Summary

This Request for Proposals (RFP 2025-213) issued by the Florida Municipal Power Agency (FMPA) seeks proposals for the long-life replacement of high-pressure superheater and reheater sky vent valves at the Treasure Coast Energy Center (TCEC) located at 4545 Energy Lane, Fort Pierce, Florida. The project requires vendors to supply complete turnkey valve assemblies including automatic actuator assemblies, valve bodies, trim, hardware, seals, stainless steel 316 components, instrumentation and control equipment, corrosion-resistant materials rated for chloride-rich coastal environments, complete technical documentation, on-site field support, and commissioning services. A mandatory site visit with walk-down is scheduled for December 2, 2025, at 10:00 a.m. with personal protective equipment required. Sealed proposals must be submitted via Vendor Link by 10:00 a.m. on January 15, 2026, with public opening at FMPA headquarters in Orlando, Florida. All materials, drawings, and technical information must arrive at TCEC by September 30, 2026, with installation and commissioning scheduled for December 3–10, 2026, during the fall outage. The notice of award is estimated for February 16, 2026, and the resulting agreement will consist of a Master Agreement and project-specific Purchase Orders with no specified contract term or renewal options noted.

Proposals must include lump sum pricing for materials with freight and tariffs, labor, supervision, equipment, documentation, a minimum of 15 percent spare consumables, three days of built-in schedule slippage, and all associated costs. The vendor is responsible for all off-site storage logistics, safety protocols, and quality assurance. Evaluation criteria include technical compliance, vendor experience and references, schedule adherence, warranty offerings, safety and quality plans, and cost competitiveness. No performance bond or bid surety is required. FMPA reserves the right to reject any or all proposals, negotiate if pricing exceeds available funds, award to multiple bidders, or move to the next-ranked proposer if performance issues arise with the selected contractor. The RFP specifies no explicit set-asides, incumbent contractor information, or identified funding source. Proposers must maintain comprehensive general liability insurance of $2,000,000, automobile liability of $1,000,000, and workers' compensation insurance at statutory limits throughout contract performance.

View the file

Other files

File Type Posted
No_Award_Memo.pdf PDF
Questions_&_Answers_-_Revised.pdf PDF
Addendum_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Municipal Power Agency 8553 Commodity Circle

Orlando, Florida 32819-9002

(407) 355-7767 Fax (407) 355-5796

Request for Proposals No. 2025-213 November 2025

Florida Municipal Power Agency

REQUEST FOR PROPOSALS

FOR

TCEC HIGH-PRESSURE SUPERHEATER &

REHEATER SKY VENT VALVES

REQUEST FOR PROPOSALS

(This is not an order)

R E Florida Municipal Power Agency T TO: 8553 Commodity Circle

RFP FMPA 2025-213

Date Issued: November 12, 2025 U Orlando, Florida 32819 R Attn: Sharon Samuels Telephone: (407) 355-7767 N

SEALED PROPOSALS MUST BE SUBMITTED PRIOR TO PROPOSAL OPENING AT 10:00 A.M. ON JANUARY 15, 2026. PUBLIC OPENING WILL BE IN THE FMPA FIRST FLOOR CONFERENCE ROOM LOCATED IN THE

FMPA BUILDING AT 8553 COMMODITY CIRCLE, ORLANDO, FLORIDA 32819.

Proposals shall be submitted via Vendor Link. Forms provided in the RFP must be manually signed; Docusign/ReadySign secure signatures are also acceptable.

Proposals received after the opening date and time may be rejected and returned unopened.

The attached Request for Proposals shall become part of any purchase order resulting from this Request for Proposal.

DESCRIPTION

November 2025

Florida Municipal Power Agency Request for Proposals for

TCEC High-Pressure Superheater & Reheater Sky Vent Valves

See attached Request for Proposals, General Conditions, Specifications, and Proposal Forms for detailed description.

It is the intent and purpose of the Florida Municipal Power Agency that this Request for Proposal promotes competitive bidding. It shall be the proposer's responsibility to advise if any language, requirements, etc. or any combination thereof, inadvertently restricts or limits the requirements stated in this Request for Proposal to a single source. Such notification must be submitted in writing and must be received by not later than ten (10) days prior to the proposal opening date.

ADVERTISEMENT

Proposal For

November 2025

FLORIDA MUNICIPAL POWER AGENCY

REQUEST FOR PROPOSALS FOR

TCEC HIGH-PRESSURE SUPERHEATER & REHEATER SKY VENT VALVES

REQUEST FOR PROPOSALS

FMPA 2025-213

Sealed proposals will be received by the Florida Municipal Power Agency (FMPA), 8553 Commodity Circle, Orlando, Florida 32819, until 10:00 A.M. ON JANUARY 15, 2026, when at that time Proposals will be opened publicly by a FMPA representative.

The proposal is for the Treasure Coast Energy Center (TCEC) High-Pressure Superheater & Reheater Sky Vent Valves as more fully described in the Scope of Work section of the Request for Proposals package.

RFP packages for this project may be obtained from FMPA at the above address, by telephone

(407) 355-7767, via e-mail request to bidinfo@fmpa.com, via Internet download at www.fmpa.com, or via https://myvendorlink.com

No proposal may be altered, withdrawn, or resubmitted after the scheduled closing time for receipt of proposals, except as otherwise permitted in the RFP package. Proposals received after the day and time stated above will not be considered.

Proposals will be accepted for TCEC High-Pressure Superheater & Reheater Sky Vent Valves from companies who have established, through demonstrated expertise and experience, that they are qualified to provide the services as specified.

The Florida Municipal Power Agency reserves the right to reject any and all proposals in total or in part and to waive defects in proposals.

Jacob Williams General Manager and CEO Florida Municipal Power Agency http://www.fmpa.com/ https://myvendorlink.com/

FLORIDA MUNICIPAL POWER AGENCY

Request for Proposals for

TCEC High-Pressure Superheater & Reheater Sky Vent Valves

1. FMPA Description Formed by Florida’s municipal electric utilities in February 1978, the Florida Municipal Power Agency (FMPA or the Agency) is a non-profit, governmental, wholesale electric utilities company created to serve the needs of municipal electric utilities in Florida. All 33 municipal systems in the State are FMPA members who participate at varying levels in Agency activities.

2. Introduction - General Description of Services Sought

Florida Municipal Power Agency, (FMPA/Owner) invites proposals to Treasure Coast Energy Center (TCEC) High-Pressure Superheater & Reheater Sky Vent Valves

Based on the relevant previous experience, your firm has been selected to receive this RFP and is invited to submit a proposal to supply the work described herein.

