TCSG_419_DP Addendum _1.pdf
PDF 125 KB Posted
- Solicitation number
- PE-40900-RFQC-2024-000000073
- Issued by
- Fulton County, Georgia
About this file
This document is an addendum for Project No. TCSG-419-DP, the ATL Renovation/Expansion of the Henry Louis "Hank" Aaron Academic Complex. The addendum provides a corrected schedule for the project, which is being managed by the Georgia State Financing and Investment Commission (GSFIC). Key milestones include the GSFIC posting the advertisement on June 20, 2024, the Design Professional selection on August 14, 2024, the start of design phase on September 1, 2024, the completion of the design phase on June 9, 2025, the construction start on July 14, 2025, material completion on June 8, 2026, and the building opening for occupancy on August 3, 2026.
The document does not provide details on pricing terms, set asides, incumbents, funding requirements and sources, or other salient financial information. It solely focuses on the project schedule and timeline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Shortlisted Firms.pdf | ||
| TCSG_419_DP RFQ _ Hank Aaron Academic Complex.pdf | ||
| TCSG_419_DP Questions _ Answers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TCSG-419 - ATL Renovation/Expansion Henry Louis “Hank” Aaron Academic Complex
Addendum #1
Please see the attached corrected schedule for Project No. TCSG-419-DP.
Milestone Date
GSFIC posts advertisement: June 20, 2024
Design Professional Selection: August 14, 2024
DP services begin: September 1, 2024
Design Phase complete: June 9, 2025
Construction Start: July 14, 2025
Material Completion: June 8, 2026
Open for occupancy: August 3, 2026