document is an addendum for Project No. TCSG-419-DP, the ATL Renovation/Expansion of the Henry Louis "Hank" Aaron Academic Complex. The addendum provides a corrected schedule for the project, which is being managed by the Georgia State Financing and Investment Commission (GSFIC). Key milestones include the GSFIC posting the advertisement on June 20, 2024, the Design Professional selection on August 14, 2024, the start of design phase on September 1, 2024, the completion of the design phase on June 9, 2025, the construction start on July 14, 2025, material completion on June 8, 2026, and the building opening for occupancy on August 3, 2026.

The document does not provide details on pricing terms, set asides, incumbents, funding requirements and sources, or other salient financial information. It solely focuses on the project schedule and timeline.

View the file

Other files

File Type Posted
Shortlisted Firms.pdf PDF
TCSG_419_DP RFQ _ Hank Aaron Academic Complex.pdf PDF
TCSG_419_DP Questions _ Answers.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TCSG-419 - ATL Renovation/Expansion Henry Louis “Hank” Aaron Academic Complex

Addendum #1

Please see the attached corrected schedule for Project No. TCSG-419-DP.

Milestone Date

GSFIC posts advertisement: June 20, 2024

Design Professional Selection: August 14, 2024

DP services begin: September 1, 2024

Design Phase complete: June 9, 2025

Construction Start: July 14, 2025

Material Completion: June 8, 2026

Open for occupancy: August 3, 2026