The scope includes details for the work at the Treasure Coast Energy Center, 4545 Energy Lane, Fort Pierce, FL 34981.

3. Overview Upon selection of the awarded Contractor(s), FMPA will enter into a Master Agreement specifying terms and conditions. FMPA will issue a Purchase Order with project-specific technical specifications.

The submission of a proposal implies a general acceptance on the part of the bidder of the terms of this RFP, form of contract, and especially of those parts establishing warranties and guarantees.

4. Purchasing Services Subsequent to the award, FMPA shall issue Purchase Orders to the Contractor(s) awarded the agreement pursuant to this Request for Proposal.

5. Indemnity After notification of award, the successful bidder shall indemnify and save harmless FMPA from and against all claims, suits, actions, damages, or causes or action arising during the terms of the resulting agreement for any personal injury, loss of life, or damage to property sustained by reason of a result of the performance of the services or delivery of goods for which the resulting agreement was entered into, or its agents, employees, invitees, and all other persons, and for and against any orders, judgements, or decrees, which may be entered thereto, and from and against all costs, attorney's fees, expenses and liabilities incurred in or by reason the defense of any such claim, suit or action, and the investigation therefore.

Nothing in the award, resulting agreement, contract or Purchase Order shall be deemed to affect the rights, privileges and immunities of FMPA as set forth in Florida Statute 768.28.

The successful bidder(s) covenants and agrees to indemnify and save harmless FMPA and to defend from all cost, expenses, damages, attorney's fees, injury or loss to which FMPA may be subjected by any person, firm, corporation, or organization by reason of any wrongdoing, misconduct, want, or need of care or skill, negligence or default or breach of contract, guaranty, or warranty, by the successful bidder(s), his employees, his agents or assigns.

6. Notice to Proposers Sealed proposal packages will be received until 10:00 A.M. ON JANUARY 15, 2026 ("Proposal Due Date") via Vendor Link (https://myvendorlink.com).

Each proposer is required to submit a Proposer Information Form (included in this RFP package), other forms included in this package as appropriate, and all other information necessary to allow a complete evaluation of the proposal. Registered proposers will be notified through the issue of RFP addenda of any change in the Proposal Due Date or other necessary revision to information contained in this RFP. FMPA reserves the right to reject all proposals received after the Proposal Due Date, outside of Vendor Link, or outside of the submittal process. Emailed submittals will not be accepted.

7. Duration of Offer Proposals submitted in response to this RFP are irrevocable 120 days, unless withdrawn or modified as provided in Section 16 below. This period may be extended at FMPA’s request only by written agreement of the proposer. The content of this RFP and the proposal of the successful proposer will be included by reference in any resulting contract.

8. Right of Rejection This RFP is not an offer establishing any contractual rights. This solicitation is solely an invitation to submit proposals.

FMPA reserves the right to:

• Reject any and all proposals received in response to this RFP;

• Waive any requirement in this RFP;

• Waive any irregularities, regardless of the severity

• Not disclose the reason for rejecting a proposal;

• Not select the proposal with the lowest price; and

• Seek and reflect clarifications to proposals.

• Negotiate with the selected bidder in the event that the price exceeds available funds.

• If performance issues with Awarded Bidder; FMPA moves to next best evaluated bidder to complete work.

• Award to more than one bidder.

• Select the proposal that is in the best interest of FMPA https://myvendorlink.com/

9. Proposal Contents The submission of a proposal implies a general acceptance on the part of the bidder of the terms of this form of contract, and especially of those parts establishing warranties and guarantees

The proposal should include a description of the firm’s capabilities and experience with providing the requested services, including a description of any special qualifications which are indicative of working familiarity with similar projects.

The following information must be included:

1. Demonstration of first-hand experience in providing similar services to those requested in this RFP;

2. Description of the resources available, including staffing levels, qualifications of key personnel who will be performing the work, equipment and capabilities; and locations of offices;

3. Proof of Insurance coverage;

4. Proof of licenses and certifications, if applicable;

5. Safety protocols;

6. A schedule for the work, including the range of start dates to which your firm is prepared to commit to and anticipated completion dates.

7. General description of how projects will be staffed, managed, and completed, including project management and invoicing;

8. Identification of any work or services that may be provided by a subcontractor.

Bidder shall provide information similar to that above concerning subcontractor’s equipment, personnel, and qualifications; including a minimum of two (2) reference projects with similar scope of work. If after award of the RFP, the successful bidder(s) desire to utilize a subcontractor other than listed in the bid, the bidder must obtain approval of the subcontractor from FMPA.

Denial of a subcontractor by FMPA will NOT absolve the bidder from getting the work done for the contracted price;

9. List of at least two (2) references for which similar projects were conducted, including name, company, title, phone number and email address, and a brief description of the project including the start and end dates;

10. List any past High-Pressure Superheater & Reheater Sky Vent Valves experience for which your firm conducted work for FMPA, as well as others. Provide a brief description of the project including the start and end dates and point of contact.

Please include an experience list any discovery work and/or scope deficits and/or lessons learned that required a T&M change order & delays.

11. The name and contact information of the person in Bidder’s firm who would be the official contact person for any contractual relationship.

12. Fully executed forms as provided in Appendix C - Bid Forms.

10. RFP Schedule FMPA’s timetable for this RFP process is shown below. Note that the dates shown are only estimates and may be modified at any time by FMPA.

Public Notice/Distribution of RFP Intent to Bid & Questions Deadline Sealed Proposals Due Date Notice of Award (Estimated date)

November 12, 2025 December 12, 2025 January 15, 2026 February 16, 2026

11. Site Visit and Walk-down Mandatory site visit with walk-down for December 2, 2025 at 10:00am. PPE is required.

Treasure Coast Energy Center, 4545 Energy Lane, Fort Pierce, FL 34981.

12. Evaluation The proposals will be evaluated based on information provided by each proposer by the Proposal Due Date. No additional data will be considered after the Proposal Due Date, except for clarifications requested by FMPA. FMPA will evaluate the proposals in terms of cost and other quantitative and non-quantitative factors.

Selection and rejection of proposals and notification of proposers at all stages will remain entirely with FMPA’s discretion. FMPA intends to notify proposers not selected under this solicitation within a reasonable amount of time.

