This is a Statement of Work (SOW) for fuel tank integrity testing at USCG Base Cape Cod in Bourne, Massachusetts, with work to be completed over a four-year period. The Contractor must provide all personnel, equipment, tools, materials, supervision, and services necessary to perform external inspections of aboveground fuel tanks and potassium sodium tanks in accordance with Steel Tank Institute (STI) SP001 standards and API 653 specifications. Internal inspections and wall thickness measurements are required for three specific tanks: one 30,000-gallon JP-8 tank and two 15,000-gallon JP-8 tanks located adjacent to Taxiway Delta. The inspection schedule specifies Year 1 for the 30,000-gallon tank, Year 2 for the two 15,000-gallon tanks, Year 3 for two 10,000-gallon tanks adjacent to the Mini Mart, and Year 4 for the 5,000-gallon tanks and two 5,000-gallon potassium sodium tanks.
Deliverables include completion of STI SP001 AST records for each inspected tank, a detailed report documenting tank condition, observed deterioration, test results, and predictions of remaining service life, and cost estimates for required repairs. All work must be completed within 45 calendar days of the Notice to Proceed. The Contractor is responsible for safety compliance with OSHA regulations and Federal codes, environmental protection including spill prevention, proper disposal of hazardous materials and waste with documentation, and development of a Safety Plan using USACE EM 385 framework and an Environmental Protection Plan with storm water provisions. On-site supervision is required, and all personnel must pass NCIC background checks for base access. Standard working hours are 7:00 A.M. to 4:00 P.M., Monday through Friday, excluding Federal Holidays.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DEI CLAUSE FOR SOLICITATIONS.docx | DOCX document | |
| SF1449-21 SOLICITATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
Tank Integrity Testing
BASE CAPE COD
11June2026
SECTION 01010
GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 SCOPE: The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform external inspections of aboveground fuel tanks, and potassium sodium tanks. Internal inspections and tank wall thickness measurements shall be included in inspection for three (3) tanks – one (1) 30,000 gallon JP-8 tank, and two (2) 15,000 gallon JP-8 tanks located adjacent to taxiway delta. Contractor shall provide a detailed report of conditions found to include estimates for repairs. All work located at USCG Base Cape Cod in Bourne, MA 02542.
1.1.2 REQUIRED WORK: This list should not be considered complete. It represents the general items needed to complete the contract requirements. Base Cape Cod manages six (6) above ground tanks that are greater than or equal to 6,000 gallons, that are used for the storage of fuel products. Three (3) above ground tanks, used for the storage of gasoline, are located adjacent to Coast Guard Base Cape Cod’s (BCC) Mini Mart. Two (2) of the tanks adjacent to BCC’s Mini-Mart have a 10,000 gallon capacity the third tank has a 6,000 gallon capacity. Three (3) above ground tanks, used to store JP-8 (aviation fuel), are located adjacent to Taxiway Delta behind building 3170. Two (2) of the tanks adjacent to Taxiway Delta have a 15,000 gallon capacity, the third tank has 30,000 gallon capacity. Base Cape Cod also manages two 5,000 gallon potassium sodium tanks located behind building 124.
1. Inspect the tanks in accordance with Steel Tank Institute (STI) SP001 and complete the STI SP001 AST record.
2. Perform wall thickness testing, and internal inspection IAW API 653. Wall thickness testing, and internal inspection to only be completed on 30,000-gallon tank, and two (2) 15,000-gallon tanks located adjacent to taxiway delta.
3. Drafting a report on the condition of the tanks including any observed deterioration, the results of tests, and predictions of the expected service life remaining.
1.1.3 TANK INSPECTION SCHEDULE: Work shall be completed over a four (4) year period.
1. Year 1; Inspect 30,000 gallon tank adjacent to taxiway delta
2. Year 2, Inspect two (2) 15,000 gallon tanks adjacent to taxiway delta
3. Year 3, Inspect two (2) 10,000 gallon tank adjacent to CGEX
4. Year 4, Inspect 5,000 gallon tank adjunct to CGEX & (2) 5,000 gallon Potassium Sodium Tanks
1.2 SITE VISITS: Bidders are strongly recommended to inspect the site where work is to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award. Arrangements for such visits shall be made by contacting the COR, Steven Simpson, at Steven.M.Simpson@uscg.mil, any questions regarding this specification or the work shall be addressed in writing and directed to the Contracting Officer.
