TCSG_404_Commissioning Item Checklist.pdf

PDF 131 KB Posted

Attached to
CxA Services Stewart Building Renovation - Oconee Fall Line Tech
Solicitation number
PE-40900-RFQC-2024-000000047
Issued by
Lanier County, Georgia

About this file

This document is a Building Commissioning Checklist for the OFTC Stewart Building Renovation project, a state contract opportunity located in Dublin, Georgia. The checklist identifies required and optional mechanical, HVAC controls, plumbing, electrical, laboratory, renewable energy, and building envelope systems to be commissioned as part of the project scope. The required items include components such as thermometers, vibration isolation, hot water heating, chillers, air terminal units, lighting controls, and fume hoods. The optional items provide additional systems that may be selected for commissioning based on project needs, including emergency power, exterior lighting, security systems, and building envelope testing. No information is provided on response dates, due dates, site visits, bidder's meetings, award dates, or contract term.

The document does not contain details on pricing, set asides, incumbents, funding requirements, or other commercial terms. It is focused solely on outlining the commissioning requirements and systems that may be included in the project scope.

View the file

Other files

File Type Posted
TCSG_404_Cx ONE STEP RFQ.pdf PDF
Highest Ranked Firm TCSG_404_CX.pdf PDF
Selected Firm TCSG_404_CxA.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 11/28/16

GSFIC

BUILDING COMMISSIONING CHECK LIST

PROJECT NUMBER: TCSG-404; 2023-227

PROJECT NAME: OFTC Stewart Building Renovation

LOCATION: Dublin, Georgia 31021

PREPARED BY: Wayne Wellington, CROFT & Associates

INSTRUCTIONS: Design Professional is to fill out the commissioning checklist prior to advertisement for the Commissioning Agent’s selection.

• Design Professional should check only those Required Items that are in the project scope

• The Project Team should determine which Optional Items to select for commissioning based on specific project needs; Design Professional is to lead this coordination effort

Table 5.1 – Mechanical Systems

REQUIRED ITEMS

No. Main Items Included in Scope Check if in project scope

1. Thermometers and gauges

2. Vibration isolation

3. Steam condensate system

4. Hot water heating systems

5. Computer room HVAC systems

6. Chemical water treatment systems

7. Chillers

8. Cooling towers

9. Condenser water system

10. Air terminal units

11. Humidifiers and controls

12. Duct silencers (physical observation of unit)

13. Dampers

14. Variable frequency drives and motors

15. Air distribution systems

16. Exhaust air systems and building pressurization controls

17. Test and Balance verification

18. Refrigeration equipment and controls

19. Chilled water system

20. Variable Refrigerant Flow system Notes:

2 11/28/16

Table 5.2 – HVAC Controls Systems

REQUIRED ITEMS

No. Main Items Included in Scope Check if in project scope

1. Component FPT and calibration

2. Control air supply

3. Air terminal units (non-lab)

Sequence controls to include:

4. Air handling units

5. Fans (e.g. exhaust air fans)

6. Differential bypass valve

7. Air terminal units

8. Heat exchanger

9. Variable speed pumps

10. Heaters (e.g. cabinet unit heaters)

11. Condenser water system

12. Humidifiers

13. Water heaters

14. Heating coils / radiant panels

15. Labs with VAV fume hoods

16. Steam generator

17. Building pressurization

18. Air conditions systems (e.g. VRF, WSHP)

19. Graphic display

20. Trend logs

21. Status review screens, checks and alarming

22. Network communication

OPTIONAL ITEMS

No. Main Items Included in Scope Check if in project scope

Check if scope to be commissioned Sequence controls to include:

1. Smoke controls

2. Energy Analysis 3.

4.

5.

3 11/28/16

Table 5.3 – Plumbing Systems

REQUIRED ITEMS

No. Main Items Included in Scope Check if in project scope

1. Domestic hot water systems

2. Tempered water systems

3. Fuel oil / gas systems project scope

Check if scope to be commissioned

1. Vibration isolation

2. High purity water system

3. De-ionized water system

4. Thermometers and gauges

5. Water filtration (general use)

6. Fuel oil / gas systems

7. Potable water and booster pump systems

8. Sump pumps and electors

9. Compressed air systems (non-lab use) 10.

11.