The evaluation criteria will include a variety of considerations, which may include:

a. Experience with similar projects and references

b. Past Performance

c. Schedule, availability and lead time

d. Warranty and support offerings

e. Safety and quality plans

f. Pricing

Proposals must include sufficient information supporting pricing to permit FMPA to evaluate all proposals, which may include different pricing elements, different products, and different methods and assumptions, on an equal basis. If sufficient information supporting pricing is not provided, FMPA may have to make pricing assumptions in evaluating proposals to achieve, in FMPA’s judgment, an equal evaluation of all proposals.

Those pricing assumptions made by FMPA are at FMPA’s discretion and based upon FMPA’s subjective evaluations of the proposals received, and may or may not be shared with proposers.

Any proposer that proposes an alternative to any FMPA specified technical or business terms, or specified-products, must clearly identify such alternatives and provide supporting information for why the proposer believes its alternative(s) are superior to FMPA’s specifications. FMPA is not obliged to accept any proposer’s alternatives.

13. Performance Bond/Surety Neither a bid nor a performance bond or surety is required pursuant to this RFP.

14. Budgetary Constraints The Florida Municipal Power Agency reserves the right to reduce or increase the quantity, retract any item from the bid, or upon notification, terminate entire agreement without any obligations or penalty based upon availability of funds.

15. Interpretations and Addenda All questions regarding interpretation of this RFP, technical or otherwise, must be submitted in writing to the following:

By E Mail: sharon.samuels@fmpa.com

By Fax: Ms. Sharon Samuels

(407) 355 - 5796

By Mail or Courier: Ms. Sharon Samuels Florida Municipal Power Agency 8553 Commodity Circle Orlando, Florida 32819

Only written responses provided by FMPA to proposers’ questions will be considered official. A verbal response by FMPA will not be considered an official response. Written responses to questions and requests for interpretations will be provided to all potential proposers. Copies of all addenda issued in connection with this RFP may be sent to all potential proposers.

Questions and Answers Questions will be accepted through the deadline noted in the schedule from potential bidders who notify us that they will be a bidder. We reserve the right not to answer other questions.

Bidders are to submit questions via email to sharon.samuels@fmpa.com . Questions will be answered and all answers will be distributed to all bidders.

Upon receipt of this Request for Proposals (“RFP”), potential Contractors shall immediately cease direct contact with individual FMPA or Generating Facility employees regarding the subject matter of this RFP.

Notwithstanding the previous sentence, If FMPA has questions about a particular proposal that, in the judgment of FMPA, would be appropriate to ask a proposer to clarify, explain, or otherwise provide supporting information for its proposal, FMPA reserves the right to pose such questions to proposers. In the event FMPA does this, it will provide a notice to all proposers of the proposers that received questions from FMPA, and the general nature of the questions, but FMPA will not provide information that it believes will give an proposer any competitive advantage over another. FMPA will evaluate answers received from proposers, but will not accept modifications to proposals after the Proposal Due Date.

16. Errors, Modifications or Withdrawal of Proposal Each proposer should carefully review the information provided in the RFP prior to submitting a response. The RFP contains instructions which must be followed by all proposers. Modifications to proposals already received by FMPA will only be accepted prior to the Proposal Due Date. Proposals may be withdrawn by giving written notice to FMPA prior to the Proposal Due Date.

mailto:sharon.samuels@fmpa.com

17. Proprietary Confidential Business Information All proposals shall become property of FMPA. FMPA will not disclose to third parties any information that is clearly labeled “Proprietary Confidential Business Information” in a proposal unless, in the opinion of counsel for FMPA, such disclosures are required by law or by order of the court or government agency having appropriate jurisdiction. Each page of Proprietary Confidential Business Information must be clearly labeled “PROPRIETARY CONFIDENTIAL BUSINESS INFORMATION” at the top of the page. FMPA reserves the right to disclose information contained in proposals to its consultant(s) for the sole purpose of assisting in the proposal evaluation process. FMPA will require the consultant(s) to maintain the confidentiality of the document.

18. Default and Damages Provisions

FMPA will negotiate standard terms and conditions for default and damages with the awarded Contractor(s). All proposers are requested to include proposed default and damages provisions in their proposals.

19. Public Entity Crimes Statement Pursuant to Section 287.133(2)(a), FLORIDA STATUTES, all proposers should be aware of the following:

"A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted vendor list."

20. Collusion

By offering a submission pursuant to this RFP, the proposer certifies the proposer has not divulged, discussed, or compared his proposal with other proposers and has not colluded with any other proposer or parties to this proposal whatsoever. Also, the proposer certifies, and in the case of a joint proposal, each party thereto certifies, as to his own organization, that in connection with this proposal:

1. Any prices and/or cost data submitted have been arrived at independently, without consultation, communication, or agreement for the purpose of restricting competition, as to any matter relating to such prices and or cost data, with any other proposer or with any competitor.

2. Any prices and/or cost data quoted for this proposal have not knowingly been disclosed by the proposer and will not knowingly be disclosed by the proposer prior to the scheduled opening directly or indirectly to any other proposer or to any competitor

3. No attempt has been made or will be made by the proposer to induce any other person or firm to submit or not to submit a proposal for the purpose of restricting competition

4. The only person or persons interested in this proposal, principal or principals is/are named therein and that no person other than therein mentioned has any interest in this proposal or in the contract to be entered into and

5. No person or agency has been employed or retained to solicit or secure this contract upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee excepting bona fide employees or established commercial agencies maintained by the Proposer for the purpose of doing business.

21. Drug Free Workplace A Drug-Free Workplace Statement must be completed, signed, and returned prior to award of proposal. This form will be used whenever two or more proposals that are identical with respect to price, quality, delivery, and service are received; a proposal received from a business that certifies that it has implemented a drug-free workplace program shall be given preference in the award process.

22. Subcontracted Services Proposal should indicate which, if any, of the services to be provided would be subcontracted by the proposer to independent contractors. If work is intended to be subcontracted, BID SUBMITTAL MUST BE ACCOMPANIED BY BACKGROUND

MATERIALS AND REFERENCES FOR PROPOSED SUBCONTRACTOR(S) -

NO EXCEPTIONS. In addition, Contractor(s) must notify FMPA any time work will include subcontracted services. FMPA maintains the right to reject the proposed subcontractor for specific project work.

23 Definitions The words and terms defined in this document shall have the following meanings as used throughout.

ACCEPTANCE – Written acknowledgement by the FMPA and authorized representative that the Work has been completed in a manner consistent with the terms, conditions and specifications of a Contract or Purchase Order.