1.3 LOCATION: Work will be performed on Joint Base Cape Cod, Buzzards Bay, MA 02542.
1.4 HOURS OF WORK: Normal working hours for the contract are 7:00 A.M. to 4:00 P.M., Monday through Friday (excluding Federal Holidays). If the Contractor desires to work other than normal duty hours, on weekends or federal holidays, he/she must request written permission from the Contracting Officer at least 36 hours in advance of such work and approval must be received prior to the requested work time. The Contractor shall coordinate the work schedule and all work with the COR. The Contractor shall not make any attempt to access any work areas without prior arrangements with the COR.
1.5 PRECONSTRUCTION CONFERENCE: Upon award of the contract and prior to starting the project, the Contractor shall attend a pre-construction conference with the Contracting Officer to ensure a complete understanding of the project. The Contractor shall pay for all expenses incurred by him in this regard. All questions shall be resolved and confirmed in writing if required.
1.6 SECURITY REQUIREMENTS: All Contractor personnel scheduled to work on JBCC shall be subject to a National Crime Information Center (NCIC) background check to gain access through the Base security gates. To process the NCIC background check, all Contractors shall provide the following information: name, citizenship, drivers’ license state and number, and date of birth. The NCIC form shall be filled out by the Contractor, listing all personnel that require access to JBCC; form shall be submitted to the COR for processing at least 7 calendar days prior to the date of access.
1.6.1 Contractor’s vehicles shall have a valid and current proof of insurance and vehicle registration. The drivers shall have a valid license, and all passengers shall have a positive photo ID. All Contractor vehicles must enter the Base through the main gate on the Bourne side of the Base property.
1.7 REMOVAL OF CONTRACTOR EMPLOYEES: All employees of the Contractor in the performance of this contract, or any representative of the Contractor entering the worksite, shall abide by all applicable regulations and shall submit to security checks as may be deemed necessary. The Government reserves the right to direct the Contractor to remove from the performance under this contract, any employee, for misconduct or security reasons. This shall not relieve or constitute an excuse from the contract performance. Upon dismissal the employee shall render all identification for entry to the worksite.
1.8 SCHEDULE OF WORK: After receiving the notice to proceed, the Contractor shall submit a Schedule of Work on the Government furnished form or other form approved by the Contracting Officer. The Contractor shall not commence work under this contract without receiving a copy of the signed, approved schedule.
1.9 LABOR & DAILY LOGS: All personnel shall be skilled and have sufficient knowledge and experience necessary to perform work assigned to them. The Contractor shall complete the Base Cape Cod daily log form at the end of each working day and deliver weekly to the COR. The Government will attest to its accuracy by initialing the form and providing a copy back to the Contractor.
1.10 SAFETY: The Contractor shall take all necessary precautions to meet proper safety standards and regulations of the State and Federal Codes. OSHA regulations apply to all work performed on site. In addition, the Contractor shall conform to any restrictions as may be outlined by the Base Safety Officer and Fire Department during the contract. Prior to doing any welding or burning with a torch the Contractor shall obtain a “hot work” permit from the USCG FED Safety Office. Contractor Safety Plan shall be written using USACE EM 385 1-1 Accident Prevention Plan 13-part framework.
1.10.1 FIRE SAFETY: All requirements per Joint Base Cape Cod Fire Prevention Standard 911-1 shall be followed. A copy of the instruction will be provided.
1.11 ON SITE SUPERVISION: The Contractor always provide qualified supervision when work is being conducted by Contractor employees or Sub-Contractor employees. Prior to commencing work, the Contractor shall submit a letter to the Contracting Officer designating an employee from his/her company as the foreman or supervisor. The supervisor shall be on site any time work is being performed. The supervisor shall be able to read, write, speak English, and have the authority to approve and accept delivery orders and minor (under $2000.00) modifications to delivery orders.
1.12 PROTECTION OF PROPERTY: The Contractor shall comply with the requirements of Paragraph 52.236-9 and 52.236-10 of the Federal Acquisition Regulation and the following: All existing grounds, fences, utilities, equipment, building components and adjacent property, including vehicles, shall be protected from any damage resulting from contract operations. Contractors will be responsible for any damage to Government property. Damaged property (done by the Contractor) shall be repaired by the Contractor, at Contractor’s expense, to meet previous existing conditions.
1.13 ENVIRONMENTAL PROTECTION. The Contractor shall comply with all Federal, State, and Local environmental protection regulations. Contractor shall develop and submit an Environmental Protection Plan prior to initiating operations/inspections. Environmental Protection Plan shall include a Storm Water Protection Plan. EPP shall include location of and materials within spill kits, spill response checklist, and notification requirements.
