Task Order
Performance Work Statement
Project Title: Boundary Line Maintenance, Cabin Lot Surveys, Ground Maintenance, Clarence Cannon NWR HREP Year 1, and 2023 Forestry Projects
This project involves conducting boundary line maintenance and cabin lot surveys as well as ground maintenance. Boundary maintenance and cabin lot surveys will take place along the Mississippi River in River Pools 24 and 25, lower Mississippi, and along the lower Illinois River). Total distance is approximately 46.6 miles of boundary line maintenance (Section 1.0) and the survey of 37 cabin lots (Section 3.0). The project will also authorize the replacement of missing and damaged monuments by a certified surveyor (Section 2.0). The cabin lot surveys will include a survey of the currently leased subdivision lots, pinning, and demarcation by placement of boundary signs at the 4 corners of the lot.
Ground maintenance will include herbicide spraying for invasive species control, mowing, and the use of a seed drill. Maintenance will take place at the Riverlands Migratory Bird Sanctuary in St. Charles County, MO and Timber Ridge Natural Area in Madison County, IL. (Sections 4.0 and 5.0)
Forestry projects include a large amount of timber stand improvement and supplement tree planting in Mississippi River pools 24 and 26 near Ashburn, MO and St. Charles, MO. (Sections 6.0 and 7.0)
Clarence Cannon NWR HREP project is a restoration and TSI effort at Clarence Cannon National Wildlife Refuge in Pool 25 of the Mississippi River near Annada, MO. (Section 8.0, 9.0, 10.0, and 11.0)
Mobilization and demobilization will be calculated as if traveling from the Rivers Project Office (301 Riverlands Way, West Alton, MO 63386).
All work shall be completed in accordance with the contract specifications and Corps of Engineers Manual EM 385-1-1.
Work Period:
Boundary Maintenance and Cabin Lot Surveys: Date of Award - June 30, 2024.
Ground Maintenance: Date of Award -November 30, 2023
Forestry Projects: October 1, 2023- December 31, 2023
Clarence Cannon NWR HREP: Date of Award - December 31, 2023
Boundary Groups: 41IL Cincinnati Landing (1.78 miles), 38M Eagle, Westport (1.71 miles), 41M Crider, Louisiana, Blackburn (4.3 miles), 33IL Mortland (12.1 miles), 39IL Two Rivers, Gosline, L&D 24 (10.91 miles), 26IL Chain of Rock North (11.12 miles), and 38IL Pleasant Hill (2.68 miles), 46.6 miles total.
Subdivisions: Cincinnati Landing (37 lots)
Location: River Pools 24, 25, and 26, lower Mississippi River, and the lower Illinois River
1.0. Boundary Line Maintenance
1.1 Location: River Pools 24 and 25, lower Mississippi, and along the lower Illinois River
1.2. General Scope:
The primary focus of the project is to clear woody and herbaceous vegetation along boundary lines, demarcating boundary lines by installing/replacing boundary posts and signage, and reporting any boundary encroachments, trespasses, or missing monuments. Work will include the use of chainsaws, brush cutters, and hand tools, application of herbicide to cut stumps, and survey level and GPS to identify boundary line. Contractor will compile reports and identify any encroachments (Appendix A, Exhibits F-1 to F-3) along the following boundary groups: 38M Eagle, Westport (1.71 miles), 41M Crider, Louisiana, Blackburn (4.3 miles), 33IL Mortland (12.1 miles), 39IL Two Rivers, Gosline, L&D 24 (10.91 miles), 41IL Cincinnati Landing (1.78 miles), 26IL Chain of Rock North (11.12 miles), and 38IL Pleasant Hill (2.68 miles) (Figure 1). Government will furnish galvanized steel channel posts, signage, hardware, magnet detector, boundary survey notes, and boundary survey maps.
The Contractor shall perform all work in accordance with this Statement of Work and the base Contract.
Contractor shall coordinate with Rivers Project Office and do a site walk of the areas to be treated and worked through this Statement of Work, prior to initiation of work. Contractor shall be responsible for ensuring a qualified licensed applicator can apply all herbicides in accordance with all manufacturer recommendations and all Federal, State and/or local laws and regulations.