CONTRACTOR – The business entity (and its affiliates and authorized assigns),which has been awarded by FMPA or executed a contract with FMPA shall include any and all subcontractors, affiliates and authorized assigns that provide or perform any or all of the Work. This entity may also be referred to as the Contractor, successful bidder, or successful proposer.

PARTICIPANT CONTRACT – The aggregation of all documents that constitute the binding agreement between the Contractor and FMPA. The Participant Contract may include but shall not be limited to The Award or Agreements that result from this solicitation, Blanket Orders, Purchase Orders, Order Releases, and all attachment agreements.

PURCHASE ORDER (PO) – A Work authorization, issued by FMPA or an FMPA Member, which is issued subject to the terms and conditions of the Award or Agreement. The term “Purchase Order” shall also include “blanket order releases” and any other ordering methodology agreed to in writing by FMPA and Contractor.

WORK – Labor, materials, supplies, equipment, goods, and services including any related documentation, software, reports, testing, transport, administration, management, tools and any and all other requirements to be furnished or performed by Contractor under this Agreement and/or a Participant Contract together with all other additional necessities that am not specifically recited in this Agreement or Participant Contract but which could be reasonably inferred as necessary to complete all obligations and fully satisfy the intent of this Agreement and/or a Participant Contract.

24. Entire Contract These General Terms and Conditions, the Master Agreement between FMPA and the selected Contractor(s), and the Purchase Order (PO) for which they are being provided (including attachments thereto) constitute the entire agreement between FMPA and the Contractor.

25. Acceptance of Services and Work Product The Product or Services shall be subject to FMPA and authorized staff’s inspection at any time. FMPA may reject Product/Services within a reasonable time after completed, if such Product/Services do not comply with the requirements of the Purchase Order or the specifications for the Product/Service. The making or failure to make any inspection of, or payment for or acceptance of Product/Service shall in no way impair FMPA’s right to reject or revoke its acceptance of nonconforming Product/Service, or to avail itself of any other remedies to which FMPA may be entitled, notwithstanding FMPA’s knowledge of the nonconformity, its substantiality or ease of discovery.

Final acceptance of the Services and Work Product for purposes of the Purchase Order shall be the date upon which FMPA confirms that all Services and Work Product have been completed in accordance with the terms of the Purchase Order (“Final Acceptance”).

26. Site Access Conditions FMPA and authorized staff shall provide Contractor access to the Facility as necessary to perform the Work or Services. Access shall be subject to Contractor’s obligation to comply with the following conditions:

1. Contractor shall confine its activities to only those portions of the Facility necessary for performance of the Services.

2. Contractor shall take all safety measures reasonably necessary to protect

FMPA and FMPA property, its permittees and licensees and the property of each, from injury or damage caused by or resulting from the performance of Services. Contractor shall follow any and all safety and security procedures established by FMPA for the Facility. In the event of a security emergency, FMPA and its Members may deny Contractor access to a Facility or request that Contractor leave the Facility.

3. Contractor shall maintain all required insurance coverage’s set forth in

Section 27 at all times during the term of the Purchase Order.

4. Contractor’s performance of Services shall not interfere with the use, occupancy or enjoyment of the Facility by FMPA and its Members.

5. No work or activity performed as part of the Services shall cause FMPA and its Members to be in violation of any requirement of law nor shall Contractor or any agent, employee or representative violate any federal, state or local laws while performing Services.

6. All Services shall be performed in a manner that will not damage the Facility and Contractor shall promptly notify FMPA and shall be responsible for the cost of repairing any such damage should it occur.

7. FMPA rules on maintaining a drug-free workplace shall be strictly followed and enforced by Contractor with respect to all of its employees or subcontractors and none of Contractor’s employees, subcontractors, agents or representatives shall be permitted to use non-prescription drugs or alcohol at any FMPA and its Member Facility.

27. Required Insurance The Contractor shall acquire and maintain at all times during the performance of Services the insurance coverage set forth below. Contractor shall furnish FMPA a copy of the insurance certificate. Additional information on insurance requirements are noted in Appendix B, page 5.

The liability limits shall not be less than:

Workers’ Compensation Statutory

Commercial General Liability $2,000,000

Automobile Liability $1,000,000

Product Liability as set forth in the Purchase Order, if any;

Pollution Insurance as set forth in the Purchase Order, if any;

28. Termination for Default Any failure by Contractor to perform or comply with the terms and conditions of the Purchase Order which continues for ten (10) calendar days after written notice from FMPA to Contractor demanding that such failure to perform be cured, shall be deemed an event of default by Contractor. Upon the occurrence of any such event of default, FMPA may terminate the Purchase Order and pursue any remedies available at law or in equity.

29. Termination for Convenience FMPA shall have the right in its sole discretion to terminate by written notice, in whole or in part, the Purchase Order for its convenience. FMPA shall pay Contractor for any Services performed under the Specifications of the Bid Package prior to the termination date.

30. Termination for Cause The performance of work on a Purchase Order issued under this Award agreement may be terminated for cause by a FMPA or Participating Member (s) in accordance with this clause in whole, or from time to time, in part, whenever the authorized FMPA or Member representative, in his or her sole judgment, determines that the Awarded Bidder is not meeting the minimum performance level required. If the Award agreement is terminated under this provision, the FMPA or Member shall not be required to purchase any remaining items or continue any work. Additionally, the terminated Bidder shall not be eligible for consideration for any replacement Award agreement.

FMPA shall have the right in its sole discretion to terminate by written notice, in whole or in part, the Purchase Order for performance issues. FMPA reserves the right to terminate the Contract with that Contractor(s) and re-advertise or select a second Contractor(s) from the original solicitation.

31. Use of Ideas All materials submitted in response to the RFP become the property of FMPA and will be returned only at the option of FMPA. Except as otherwise prohibited by law, FMPA has the right to use any and all ideas presented in response to this RFP. Selection or rejection of a proposal does not affect this right.

32 Warranties Reference Warranty section of Appendix B, page 3.

33. Hazardous Materials of Contractor Any Hazardous Materials used by Contractor in the performance of the Services shall be packaged, shipped, handled, labeled and disposed of by Contractor in a manner that complies with all federal, state and local laws or regulations applicable to Hazardous Materials. No Hazardous Materials shall be stored by Contractor at the FMPA and its Member’s Facility before, during or after the performance of Services hereunder.