12.

4 11/28/16

Table 5.4 – Electrical Systems

REQUIRED ITEMS

No. Main Items Included in Scope Check if in project scope

1. Lighting controls (scheduled activators and occupancy sensors, etc.)

2. Daylight dimming controls

No. Main Items Included in Scope Check if in project scope Check if scope to be commissioned

1. Service switchgear

2. Emergency power system

3. Generators / auto transfer switches

4. Lighting - exterior

5. Switchboards

6. Distribution panel boards

7. Motor control centers

8. Transient voltage surge suppressors

9. Variable frequency and speed drives

10. Grounding and ground fault systems

11. Over-current protective devices

12. Thermo graphic survey

13. White noise system

14. Paging system and security

15. Fire alarm and smoke detectors

16. Standby and emergency power systems

17. Emergency lighting

18. Security systems

19. Transformers

20. Power monitoring and metering 21.

22.

23.

5 11/28/16

Table 5.5 – Laboratory Systems

REQUIRED ITEMS

No. Main Items Included in Scope Check if in project scope

1. Fume hoods

2. Lab waste neutralization

3. Special gas manifolds

4. Vacuum air system

5. Compressed air system (lab use)

6. Electronic calendaring or directory project scope

Check if scope to be commissioned

1. Emergency shower / eyewash

2. Biosafety pressure controls 3.

4.

5.

Table 5.6 – Renewable Energy Systems

REQUIRED ITEMS

No. Main Items Included in Scope Check if in project scope

1. Heat recovery systems

2. Controls and thermostats

3. Photovoltaic cell panels (solar power systems)

4. Solar hot water systems

5. Geothermal systems

6 11/28/16

Table 5.7 – Building Envelope

OPTIONAL ITEMS

No. Main Items Included in Scope Check if in project scope

Check if scope to be commissioned

1.

Roofing system – water-proofing, insulation, roof membrane, rain and ice shield, pitch, coping, flashing, curbs for mechanical equipment, downspouts, drains, scuppers

2.

Exterior skin – curtain wall, storefront, masonry, brick / stone veneers, precast panels, metal panels, stucco / EIFS, siding

3. Walls – vapor barriers, insulation, mortar nets, weeps, joints, sealants, masonry ties

4. Slab on grade – vapor barriers, water-proofing, drainage, foundation drains

5. Doors and windows – sealants, mechanical operation, sills, flashing, end dams, hardware

6. Water tests, mockups, wind loads, thermal infiltration Indicate if testing is to be

Performed by CxA, or Observed by CxA?

7. Special design features – dome, cornice, canopy, skylight, etc.

8. Envelope thermographic test

9. Pre-engineered Metal Building (PEMB) 10.

11.

7 11/28/16

Table 5.8 – Retro-Commissioning

OPTIONAL ITEMS

No. Main Items Included in Scope Check if in project scope

Check if scope to be commissioned

1. Compressed air system

2. Steam condensate system

3. Hot water heating system

4. Computer room HVAC system

5. Chemical water treatment system

6. Chillers

7. Cooling towers

8. Air terminal units

9. Humidifiers and controls

10. Dampers

11. Variable frequency drives and motors

12. Air handling units & distribution systems

13. Exhaust air systems and building pressurization controls

14. Building automation systems, including controlled devices, sensors, control loops, and logic

15. Lighting controls (scheduled activators and occupancy sensors)

16. HVAC DX systems

17. Domestic hot water systems

18. Natural gas / fuel systems

19. Other HVAC systems

20. Standby and emergency power system

21. Generators / auto transfer switches 22.

Table 5.1 – Mechanical Systems
REQUIRED ITEMS
Table 5.2 – HVAC Controls Systems
REQUIRED ITEMS
Table 5.3 – Plumbing Systems
REQUIRED ITEMS
REQUIRED ITEMS
Table 5.5 – Laboratory Systems
REQUIRED ITEMS
OPTIONAL ITEMS
Table 5.6 – Renewable Energy Systems
REQUIRED ITEMS
Table 5.7 – Building Envelope
OPTIONAL ITEMS
Table 5.8 – Retro-Commissioning