1.3. Order and Coordination. 41IL Cincinnati Landing (1.78 miles), 38M Eagle, Westport (1.71 miles), 41M Crider, Louisiana, Blackburn (4.3 miles), 33IL Mortland (12.1 miles), 39IL Two Rivers, Gosline, L&D 24 (10.91 miles), 26IL Chain of Rock North (11.12 miles), and 38IL Pleasant Hill (2.68 miles)
1.4. Work Period. Date of Award - June 30, 2024.
1.5. Boundary Group 41IL. Boundary Group Cincinnati Landing is located within Pike County, IL and totals 1.78 miles. (Fig. 2). There are at least 13 Angle Points. Site can be accessed via Hwy 96 and 245th Avenue. All angle points should be accessible by land during normal flood conditions. RPO will provide Plat Maps to assist contractor in maintenance.
1.6. Boundary Group 38M. Boundary Group 38M (Eagle, Westport) totals 1.71 miles in length and is in Lincoln County, MO. (Fig. 3). There are 19 Angle Points in total. Site can be accessed from Hwy 94 and through Leach Memorial Conservation Area. All angle points should be accessible by land during normal flood conditions. RPO will provide Surveyor Reports and Plat Maps to assist contractor in maintenance.
1.7. Boundary Group 41M. Boundary Group 41M (Crider, Louisiana, Blackburn) is separated into five sections totaling 4.3 miles in length and all sections are located within Pike County, MO. (Fig. 4). There are 41 Angle Points in total. Sites can be accessed from Hwy 79. All angle points should be accessible by land during normal flood conditions. RPO will provide Surveyor Reports and Plat Maps to assist contractor in maintenance.
1.8. Boundary Group 33IL. Boundary Group 33IL (Mortland) is separated into three sections totaling
12.1 miles in length and is in Calhoun County, IL. (Fig. 5). There are 102 angle points in total. Sites can be accessed from Illinois River Road, N Mississippi River Road, and Two Rivers Wildlife Refuge (Batchtown).
RPO will provide Surveyor Reports and Plat Maps to assist contractor in maintenance.
1.9. Boundary Group 39IL. Boundary Group 39IL (Two Rivers, Gosline, L&D 24) totals 10.91 miles in length and is in Pike County, IL. (Fig. 6). There are 107 Angle Points in total. Site can be accessed from Hwy 54, Ralphs Landing Rd, and Two Rivers Boat Ramp. RPO will provide Surveyor Reports and Plat Maps to assist contractor in maintenance.
1.10. Boundary Group 26IL. Boundary Group 26IL Chain of Rock North totals 11.12 miles is located within Madison County, IL. (Fig. 7). There are at least 146 Angle Points. Site can be accessed via Illinois 3, Chain of Rocks Canal Bridge, and Frontage Road. All angle points should be accessible by land during normal flood conditions. RPO will provide Plat Maps to assist contractor in maintenance.
1.11. Boundary Group 38IL. Boundary Group 38IL (Pleasant Hill) totals 2.68 miles located within Pike and Calhoun County, IL. (Fig. 8). There are at least 43 Angle Points. Site can be accessed via Clarksville Dam Waterfront and Iowa Cutoff Rd. All angle points should be accessible by land during normal flood conditions. RPO will provide Plat Maps to assist contractor in maintenance.
2.0. Monument Replacement.
2.1 Location: River Pools 24 and 25, lower Mississippi, and along the lower Illinois River.
2.2. General Scope: The primary focus of this section is to replace boundary monuments that are missing or damaged as determined during boundary maintenance and inspection identified above and from previous inspections on the Mississippi River. Contractor is not authorized to go above this without first contacting the RPO. Surveyor will stamp monuments with Angle Point (identified by USACE), surveyor’s number and direction of boundary line. Upon completion of survey and monument emplacement.
Surveyor will record annotated survey notes with the appropriate County Recorder’s Office. A copy of the survey notes will be provided to the Rivers project Office. Work is to be performed following boundary maintenance and no later 30June2024. Government will furnish Official USACE Boundary Monuments.