Contractor shall, at its expense, remove, transport and dispose of all Hazardous Materials

(i) brought by Contractor to the Facility or (ii) disturbed by Contractor’s performance of Services or created by Contractor’s use, handling or combination of non-hazardous materials brought by Contractor to the Facility during the performance of Services. For purposes of the Purchase Order, the term “Hazardous Materials” shall mean any substance which by law requires special handling, containment or disposal, including without limitation “hazardous substances” as defined in the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended (42 USC Sections 9601, et seq.), the Hazardous Materials Transportation Act, as amended (49 USC Sections 5101, et seq.), “hazardous wastes” as defined in the Resource Conservation and Recovery Act, as amended (42 USC Sections 9601, et seq.), “toxic substances” as defined in the Toxic Substance Control Act as amended (15 USC Section 2601 et seq.), as amended and in the regulations adopted, published, and promulgated pursuant thereto. Contractor shall be responsible for obtaining and maintaining any licenses, permits, and/or other authorizations of any kind required for the performance of the Services. Contractor shall pay all costs of such licenses, permits and authorizations and all costs and expenses incurred in obtaining and maintaining them. The Contractor shall comply with all federal, state and local laws, and rules and regulations that are applicable to the performance of the services requested by FMPA.

34. Safety and Protection Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with work under this RFP. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:

1. All persons on the site who may be affected by the project work;

2. All Work and materials and equipment to be incorporated therein, whether in storage on or off of the project site. Any off-site storage logistics such as sourcing/allocation, safety, security and transfer/delivery, etc. will be the sole responsibility of the contractor.

3. Other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and underground facilities not designated for removal, relocation or replacement in the course of the project.

35. Control of Work and Subcontractors Contractor shall be solely responsible for all construction means, methods, techniques, sequences, procedures, and safety programs in connection with the performance of the Work. In addition, Contractor shall be solely responsible for the engagement and management of any subcontractors used to perform any portion of the Work.

36. Domestic Preference As appropriate and to the extent consistent with law, Contractor should, to the greatest extent practicable, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States (including but not limited to iron, aluminum, steel, cement, and other manufactured products).

37. Public Records Supplier acknowledges that FMPA is subject to Florida’s Government in the Sunshine Law, including, without limitation, Chapter 119, Florida Statutes. As such, any documents submitted in response to this RFP may be public records subject to public disclosure. Please refer to Section 17, above, for confidential proprietary business information or trade secrets contained in such records. If Supplier does not designate its confidential proprietary business information in its response in accordance with Section 17, above, FMPA may disclose all undesignated information that FMPA is legally bound to disclose in response to a public records request.

38. Change Orders Contractor is not authorized to act on any Change Order until they receive a written revision to the Purchase Order for the added scope and price.

FMPA has no obligation to pay for any goods or services outside of the authorized Purchase Order.

APPENDIX A

SCOPE OF WORK

TCEC High-Pressure Superheater & Reheater Sky Vent Valves Scope

1. Project Overview

The Florida Municipal Power Agency (FMPA) is requesting proposals for a long-life replacement of the high-pressure superheater & reheater sky vent vales at the Treasure Coast Energy Center. In addition, FMPA also requests an adder option for the commissioning of the valves.

All base and adder scopes shall include the supply of all technical operational manuals and drawings, materials and kits, technical supervision, and labor necessary to complete the outlined scope for the fall 2026 outage. As the awarded vendor will be responsible for the delivery of materials; ALL parts, drawings and technical information arrival at TCEC is due by September 30, 2026.

Installation and commissioning for the valve for the fall 2026 outage is currently scheduled for December 3-10, 2026.

2. Scope of Work

Vendor shall provide a complete itemized turnkey all-in firm quote for material (plus freight & tariffs), labor/support & supervision, equipment and documentation for each valve manufacturing and commissioning.

The tasks responsible of the vendor are as follows:

• Review in detail the supplied current valve design & currently installed arrangement information provided with this RFP package.

• Supply complete fully functioning severe-duty valves that will be placed into service in the outside elements that meet or exceed the “as new” performance of the existing valves that are fully compatible with the currently installed piping (type & schedule, routing, etc.), electrical/controls, available instrumentation air and noise level.

• Complete valve assemblies & associated hardware are identified as:

o Automatic actuator assembly with bonnet & stem assembly o Valve body (with finished seat) o Trim, hardware/gland packing assemblies o Seals/gaskets o Stainless 316 hardware, tubing & fittings o Accessory kit (incl. positioner, airset/filter regulator, solenoid valve, limit switches, etc.)

• I&C Information & Supply o Supply all wiring and pneumatic connectors specific to proposed valve o Current available air specifications at the valves are: 100 PSI (+/-5 PSI), with

-40°F (+/-10°F) dew point o Current DCS information

Demand & position feedback: 4-20 mA dc analog Valve positioner: Smart positioner w/ HART protocol & diagnostics o Fail position: CLOSED

• Corrosion Protection o All exterior valve components shall be materials that are designed for long-life, corrosion resistant and coated (where applicable) to withstand frequent misting of moist air with +600 ppm in chlorides, daily rain and direct UV exposure.

• Technical Information & Installation/Commissioning Scope o Supply complete mechanical, wiring & control drawings all with dimensions specific to proposed valves o Supply complete detailed technical specifications (cut-sheets) specific to proposed valves o Supply complete ANSI B16.25 approved installation & operation instructions specific to TCEC & proposed valves that will require post-weld heat treatment (i.e., any trim parts removal, etc.)

o Supply on-site field technical I&C installation support, in addition to any technical, mechanical and commissioning support Note: FMPA will be contracting TEiC for mechanical (welding) installation of the valves with new P91 & P22 piping requiring post-weld heat treatment in strict accordance with the vendor installation instructions and ANSI B16.25 code. Precision Electric will be contracted for I&C installation scope.

o If the proposed individual high-pressure superheater & reheater valve weights exceed 1,512 & 1,621 Lbs, respectively, by more than 10%, then vendor shall evaluate the current structural support system for adequate design and present findings to FMPA. If current support is found to be insufficient, vendor will engineer & supply additional valve and/or piping support material(s), drawings (PE stamped) and installation labor within the required dates as identified in the RFP packet.

• Supply base warranty

• Option Adders o Warranty extension options o Manual actuator assembly(s) o Recommended spare parts

3. Additional Services Required (Turnkey Supply and Installation)

Proposer shall include all the following in the proposal:

• Technical advisor services

• On-site supervision

• Qualified craft labor

• All required materials, including a minimum of 15% spare quantity(s) of consumables

• Built-in three (3) day 10 hr./day base schedule slippage full crew labor costs, with a pro-rate deduct if not utilized

• Packaging and shipping to site (incl. tariffs)

• All tools and equipment

• Warranty for parts and labor on all materials and workmanship

• Experience list and references for completed projects of this type

4. Deliverables

• Detailed bill of materials and corresponding coverage area by September 30, 2026.

