Tab 4. Civil Bill of Materials.xlsx
XLSX spreadsheet 19 KB Posted
- Solicitation number
- FA489726QC026
About this file
This is a Civil Bill of Materials estimate for construction of a Shower, Shave, and Latrine (SSL) facility at Mountain Home Air Force Base. The document outlines required materials and quantities with anticipated delivery dates, primarily scheduled between April 15 and June 26, 2026. Key materials include 250 tons of 3/4" minus road mix, 250 cubic yards of 3,500 PSI concrete, 80 tons of utility sand, 210 tons of #4 angular rock, geotextile and geogrid products (2 rolls of Mirafi and 5 rolls of Miragrid), and 5 days of pump truck services with operators. The estimate identifies Idaho Materials and Construction and White Cap TenCate as suggested vendors for most materials.
The document includes a detailed concrete pour schedule spanning from May 8 through June 26, 2026, with six planned pours ranging from 22 to 55 cubic yards per pour, totaling 250 cubic yards. Pump truck services are marked as required for pours scheduled May 13, May 27, June 8, and June 12. This solicitation is a 100% small business set-aside issued by the 366th Contracting Squadron with quotes due by March 17, 2026, and questions to be submitted by March 11, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tab 3. HVAC Bill of Materials.xlsx | XLSX spreadsheet | |
| Tab 5. Structural Bill of Materials.xlsx | XLSX spreadsheet | |
| Tab 2. Plumbing Bill of Materials.xlsx | XLSX spreadsheet | |
| Tab 6. Electrical Bill of Materials.xlsx | XLSX spreadsheet | |
| Combo.pdf | ||
| Tab 1. PWS.pdf | ||
| Provisions and Clauses.pdf | ||
| Brand Name or Equal Justification.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| CIVIL MATERIAL ESTIMATE | ||||||||||
| ITEM NO. | SUGGESTED VENDOR | |||||||||
| (BRAND NAME OR EQUIVALENT) | DESCRIPTION | Required NLT | U/I | EST. QUANTITY | ||||||
| 1 | Idaho Materials and Construction | 3/4" Minus Road Mix | 15-Apr-26 | Ton | 250 | |||||
| 2 | Idaho Materials and Construction | Concrete: 3,500 PSI compressive strength @28 days, 5 in slump, 3/4" aggregate | VARIES | CY | 250 | |||||
| 3 | Idaho Materials and Construction | Utility Sand | 15-Apr-26 | Ton | 80 | |||||
| 4 | Idaho Materials and Construction | #4 Rock (1"-3") Angular | 15-Apr-26 | Ton | 210 | |||||
| 5 | White Cap | Tencate Mirafi 15'X300' 4500SQFT 180NC ROLL MIRAFI MFG#:180NC15300 | 15-Apr-26 | EA | 2 | |||||
| 6 | White Cap | TenCate Miragrid 3XT 12' x 150' Geogrid 1800 ft Squared/Roll | 15-Apr-26 | EA | 5 | |||||
| 7 | Pump Truck w. Operator | VARIES | Days | 5 | Anticipated Concrete Pour Dates (Will Call) | |||||
| 8 | NO DATE | Date | U/I | Quantity | PUMP TRUCK | |||||
| 9 | NO DATE | 8-May | CY | 22 | NO | |||||
| 10 | NO DATE | 13-May | CY | 30 | YES | |||||
| 11 | NO DATE | 27-May | CY | 55 | YES | |||||
| 12 | NO DATE | 8-Jun | CY | 30 | YES | |||||
| 13 | NO DATE | 12-Jun | CY | 29 | YES | |||||
| 14 | NO DATE | 17-Jun | CY | 29 | YES | |||||
| 15 | NO DATE | 26-Jun | CY | 55 | NO | |||||
| 16 | NO DATE | |||||||||
| 17 | NO DATE | |||||||||
| 18 | NO DATE | |||||||||
| 18 | NO DATE | |||||||||
| 19 | NO DATE |