2.3. Order and Coordination. 41IL Cincinnati Landing (1.78 miles), 38M Eagle, Westport (1.71 miles), 41M Crider, Louisiana, Blackburn (4.3 miles), 33IL Mortland (12.1 miles), 39IL Two Rivers, Gosline, L&D 24 (10.91 miles), 26IL Chain of Rock North (11.12 miles), and 38IL Pleasant Hill (2.68 miles)
2.4. Work Period. Date of Award - June 30, 2024.
Figure 1. Location of boundary groups projected for maintenance in 2023/2024. Anticipate a total of 46.6 miles of boundary maintenance across the Upper and Lower Mississippi River and Lower Illinois River.
N
28 IL – Cincinnati Landing
39IL – Two Rivers, Gosline, L&D 24
28 IL – Crider, Louisiana, Blackburn
38IL – Pleasant Hill
38M – Eagle, Westport
33IL -
Mortland
26 IL – Chain of Rocks North
Figure 2. Boundary Group Cincinnati Landing is located within Pike County, IL and totals 1.78 miles. There are at least 13 Angle Points. Site can be accessed via Hwy 96 and 245th Avenue.
28 IL
1.78 miles total
Hwy 96
245th Ave
Figure 3. Boundary Group 38M (Eagle, Westport) totals 1.71 miles in length and is in Lincoln County, MO. (Fig.
3). There are 19 Angle Points in total.
38M
1.71 miles
Hwy 79
Figure 4. Boundary Group 41M (Crider, Louisiana, Blackburn) is separated into five sections totaling 4.3 miles in length and all sections are located within Pike County, MO. There are 41 Angle Points in total. Sites can be accessed from Hwy 79.
41M
4.3 miles total
Figure 5. Boundary Group 33IL (Mortland) is separated into three sections totaling 12.1 miles in length and is in Calhoun County, IL. There are 102 angle points in total. Sites can be accessed from Illinois River Road, N Mississippi River Road, and Two Rivers Wildlife Refuge (Batchtown).
33IL
12.1 miles
33IL
12.1 miles
Illinois River Road
Figure 6. Boundary Group 39IL (Two Rivers, Gosline, L&D 24) totals 10.91 miles in length and is in Pike County, IL. (Fig. 6). There are 107 Angle Points in total. Site can be accessed from Hwy 54, Ralphs Landing Rd, and Two Rivers Boat Ramp.
39IL
10.91 miles
Two Rivers North Access
Ralphs Landing Rd
Figure 7. Boundary Group 26IL Chain of Rock North totals 11.12 miles is located within Madison County, IL.
There are at least 146 Angle Points. Site can be accessed via Illinois 3, Chain of Rocks Canal Bridge, and N Slough Rd.
26IL
11.12 miles
Chain of Rock Bridge
N Slough Rd
Figure 8. Boundary Group 38IL (Pleasant Hill) totals 2.68 miles located within Pike and Calhoun County, IL. (Fig.
8). There are at least 43 Angle Points. Site can be accessed via Pleasant Hill Rd, and Iowa Cutoff Rd.
3.0. Cabin Lot Survey and Demarcation
3.1 Location: Mississippi River Pool 24
3.2. General Scope:
The primary focus of this project is to survey existing leased cabin lots on the Rivers Project management area and to pin and demarcate each corner of the lot. Cabin lots to be surveyed are in Cincinnati Landing subdivision in Pike County, IL (Figure 9) A copy of the survey notes will be provided to the Rivers Project Office. Upon completion of survey and signage emplacement, surveyor will record annotated survey notes with the appropriate County Recorder’s Office. Work is to be performed following boundary maintenance and no later than 30June2024.
Contractor will install boundary posts and signage at the corners of each cabin lot surveyed during this project. Cabin Subdivision to be maintained is Cincinnati Landing (Figure 9). Surveyors will mark the four corners of the cabin lot to identify lot boundary and bury a pin to mark its location. Boundary signs and
38IL
2.68 miles
Pleasant Hill Rd.
Iowa Cutoff Rd.
posts will be placed at these corners. Contractors will also take a photo of each corner once appropriate boundary signage is placed. Photos will be provided to the Rivers Project Office along with survey coordinates and annotated notes and drawings. Government will furnish galvanized steel channel posts, signage, hardware, and survey plats.
The Contractor shall perform all work in accordance with this Statement of Work and the base Contract.