• Detailed warranty & expected lifespan Information with the proposal

• Safety and QA/QC Plan with the proposal

• Labor and Equipment Rates with the proposal

• Lump Sum Pricing

5. Site Information

Location:

FMPA Treasure Coast Energy Center 4545 Energy Lane Fort Pierce, FL 34772

6. Division of Responsibilities

Item Supplier FMPA Sanitary and Wash Facilities X Office and Break Trailers X

LOTO X

Safety Orientation X Forklift, etc. and Material Handling X Electrical & Pneumatic Supply X I&C Installation X Field Support & Commissioning X Materials X Mechanical Installation X

7. Evaluation Criteria

Proposals will be evaluated based on the following:

• Technical compliance with specifications

• Vendor experience and references

• Schedule and delivery timelines

• Warranty and support offerings

• Safety and quality plans

• Cost competitiveness

• Other (FMPA discretion)

HIGH-PRESSURE SUPERHEATER

SPECIFICATIONS & DRAWINGS

chucks Oval

COPES-VULCAN

VALVES & CONTROLS

Installation & Instruction Manual

TABLE OF CONTENTS

60:37:30 General Information

01 :P112:37 Storage Recommendations for Diaphragm-Operated Valves & Desuperheaters

SECTION 1.0 GS & SD CONTROL VALVES

Model: 6" (150mm), CL2500, C12A, BW, SD-700-160RA Application: HP Startup Vent Serial Number: 0610-129856-1-1 Tag: 11-SGG-PCV-l 602-32

SK-A-10-129856-A Control Valve Outline Dimensions Control Valve Specification Sheet Recommended Spare Parts List

APPLICABLE DRAWINGS & BILLS OF MATERIAL (SEE SECTION 1.1)

C-360475 Actuator Assembly / VACT410140531 C-342111 Trim Assembly / VTRM506103712103 C-359260 Hardware Pack Assembly / VHDP5215112 D-3 89021 Accessory Kit / V3 89021 D-357435 Accessory Kit / V357435 D-389022 Wiring Diagram / V389022

SECTION 1.0 GS & SD CONTROL VALVES

Model: 4" (100 mm), CL600, WCB, BW, GS-700-100RA Application: IP Startup Vent Serial Number: 0610-129856-2-1 Tag: li-SGJ-PCV-1702-32

SK-B-10-129856-A Control Valve Outline Dimensions Control Valve Specification Sheet Recommended Spare Parts List

ACCESSORIES:

POSITIONER: Copes SIPART PS2. Single Acting

1/2" NPT customer conduit connection

AIRSET: SMC AW20-N02-CZ

1/4" NPT customer air supply connection

SOLENOID VALVE: Asco 8300D61U 7/8" Dia. hole for 1/2" NPT customer conduit connection

LIMIT SWITCH: (2) Allen-Bradley 802T-ATP

CUSTOMER NAME: Vogt Power International

USER NAME: Florida Municipal Power Agency - Treasure Coast

CUSTOMER PO: V0000389

CVJOB. 0610-129856

TAG: 11-SGG-PCV-1602-32

SERIAL #: 0610-129856-1-1

APPLICATION: HP Startup Vent

VALVE END CONNECTIONS:

Butt Weld per ANSI B16.25, Fig. 2b

Inlet: 6 inch Sen 160 Outlet: 6 inch Sen 80

ACTUATOR:

Reverse Acting - Spring to close Increase in control pressure opens valve

— 9.25 [235.0] CLEARANCE REQD

FOR ACTUATOR REMOVAL

1/2" NPT CONDUIT

CONNECTION FOR

WIRING TO EACH

SWITCH

THE INFORMATION CONTAINED HEREIN IS PROPRIETARY TO

COPES-VULCAN AND IS NOT TO BE REPRODUCED OR GIVEN

TO ANY OTHER FACILITY WITHOUT THE PRIOR WRITTEN

CONSENT OF COPES-VULCAN. ANY USE OF THIS INFORMATION

IN ANY WAY DETRIMENTAL TO COPES-VULCAN IS PROHIBITED

1. ALL DIMENSIONS ARE IN INCHES AND ARE

REFERENCE UNLESS OTHERWISE SPECIFIED.

BRACKETS INDICATE METRIC EQUIVALENTS.

2. APPROX. TOTAL VALVE WEIGHT: 1512 lbs [686 kg]

C O P E S - V U L C A N , SPX Valves & Controls McKean, PA USA

Phone: 811-476-5800 Fax: B14-476-5654

61150] CLASS 2500

SD SERIES VALVE

BUTT WELD ENDS

WITH MODEL 700-160 RA ACTUATOR

• CERTIFIED CORRECT BY : A- LOO 2.^1 AjL- DATE: B-li-Otm VALVE OUTLINE DIMENSIONS

Nof SK-A-10-129856-A Rev.5REFERENCE SPEC SHEET' Q.Uobs-2006V129B56-1.VS3 Rev.5. tgc, Aug-01-2006

COPES-VULCAN, SPX Valves & Controls McKean, PA USA

Phone: 614-476-5800 Fax: 614-476-5854

CONTROL VALVE

SPECIFICATION SHEET

CV Inquiry: 91-90801-10 CV Job: 0610-129856

CV Job Ref:

CV Serial #: 0610-129856-1-1

Quantity: 1

Customer Name: Vogt Power International ustomer Inquiry: ..377 (17424)

Customer PO: V0000389 Ultimate User: Florida Municipal Power Agency - Treasure Coast

Tag: 11-SGG-PCV-1602-32 Application: HP Startup Vent

Description: 6" (150 mm), CL2500, C12A, BW, SD-700-160 RA

SERVICE CONDITIONSFLUID: Steam Valve Outlet Vel.

tft/min)_(lb/hr)_ Remarks

228350Hot Start 192328Warm Start 129896Cold Start

MinFlow

Estimated Noise Level with 3" of InsulationAllowable Leakage:SHUTOFF

DESIGN

BODY AND BONNET

Bonnet Type: Bolted

Packing Material: Graf oil Packing Hardware: Stainless Steel

Packing Nut Torque: 18 tt-lbs.