1.14 HAZARDOUS MATERIAL: The Contractor shall be solely responsible for all Contractor generated or owned hazardous materials. While performing work Specific herein, if potentially hazardous materials are utilized a SD will be submitted to the COR prior to its use. If the hazardous materials are encountered, the Contractor shall notify the COR immediately. The Contractor’s responsibility for handling hazardous material is incidental to work performed, i.e., the Contractor shall handle, remove, and properly dispose of only those hazardous materials necessary to complete the contract work.
1.14.1 Any commercial adhesives, sealants, adhesive primers, sealant primers, and associated surface preparation and cleanup solvents in containers greater than a net volume of 16 fluid ounces, or a net weight of one pound shall not exceed volatile organic compounds (VOC) limits as established in the Massachusetts Department of Environmental Protection promulgated Adhesives and Sealants regulations, 310 CMR 7.18(30)."
1.15 DISPOSAL OF REMOVED MATERIALS: Dumpsters placed on site require a permit. Permits are obtained from the USCG FED Safety Office. All material removed by the Contractor that is not indicated to be salvaged by the Government shall become the property of the Contractor. This material shall be disposed of legally off Joint Base Cape Cod property. The Contractor shall not cause, suffer, or permit the handling, transportation, or storage of any material in a manner which results, or may result in emissions that cause or contribute to a condition of air pollution, any debris which could create air-borne dust must be shipped in a closed container or wet down and securely tarped over. The Contractor is responsible to comply with all applicable federal, state, and local environmental and disposal regulations. The Contractor shall submit to the COR the following:
1.15.1 Bill of landing for all disposed materials.
1.15.2 Copy of landfill receipts.
1.15.3 Recyclers operating permit.
1.16 SUBMITTAL DESCRIPTION: Samples, catalog cuts, shop drawings, and other information shall be submitted by the Contractor as required by the list of submittals on the Submittal Register Form(s) which is included in this specification. No other forms shall be used or will be accepted by the COR. The contactor shall submit the following deliverables in accordance with the table below.
| Submittal |
| Frequency |
| Submittal Schedule |
Contact information for the designated on-site supervisor
With Quote
Certificate of Insurance
With Quote
Base Access Request Form
Within 5 days of contract award date
| Safety Data Sheet (SDS) and product label for chemicals and materials |
| As needed |
| Prior to use |
Safety Plan
15 calendar days after award
Environmental Protection Plan
15 calendar days after award
Solid Waste Disposal Bill of Lading & Landfill Receipts
Project Close Out
Hazardous Waste Profiles and Shipping Manifests
Prior to shipment of waste.
STI SP001 AST (record) (for each tank inspected)
Project Close Out
Detailed report of tank condition and list of required repairs
Project Close Out
Estimates for required repairs
Project Close Out
API 653 Tank wall thickness report
Project Close Out
1.16.1 The Contractor shall submit a list of all hazardous materials with Safety Data Sheets (SDS) to the COR for approval prior to work commencement on this project. Storage of hazardous materials will not be permitted on Joint Base Cape Cod property.
1.16.2 All materials used by the Contractor shall comply with VOC Emission limits for use in the Commonwealth of Massachusetts (310 CMR 7.00). Cleaning and maintenance of the Contractor's and Sub-Contractor's equipment shall not be conducted on Joint Base Cape Cod property.
1.16.3 The Contractor shall ensure that adequate protective measures are taken to minimize personnel exposure to harmful substances. If protective measures are required, the Contractor shall include them in a Safety Plan and they shall be reviewed by the Contracting Officer prior to the start of any contract work involving use of the harmful substance.
1.16 RESTORATION AND CLEAN-UP: All areas disturbed by construction shall be restored to match the condition and material that existed prior to the start of work. The Contractor shall always keep the work areas clean of trash and debris. The Contractor shall not allow trash or debris to blow from the work area.
1.18 GOVERNMENT INSPECTION: The Contractor shall keep the COR informed of contract operations and plans so that they may arrange to be present at the various times that work is being performed.
1.19 PERFORMANCE PERIOD: All work under this contract including site cleanup, punch list, acceptance by the COR and required submittals shall be completed within (45) calendar days of issuance of the Notice to Proceed (NTP) by the Contracting Officer unless stated otherwise.
1.20 WARRANTY: The provisions of the entire warranty clause from paragraph 52.246-21 (April 84) and Federal Acquisition Regulation are incorporated into this contract. The clause is written, in part, as follows:
“In addition to any other warranties set out elsewhere in this contract, the Contractor shall warrant that work performed under this contract conforms to the contract requirements and is free of any defect of equipment, material, or design furnished or workmanship performed by the Contractor or any of his Sub-Contractors or suppliers at any tier. Such warranty shall continue for a period of one year from the date of final acceptance of the work.”
END OF GENERAL SECTION