Contractor shall coordinate with Rivers Project Office and do a site walk of the areas to be treated and worked through this Statement of Work, prior to initiation of work. Contractor shall be responsible for ensuring a qualified licensed applicator can apply all herbicides in accordance with all manufacturer recommendations and all Federal, State and/or local laws and regulations.
3.3. Order and Coordination. Cincinnati Landing
3.4. Work Period. Date of Award - June 30, 2024.
3.5. Cabin Subdivision Cincinnati Landing. Cincinnati Subdivision is in Pike County, IL in Mississippi River Pool 24 and near Boundary Group 41IL. (Fig. 2) This subdivision has 37 lots that are currently leased and designated to be surveyed. Lots are not adjacent, and each will require a marker on all 4 corners of the lots (original survey 1958). Subdivision can be accessed via Hwy 96 and 245th Avenue. RPO will provide Surveyor Plat Maps to assist contractor in surveying and boundary demarcation.
Figure 9. Cincinnati Landing subdivision is located within Pike County, IL. It has 37 cabin lots to be surveyed and posted. Site can be accessed via Hwy 96 and 245th Avenue.
4.0. Ground Maintenance: RMBS
4.1 Location: The Riverlands Migratory Bird Sanctuary (RMBS) is in West Alton, MO. It is accessible by Route 67 and Riverlands Way.
4.2. General Scope:
The primary focus of this project is ground maintenance to control invasive species, maintain boundary line a fire breaks, and improve native habitat. Maintenance will include herbicide spraying for invasive species control, mowing, and the use of a seed drill. Maintenance will take place at the Riverlands Migratory Bird Sanctuary in St. Charles County, MO.
The Contractor shall perform all work in accordance with this Statement of Work and the base Contract.
Contractor shall coordinate with Rivers Project Office and do a site walk of the areas to be treated and worked through this Statement of Work, prior to initiation of work. Contractor shall be responsible for ensuring a qualified licensed applicator can apply all herbicides in accordance with all manufacturer recommendations and all Federal, State and/or local laws and regulations.
4.3. Order and Coordination. Government shall coordinate exact timing
4.4. Work Period and Activity
A) Mowing Boundary and Fire Breaks 10-12ft wide as low as mower will go. Area encompasses 34 acres.
Time: July 1-15, 2023, and Sept 15-30 2023
Figure 10. This map outlines the mowing and fire breaks for the RMBS.
R-3
July 1-15 2023; Sept 15-30 2023
B) In this area, contractors will conduct herbicide application on 35 acres of bullrush with aquatic labeled Glyphosate provided by Government.
Time: July 15-30 2023
Figure 10. A total of 35 acres of bullrush will be sprayed with an aquatic labeled glyphosate.
R-11
July 15-30 2023
C) This area will have wood shredded in July 1-15 as site prep for MoBCI grant area (10 acres). It will then be treated with 2% Glyphosate (BURN DOWN) provided by Gov't July 15-30. It will be mowed during Sept 15-30. After complete site prep, this area will be seed drilled with a native species mix Nov 1-15. Seed provided by Gov’t.
Time: Date of Award – November 15 2023
Figure 11. This area of ground maintenance around the Audubon Center at Riverlands will include wood shredding, herbicide application, mowing, and seed drilling.
D) This area covers all acreage of the Riverlands Migratory Bird Sanctuary. This area will be spot treated for any sericea or johnson grass. Herbicides provided by government. Shall be 1 oz./acre mixture Outrider Tank mix, Outrider and Triclopyr 3 to treat both species at same time. It will also be spot treated for coffeeweed using 2,4,D.
Time: July 01-July 30, 2023
MB -1
July 01 2023-Nov 15 2023
Figure 12. Ground maintenance will include spot treatment of sericea and Johnson grass around the RMBS.
5.0. Ground Maintenance: Timber Ridge
5.1 Location: Timber Ridge Natural Area
5.2. General Scope:
The primary focus of this section is to spray herbicide for the control of Japanese honeysuckle at Timber Ridge Natural Area in Godfrey, IL. Government will specify what herbicide is to be used and what timing maintenance activities will take place.
The Contractor shall perform all work in accordance with this Statement of Work and the base Contract.
Contractor shall coordinate with Rivers Project Office and do a site walk of the areas to be treated and worked through this Statement of Work, prior to initiation of work. Contractor shall be responsible for ensuring a qualified licensed applicator can apply all herbicides in accordance with all manufacturer recommendations and all Federal, State and/or local laws and regulations.
5.3. Order and Coordination. Government shall coordinate exact timing
5.4. Work Period and Activity
A) In this area, contractors will spot-treat Japanese Honeysuckle with 2% Glyphosate. Care should be taken to avoid spraying until after the native vegetation has stopped photosynthesizing.
Time: November 1-30, 2023
July 01 – July 30, 2023
Figure 13. Ground maintenance at Timber Ridge will include spot treatment of Japanese honeysuckle with 2% Glyphosate.
T-2
November 1-30 2023
6.0. 2023 Forestry Project: Dardenne Island TSI and Interplanting
6.1. Location:
Dardenne Island Mississippi River Pool 26 near St. Charles, MO
6.2. General Scope:
Dardenne Island stand 16 is an old reforestation site planted around 2002. This stand is 44 acres in total.
This site shall have undesirable trees reduced by 35% along with all woody vines. See Figure 14 and Table 1. Undesirable trees include boxelder, mulberry, green ash, American elm, and silver maple. Trees under 4” will be felled and stumps will be treated with a 50% Glyphosate mixture. Trees over 4” will be double girdled and left standing, and the girdle cut shall be treated with a 50% Glyphosate mixture. All hard and soft mast trees will be retained. Following TSI, the contractor shall plant 1,550 3-gallon containerized trees into the site. Trees shall be provided by the government and will be delivered to the Riverside Landing St. Charles County Park boat ramp. The contractor will assist the government in unloading of the trees as they are delivered to the site. Planted trees should be distributed evenly throughout the site. Bamboo stakes shall be placed through the root ball and into the soil to help stabilize each tree. Trees to be planted at this site include Burr Oak, Swamp White Oak, Overcup Oak, Pin Oak, Pecan, Nuttall Oak, Shellbark Hickory, and Persimmon. Contractor will be provided a shapefile or KMZ of the stand location.
Dardenne Island stand 25 is approximately 80.5 acres. This site shall receive a crop tree release along with TSI and planting 3-gallon container trees. This site shall have undesirable trees reduced by 35% along with all woody vines. See Figure 14 and Table 1. Undesirable trees include boxelder, mulberry, green ash, American elm, and silver maple. Trees under 4” will be felled and stumps will be treated with a 50% Glyphosate mixture. Trees over 4” will be double girdled and left standing, and the girdle cut shall be treated with a 50% Glyphosate mixture. All hard and soft mast trees will be retained. Following TSI, the contractor shall plant 700 3-gallon containerized trees into the site. Trees shall be provided by the contractor. Planted trees should be distributed evenly throughout the site. Bamboo stakes shall be placed through the root ball and into the soil to help stabilize each tree. Trees to be planted at this site include Burr Oak, Swamp White Oak, Overcup Oak, Pin Oak, Pecan, Nuttall Oak, Shellbark Hickory, and Persimmon. Contractor will be provided a shapefile or KMZ of the stand location.
Table 1. Dardenne Island TSI and Interplanting
Site Species Size QTY Tree/Plant Supplier
Dardenne Island 25 Swamp White Oak 3GL 100 Government
Dardenne Island 25 Pin Oak 3GL 80 Government
Dardenne Island 25 Burr Oak 3GL 80 Government
Dardenne Island 25 Overcup Oak 3GL 100 Government
Dardenne Island 25 Nuttall Oak 3GL 80 Government
Dardenne Island 25 Pecan 3GL 100 Government
Dardenne Island 25 Shellbark Hickory 3GL 80 Government
Dardenne Island 25 Persimmon 3GL 80 Government
Dardenne Island 16 Swamp White Oak 3GL 210 Government
Dardenne Island 16 Pin Oak 3GL 210 Government
Dardenne Island 16 Burr Oak 3GL 210 Government
Dardenne Island 16 Overcup Oak 3GL 210 Government
Dardenne Island 16 Nuttall Oak 3GL 100 Government
Dardenne Island 16 Pecan 3GL 210 Government
Dardenne Island 16 Shellbark Hickory 3GL 300 Government
Dardenne Island 16 Persimmon 3GL 100 Government
6.3 Order and Coordination:
Government shall coordinate exact timing of TSI and Tree Planting.
6.4 Description of work:
• The contractor shall furnish all equipment, labor, materials, and supplies to complete TSI and tree planting for areas specified in Figure 14.
• Government shall supply all tree and plant materials for stand 16 and have them delivered to the Riverside Landing St. Charles County Park boat ramp.
• Contractor shall supply all tree and plant materials for stand 25. Government suggests having them delivered to the Riverside Landing St. Charles County Park boat ramp.
• The contractor will supply bamboo stakes according to the base contract.
• Government shall delineate the stands for the contractor by providing a shapefile or KMZ.
• This site requires marine transport for all personnel, trees, materials, equipment, and supplies.
6.5 Work Period: October 1, 2023-December 31, 2023
Figure 14: Dardenne Island Stand 16 and Stand 25 timber stand improvement and interplanting.
7.0. 2023 Forestry Project: Gilbert Island TSI and Interplanting
7.1 Location: Gilbert Island Mississippi River pool 24 near Ashburn, MO
7.2 General Scope:
TSI and hard mast interplanting – Gilbert Island stand 7 is approximately 86 total acres with about 27 acres of that being suitable elevation for hard mast trees. See Figure 15 and Table 2. The contractor shall conduct timber stand improvement to reduce undesirable trees and woody vines in this stand.
Undesirable trees include mulberry, boxelder, silver maple, green ash, and American elm. Trees under 4” will be felled and stumps will be treated with a 50% Glyphosate mixture. Trees over 4” will be girdled and left standing, and the girdle cut shall be treated with a 50% Glyphosate mixture. All hard and soft mast trees will be retained. Existing canopy gaps will be cleared, and new canopy gaps will be created.
Newly created gaps shall be no more than 1/3 of an acre in size and will be located on high elevation sites. Following TSI, the contractor shall plant 570 3 gallon containerized trees within the cleared/created canopy gaps. Trees shall be provided by the government and will be delivered to the Dupont Reservation Conservation Area MDC boat ramp. The contractor will assist the government in unloading of the trees as they are delivered to the site. Bamboo stakes shall be placed through the root ball and into the soil to help stabilize each tree. Trees to be planted at this site include Burr Oak, Swamp White Oak, Overcup Oak, Pin Oak, Pecan, Nuttall Oak, Shellbark Hickory, Persimmon, and Hackberry.
Contractor will be provided a shapefile or KMZ of the stand location.
Gilbert Island stand 8 is approximately 53 acres total with about 30 acres with suitable elevation for hard mast trees. See Figure 15 and Table 2. The contractor shall conduct timber stand improvement to reduce undesirable trees and woody vines in this stand. Undesirable trees include boxelder, mulberry, green ash, silver maple, and American elm. Trees under 4” will be felled and stumps will be treated with a 50% Glyphosate mixture. Trees over 4” will be girdled and left standing, and the girdle cut shall be treated with a 50% Glyphosate mixture. All hard and soft mast trees will be retained. Existing canopy gaps will be cleared, and new canopy gaps will be created. Newly created gaps shall be no more than 1/3 of an acre in size and will be located on high elevation sites. Following TSI, the contractor shall plant 450 3 gallon containerized trees within the cleared/created canopy gaps. Trees shall be provided by the government and will be delivered to the Dupont Reservation Conservation Area MDC boat ramp. The contractor will assist the government in unloading of the trees as they are delivered to the site. Bamboo stakes shall be placed through the root ball and into the soil to help stabilize each tree. Trees to be planted at this site include Burr Oak, Swamp White Oak, Overcup Oak, Pin Oak, Pecan, Nuttall Oak, Shellbark Hickory, Persimmon, and Hackberry. Contractor will be provided a shapefile or KMZ of the stand location.
TSI and Early Successional interplanting – Gilbert Island stand 25 is approximately 42 acres and was at one point an agricultural field. The contractor shall conduct timber stand improvement to reduce undesirable trees and woody vines in this stand. See Figure 15 and Table 2. Undesirable trees include mulberry, silver maple, green ash, boxelder, and American elm. Trees under 4” will be felled and stumps will be treated with a 50% Glyphosate mixture. Trees over 4” will be girdled and left standing, and the girdle cut shall be treated with a 50% Glyphosate mixture. All hard and soft mast trees will be retained.
Undesirable trees and woody vines shall be reduced by approximately 50%. Following TSI, the contractor shall plant 1,020 3 gallon containerized trees within the cleared/created canopy gaps. Trees shall be provided by the government and will be delivered to the Dupont Reservation Conservation Area MDC boat ramp. The contractor will assist the government in unloading of the trees as they are delivered to the site. Bamboo stakes shall be placed through the root ball and into the soil to help stabilize each tree.
Trees to be planted at this site include Cottonwood and Sycamore. Contractor will be provided a shapefile or KMZ of the stand location.
Wet Prairie planting – The contractor will plant 1,300 wet prairie plants in 3 acres of stand 16. See Figure 15 and Table 2. Plants shall be provided by the government and delivered to the Dupont Reservation Conservation Area MDC boat ramp. The contractor will assist the government in unloading of the trees as they are delivered to the site. Site prep for this task includes utility mowing to knock down existing vegetation and facilitate planting. Species to be planted include prairie cordgrass, gray’s sedge, swamp milkweed, cardinal flower, and marsh mallow. Contractor will be provided a shapefile or KMZ of the stand location.
Table 2. Gilbert Island TSI and Interplanting
Gilbert Island 7 Swamp White Oak 3GL 65 Government
Gilbert Island 7 Pin Oak 3GL 65 Government
Gilbert Island 7 Burr Oak 3GL 65 Government
Gilbert Island 7 Overcup Oak 3GL 65 Government
Gilbert Island 7 Pecan 3GL 65 Government
Gilbert Island 7 Shellbark Hickory 3GL 65 Government
Gilbert Island 7 Persimmon 3GL 55 Government
Gilbert Island 7 Hackberry 3GL 115 Government
Gilbert Island 8 Swamp White Oak 3GL 55 Government
Gilbert Island 8 Pin Oak 3GL 55 Government
Gilbert Island 8 Burr Oak 3GL 55 Government
Gilbert Island 8 Overcup Oak 3GL 55 Government
Gilbert Island 8 Pecan 3GL 55 Government
Gilbert Island 8 Shellbark Hickory 3GL 55 Government
Gilbert Island 8 Persimmon 3GL 45 Government
Gilbert Island 8 Hackberry 3GL 85 Government
Gilbert Island 25 Cottonwood 3GL 510 Government
Gilbert Island 25 Sycamore 3GL 510 Government
Gilbert Island 16 Prairie Cordgrass 1GL 400 Government
Gilbert Island 16 Swamp Milkweed 1GL 400 Government
Gilbert Island 16 Grays Sedge 1GL 150 Government
Gilbert Island 16 Cardinal Flower 1GL 150 Government
Gilbert Island 16 Marsh Mallow 1GL 200 Government
7.3 Order and Coordination
Government shall coordinate exact timing of TSI and Tree Planting.
7.4 Description of Work:
• The contractor shall furnish all equipment, labor, materials, and supplies to complete TSI and tree planting for areas specified in Figure 15.
• Government shall supply all tree and plant materials and have them delivered to the Dupont Reservation Conservation Area MDC boat ramp.
• The contractor will supply bamboo stakes according to the base contract.
• Government shall delineate the stands for the contractor by providing a shapefile or KMZ.
• This site requires marine transport for all personnel, trees, materials, equipment, and supplies.
7.5 Work Period: October 1, 2023-December 31, 2023
Figure 15: Gilbert Island Stand 7 and 8 timber stand improvement and hard mast interplanting, stand 16 wet prairie planting, and Stand 25 timber stand improvement and early successional planting.
8. TSI and supplemental planting Unit 5
8.1 Location: Clarence Cannon NWR, Annada, MO
8.2 General Scope:
The contractor shall conduct TSI throughout unit 5 of the restoration plan (Fig. 17). The goal of this task is to reduce the amount of Maple, Ash, and Elm community in this unit and promote hard mast forest.
Some oaks and pecans are already present within this stand. Those trees shall be released by cutting all other trees within 20’ of any occurring hard mast trees. Trees will also be cut to allow for the planting of additional hard mast trees. Trees under 6” will be felled and all trees over 6” shall be double girdled and left standing. A total of 1400 trees (37 trees per acre) will be planted throughout this stand. Trees to be planted will be supplied by the Government. Species to be planted include Swamp White Oak, Pin Oak, Burr Oak, Overcup Oak, Nuttall Oak, Pecan, Shellbark Hickory, Persimmon, Hackberry, Green Hawthorn, and False Indigo Bush. Tree planting to begin following 01OCT. There are two periods of no work days, 06OCT-08OCT and 19OCT-22OCT due to deer hunts being conducted on site.
8.3 Order and Coordination: Government shall coordinate exact timing of work to be done.
8.4 Description of Work:
• The contractor shall furnish all equipment, labor, materials, and supplies to complete TSI and tree planting. Government shall supply trees to be planted.
8.5 Work Period: September 1, 2023 – December 31, 2023
9. Tree planting units 16, 17, 18
9.1 Location: Clarence Cannon NWR, Annada, MO
9.2 General Scope:
The contractor shall plant bare root swamp shrub seedlings in units 16, 17, and 18. Shrubs shall be planted on 10’ x 10’ spacing in the wetland areas outlined in Fig 18. Species to be planted include Buttonbush and Swamp Privet.
9.3 Order and Coordination: Government shall coordinate exact timing of work to be done.
9.4 Description of Work:
• The contractor shall furnish all equipment, labor, materials, and supplies to complete tree planting. Government shall supply trees to be planted.
9.5 Work Period: March 1, 2023 – June 15, 2023
10. Mow and disk units 8, 9, 10, 11, 14
10.1 Location: Clarence Cannon NWR, Annada, MO
10.2 General Scope:
The contractor shall mow units 8, 9, 10, 11, and 14 (Fig 19). Following mowing, these units shall be disked two times. Total area to be mowed and disked is 136 acres. The goal of this task is to allow natural regeneration of light seeded species. Disking shall be conducted 01MAY – 31JULY.
10.3 Order and Coordination: Government shall coordinate exact timing of work to be done.
10.4 Description of Work:
• The contractor shall furnish all equipment, labor, materials, and supplies to complete mowing and disking.
10.5 Work Period: May 1, 2023 – July 31, 2023
11. Build mounds/berms unit 7
11.1 Location: Clarence Cannon NWR, Annada, MO
11.2 General Scope:
Tree planting berms shall be installed in unit 7 (Fig 20). Total area in unit 7 is 83 acres. Site prep for unit 7 includes mowing prior to berm construction. Berms shall be 70’ long x 1’ tall with a 20’ space between linear berms. Berms shall be spaced 20’ apart. See diagram Fig 21. Material to be used for the berms will be located on site. After construction of the berms has been completed, a cover crop of Virginia wild rye, partridge pea, and Illinois bundleflower shall be drill seeded across unit 7. Seed to be used shall be supplied by the Government. Virginia wild rye shall be drill seeded at a rate of 12 lbs/ac, partridge pea shall be drill seeded at a rate of 3 lbs/ac, and Illinois bundleflower shall be drill seeded at a rate of 3 lbs/ac. Seed shall be drilled to a depth of ¼” to ½”. Drill seeding shall be conducted 01OCT-31OCT. There are two periods of no work days, 06OCT-08OCT and 19OCT-22OCT due to deer hunts being conducted on site.
11.3 Order and Coordination: Government shall coordinate exact timing of work to be done.
11.4 Description of Work:
• The contractor shall furnish all equipment, labor, materials, and supplies to complete berm installation and seed drill planting. Government shall supply seed to be planted.
11.5 Work Period: September 1, 2023 – December 31, 2023.
Appendix 1
Figure 16: Clarence Cannon Afforestation Overview
Figure 17: Unit 5 - TSI and interplanting hard mast
Figure 18: Unit 16, 17, 18 - swamp shrub bare root planting
Figure 19: Unit 8, 9, 10, 11, 14 - Mowing and 2x disking for light seed tree regeneration
Figure 20: Unit 7 berm installation and drill seeding
Figure 21: Berm layout and spacing