Options: Single Packed

Style: SD - Severe Duty, Globe Size: 6 inch

ASME Class: 2500 Standard Body Inlet: Butt Weld, Sch 160 per ANSI B16.25, Fig. 2b

Body Outlet: Butt Weld, Sch 80 per ANSI B16.25, Fig. 2b Material: A-217C12A

Inlet Pipe: 6 in. {150 mm), Sch 160 Outlet Pipe: 6 In. (150 mm), Sch 80

Seat Type: METAL Trim Material: 400/70 SST

Max. Cv Available: 321 @Max. Trim Travel of 2.5" (±1/8) Min. Controllable Cv of Trim: 8

Size: 6 inch with 32 Starts Style: TANDEM w/Slots (Balanced)

Flow Direction: OVER THE WEB em Diameter: 1.00 in.

haracteristic: TANDEM SLOT

• ^ ACTUATOR

Actuator Mounting Style: 4x Studded

Actuator Spnng: 357576 Spring Rate: 1280 (lbs/inch)

Max. Stem Thrust Required to Close: 2021 (lbs) Max. Stem Thrust Required to Open: 4998 (lbs)

Spring Precompression (Diaphragm Air Pressure): 13 (psig) Pressure @ Full Valve Travel (With No Internal Valve Pres.): 33 (psig)

Style: 700 DIAPHRAGM Size: 160 (Square Inch)

Action: Spring Closing (Reverse) Handwheel; Side Mounted

Frame Material: Ductile Iron Air Pressure Available: 70 psig Air Pressure Required: 69 psig

ACCESSORIES

Positioner: Copes SIPART PS2, Single Acting Airlock: None

Filter/Regulator: SMC AW20-N02-CZ Qty: 1 Solenoid Valve: Asco 8300D61U H20VAC/60hz) Qty: 1

De-energize to vent actuator Booster Relay: None

Additional Acc'y: Junction Box - NEMA4X Qty 1

Positioner Input Range Position FeedBack Module (4-20ma)

Alarm Module HART Module

4-20 mA

Piping: Stainless Steel Tubing (Swagelok) Limit Switches: Allen-Bradley 802T-ATP Qty: 2

COMMENTS

(1) The VPI specified outlet pressure of 265 psia at the MinFlow condition is considered by the Seller to be incorrect The approx valve outlet pressure at this condition Is 18.7 psia.

(2) There are no stroke time requirements.

(3) Maximum flow based on maximum silencer back pressure of 485.6 psig (500.3 psia). Hot start flow has been reduced from 241,318 Ib/hr to 228,350 Ib/hr to limit valve outlet and piping velocity head to 30 psia.

AUQ-07-2006MinFlow was P1-950. P2-522.5, T1-1055Model = Body Option:

Bonnet Option:

Trim Option:

ardware Pack Option:

Actuator Option:

Stem Option:

Gasket Option:

Accessory Kit Option:

ID. Plate:

BDY506640916D

BNT506380916

TRM506103712103

HDP5215112

ACT510140531

STM52706012041

GSK5060601091

AC7A25*60022023

OPT198746.

Aua-07-2006P2s were 395.5f hot) - 405.9<warm) - 415.3(cold) AUQ-01-2006P2s were 265(hot) -199(warm) -119.4fcokj) AUQ-01-2006deleted upset & min conditions / added 40% conditions Jul-06-2006Valve & outlet pipe size were 6 inch Jun-22-2006VPI Rev 1, 5721/06AWW Auq-12-2006Alternate w/increased silencer P2 Auq-08-2006added notes 1. 2 & 3 in COMMENTS section Auq-O7-2006outlet pipe size was 6" / actuator was 1000-320

DescriptionInitials File Name: Q:\Jobs-2006\129856-1.VS3 (9.2.11)Program Rev Level: 9.2.11

Project No.: 17424 Customer: UE/TIC Treasure Coast

Vogt Power International Line List

Doc . No. 017424-ICNA-001 Revision: 01

Line_Tag Cust_Tag Service Spec Size1 Schedule Pipe_Matl Sys D_Press_PSIG D_Temp_F Insul_Thk PID_File Notes L-1601 11-SGG-1601 HPSH OUTLET FEEDER BAH 4 160 SA -335 P91 HP 2363 1066 4.5 017424-ICND-002-03 L-1602 11-SGG-1602 HPSH OUTLET START UP VENT BAH 6 160 SA-335 P91 HP 2363 1066 4.5 017424-ICND-002-03 L-1603 11-SGG-1603 HPSH START UP VENT OUTLET EBD 6 80 SA-335 P22 HP 930 992 5 017424-ICND-002-03 L-1604 11-SGG-1604 HPSH OUTLET SAFETY VALVE BAH 2.5 SPECIAL SA-335 P91 HP 2363 1066 4.5 017424-ICND-002-03 L-1605 11-SGG-1605 HPSH SAFETY VALVE OUTLET GBD 6 40 SA-335 P22 HP 342 965 4.5 017424-ICND-002-03 L-1606 11-SGG-1606 HPSH OUTLET PRESS IND BAH 1 80 SA-335 P91 HP 2363 1066 4.5 017424-ICND-002-03 L-1607 11-SGG-1607 HPSH OUTLET PRESS TRANS BAH 1 80 SA-335 P91 HP 2363 1066 3.5 017424-ICND-002-03 L-1608A 11-SGG-1608A HPSH STEAM SAMPLE BHH 0.75 80 A-312 TP316H HP 2363 1066 3.5 017424-ICND-002-03 L-1608B 11-SGG-1608B HPSH STEAM SAMPLE BHH 0.75 80 A-312 TP316H HP 2363 1066 3.5 017424-ICND-002-03 L-1610 11-SGG-1610 HPSH X-OVER BAK 6 160 SA -335 P91 HP 2560 1041 0 017424-ICND-002-03 L-1611 11-SGG-1611 HPSH CROSSOVER DRAIN BAH 2 160 SA-335 P91 HP 2560 1041 3.5 017424-ICND-002-03 L-1612 11-SGG-1612 HPSH OUTLET BAH 12 160 SA-335 P91 HP 2363 1066 5.5 017424-ICND-002-03 L-1615 11-SGG-1615 HP ATTEMP FEEDER BAK 6 120 SA -335 P91 HP 2560 1017 5 017424-ICND-002-03 L-1616 11-FWA-1616 HP ATTEMP LOOP BAK 12 140 SA -335 P91 HP 2560 1016 5.5 017424-ICND-002-03 L-1618 11-SGG-1618 HP SH2 FEEDER FROM ATTEMP BAK 6 120 SA -335 P91 HP 2560 1016 5 017424-ICND-002-03 L-1619 11-SGG-1619 HP ATTEMP PRESSURE TRANS BAH 1 80 SA-335 P91 HP 2560 1016 3.5 017424-ICND-002-03 L-1620 11-SGG-1620 HP ATTEMP DRAIN POT BAH 4 120 SA-335 P91 HP 2560 1016 4.5 017424-ICND-002-03 L-1621 11-SGG-1621 HP ATTEMP DRAIN POT DRAIN BAH 2 160 SA-335 P91 HP 2560 1016 3.5 017424-ICND-002-03 L-1622 11-SGG-1622 HP ATTEMP VENT BAH 1 80 SA-335 P91 HP 2560 1016 3.5 017424-ICND-002-03 L-1623 11-SGG-1623 HP ATTEMP DRAIN BAH 2 160 SA-335 P91 HP 2560 1017 3.5 017424-ICND-002-03 L-1624A 11-SGG-1624A HP ATTEMP DRAIN BBD 2 80 SA-335 P22 HP 150 365 2 017424-ICND-002-03 TRANSITION BETWEEN P-91 AND CARBON STEEL L-1624B 11-SGG-1624B HP ATTEMP DRAIN BDD 2 80 SA-106 Gr. B HP 150 365 2 017424-ICND-002-03 L-1625 11-SGG-1625 HPSH X-OVER CBK 6 120 SA -335 P22 HP 2560 814 0 017424-ICND-002-03 L-1626 11-SGG-1626 HPSH CROSSOVER DRAIN CBH 2 160 SA-335 P22 HP 2560 814 3.5 017424-ICND-002-03 L-1630 11-SGG-1630 HPSH SUPPLY CEK 6 120 SA - 106 C HP 2560 673 3 017424-ICND-002-03 L-1631 11-SGG-1631 HP SAT STEAM SAMPLE CHH 0.75 80 A-312 TP316H HP 2560 673 2 017424-ICND-002-03 L-1632 11-SGG-1632 HPSH OUT HYDRO CONNECTION CEK 1 80 SA-106 Gr. C HP 2560 673 2 017424-ICND-002-03 L-1635 11-SGG-1635 HP DOWNCOMER CEK 16 120 SA - 106 C HP 2605 675 3.5 017424-ICND-002-03 L-1636 11-SGG-1636 HPEV FEEDER CEK 6 120 SA - 106 C HP 2605 675 0 017424-ICND-002-03 L-1637 11-SGG-1637 HPEV FEEDER CEK 6 120 SA - 106 C HP 2605 675 0 017424-ICND-002-03 L-1638 11-SGG-1638 HPEV FEEDER CEK 6 120 SA - 106 C HP 2605 675 0 017424-ICND-002-03 L-1639 11-SGG-1639 HP INTERMITTENT BLOWDOWN FRONT CDH 2 160 SA-106 Gr. B HP 2830 675 3 017424-ICND-002-03 L-1640 11-SGG-1640 HP DOWNCOMER CEK 6 120 SA - 106 C HP 2605 675 3 017424-ICND-002-03 L-1641 11-SGG-1641 HPEV FEEDER CEK 4 160 SA - 106 C HP 2605 675 0 017424-ICND-002-03 L-1642 11-SGG-1642 HPEV FEEDER CEK 4 160 SA - 106 C HP 2605 675 0 017424-ICND-002-03 L-1643 11-SGG-1643 HP INTERMITTENT BLOWDOWN REAR CDH 2 160 SA-106 Gr. B HP 2830 675 3 017424-ICND-002-03 L-1644 11-SGG-1644 HP EVAP RISER CEK 4 120 SA - 106 C HP 2605 675 3 017424-ICND-002-03 L-1645 11-SGG-1645 HP EVAP RISER CEK 6 120 SA - 106 C HP 2605 675 3 017424-ICND-002-03 L-1646 11-SGG-1646 HP EVAP RISER COLLECTION CEK 10 120 SA - 106 C HP 2605 675 3.5 017424-ICND-002-03 L-1647 11-SGG-1647 HP EVAP RISER CEK 6 120 SA - 106 C HP 2605 675 3 017424-ICND-002-03 L-1648 11-SGG-1648 HP EVAP RISER CEK 6 120 SA - 106 C HP 2605 675 3 017424-ICND-002-03 L-1649 11-SGG-1649 HP EVAP RISER CEK 6 120 SA - 106 C HP 2605 675 3 017424-ICND-002-03 L-1650 11-FWA-1650 HP ATTEMP SPRAYWATER BDD 2 160 SA-106 Gr.B HP 3475 360 1.5 017424-ICND-002-03 L-1651A 11-FWA-1651A HP ATTEMP SPRAYWATER BBH 2 160 SA-335 P22 HP 3475 360 1.5 017424-ICND-002-03 TRANSITION BETWEEN P-91 AND CARBON STEEL L-1651B 11-FWA-1651B HP ATTEMP SPRAYWATER BAH 2 160 SA-335 P91 HP 2560 1017 3.5 017424-ICND-002-03 L-1652A 11-FWA-1652A HP ATTEMP SPRAY FLOW TRANS BDD 0.75 80 SA-106 Gr. B HP 3475 360 1.5 017424-ICND-002-03 L-1652B 11-FWA-1652B HP ATTEMP SPRAY FLOW TRANS BDD 0.75 80 SA-106 Gr. B HP 3475 360 1.5 017424-ICND-002-03 L-1653 11-FWA-1653 HP ATTEMP SPRAY PRESS IND BDD 1 80 SA-106 Gr. B HP 3475 360 1.5 017424-ICND-002-03 L-1654 11-FWA-1654 HP ATTEMP SPRAYWATER DRAIN BDD 1 80 SA-106 Gr. B HP 3475 360 1.5 017424-ICND-002-03 L-1660A 11-FWA-1660A HP ECON INLET BEH 10 1.25 SA-106 Gr. C HP 3475 673 3.5 017424-ICND-002-03 L-1660B 11-FWA-1660B HP ECONOMIZER INLET BEH 10 160 SA-106 Gr. C HP 2920 673 3.5 017424-ICND-002-03 L-1661 11-FWA-1661 HP ECON FEEDER BEH 5 160 SA - 106 C HP 2920 673 3 017424-ICND-002-03 L-1662 11-FWA-1662 HPEC INLET DRAIN BDH 1 80 SA-106 Gr.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .