Tab 4-DDCT_Bldg15_Upgrade.pptx

PPTX presentation 5 MB Posted

Attached to
Fence Project-DLA Distribution Corpus Christi, TX Federal contract opportunity
Solicitation number
SP3300-25-Q-0110
Issued by
Defense Logistics Agency Distribution

About this file

This PowerPoint presentation details a security upgrade project for Building 15 at DLA Distribution Corpus Christi. The project involves installing three new security fences, one fire exit gate, and one interior speed door to enhance physical security and meet regulatory standards. Specific requirements include 9-gauge wire mesh fencing with galvanized steel fabric, twisted selvage, and optional 45-degree outrigger arms with barbed wire, a fire exit door complying with UFC and OSHA standards, and a speed door meeting AIE and FAR requirements.

The project's intent is to improve facility security, control access points, support surveillance, and deter potential intrusions while fulfilling physical security guidance and life safety regulations. The scope includes removing existing materials, installing new infrastructure, and ensuring compliance with specific technical specifications for fencing, gates, and doors. The work is associated with Solicitation Number SP3300-25-Q-0110, targeting full and open competition under NAICS code 332618, with the Defense Logistics Agency Distribution as the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Fence Project-DLA Distribution Corpus Christi, TX, newest first.
File Type Posted
Tab 9-Wage Determination.pdf PDF
Tab 4-SOW.pdf PDF
Tab 11 - CSS SP330025Q0110.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fence x 3 , Exit Gate x 1, and Speed Door x 1 Install Bldg. 15

MT WOOD, DDCT SECURITY OFFICER

OCTOBER 17, 2024

DLA Distribution Corpus Christi The Nations Primmer Distribution Center Enabling warfighter readiness and lethality Intent:

The physical security barrier provided by a security fence provides one or more of the following functions:

• Gives notice of legal boundary of the outermost limits of the protected area.

• Assists in controlling and screening authorized entries into secured/protected areas by channeling vehicles and personnel to access control points.

• Supports surveillance, detection, assessment, and other security functions by providing a platform for installing intrusion detection equipment.

• Deters casual intruders from penetrating a secured/protected area by presenting a barrier that requires an overt action to enter.

• Causes a delay to obtain access to an installation/facility, thereby increasing the probability of detection.

DDCT Intent:

The desire of DDCT Security Office is to obtain the most with as little cost to DLA. With this the Security Mission is to provide the best, most up to date Security for the DLA Mission. The direct intent is to fulfill the regulatory guidance at the same time produce a product that meets or exceeds the standard to reduce the overall cost until guidance and regulations call for replacement to meet mission requirements. With the newly acquired Bldg. 15 it is necessary per. Physical Security Guidance and basic Life Safety rules to have all the requested fulfilled. The below information will allow for all criteria to be met to meet the DLA Mission at DDCT.

Lifeline to the flight line! Warfighter obsession!

Quantity:

Currently Bldg. 15, all fencing will be new fencing meeting the below criteria. It will also consist of the removal and disposal of all materials removed or not utilized.

Bldg. 15: (Install 3 New Fences to enclose the specific areas for Security of materials) Fencing fabric must be minimum 9-gage wire mesh and mesh openings must be not be greater than 2-inches (51 mm) per side. Fence fabric material will be galvanized steel, PVC coated steel fabric (use PVC coated if located in corrosive environment or where aesthetics are of prime importance), or aluminum coated steel fabric (use aluminum coated if located in corrosive environment). See Corrosion Prevention Control for additional information regarding material selection.

The fencing fabric must be extended to within 2 inches (51 mm) of firm ground and anchored, if required by service requirements, using horizontal bottom rails, tension wires, concrete curbs, sills, sheet piling, piping, or other inexpensive materials. For additional security burying the fabric 12 inches (305 mm) may also be considered; however, corrosion of the buried fabric must be monitored.

Twisted selvage must be provided on the top of the fence fabric to deter climbing. Twisted selvage must be provided at the bottom of the fence fabric to deter borrowing unless the fence has a bottom rail, is buried, or encased in concrete. In these applications the selvage may be knuckled.

When required, install outriggers (support arms) at 45-degree angles in a single arm (towards the threat side) or “Y”/”V” configuration, constructed of a single or double outrigger consisting of 18-inch (457 mm) arm(s), each having three strands of barbed wire at regular intervals along the top of the fence. The outriggers must provide a minimum of an additional 12 inches (305 mm) to the fence height. The top guard fencing adjoining gates may range from a vertical height of 18 inches (457 mm) to the normal 45-degree outward protection, but for a limited distance along the fence line to adequately open the gates. Outriggers must be permanently affixed to the fence posts with screws or by spot welding. Screws used to affix outriggers to posts must be made tamper-proof either by design, peening, or welding.

Fences requiring barbed wire must use a minimum of 3 strands of barbed wire equally spaced. Additional strands may be added as required. Barbed wire must consist of two 12.5 -gage /0.099-inch (2.5 mm) (+0. 005- inch (.127 mm)) twisted line wires with 15- gage /0.080- inch (2 mm)(+0, 005-inch (.127 mm)) round barbs. Barbed wire must be zinc-coated steel, aluminum coated steel, aluminum alloy, or PVC over zinc-coated steel as specified. All barbs must consist of four points and spacing of barbs must be at 5- inch (127 mm) (+1- inch (25.4 mm)) centers.

Quantity Cont.:

UFC 4- 440-01: Warehouses and Storage Facilities

Bldg. 15 (New):

(Install 1 Fire Exit Gate to meet the below Criteria per. UFC and OSHA Standards)

3-6.7 Doors and Hardware Exterior doors with closers must be Level 4, physical performance Level A doors complying with ANSI/SDI A250.8, Standard Steel Doors and Frames. Frames must match door level. Exterior door frames must be welded type.

Provide Grade 1 hardware typical. Locksets must be mortise type, Series 1000 as defined by ANSI/BHMA - A156.13, Mortise Locks and Latches for shop and maintenance level doors. Hinges for doors with closers must be full mortise butt hinges except where special types are required. Closers must be the best and highest grade available from each manufacturer. Exterior doors must have overhead rain drips and door drips.

Quantity Cont.:

Bldg. 15 (New):

(Install 1 Speed Door on the interior of the existing Roll Up Door to meet AIE Standards) All AIE equipment must meet the DISA requirement per. DoD which states it cannot be a component made from United States FAR Part 25.105 Critical Components:

a) The following is a list of articles that have been determined to be a critical component or critical item and their respective preference factor(s).(1)-(2) [Reserved](b) The list of articles and preference factors in paragraph (a) of this section will be published in the Federal Register for public comment no less frequently than once every 4 years. Unsolicited recommendations for deletions from this list may be submitted at any time and should provide sufficient data and rationale to permit evaluation ( see 1.502).(c) For determining reasonableness of cost for domestic end products that contain critical components or are critical items ( see 25.106(c)).

Note: The FAR can be reviewed at anytime to verify the product meets the requirement for installation and the end user is not requesting any specific product just that it meets the FAR requirements.

Makes, Models, Colors:

FOLLOW UFC 4-022-03 1 OCT 2013 (Fence) FOLLOW UFC 4-440-01 1 APR 2019 (Exit Door) FOLLOW AIE and FAR Part 25.105 ( Speed Door)

DDCT Bldg.15 (Fence Install):

Not to Scale:

Key:

= Fence Install

Approx=20ft run from 3 to 12 ft in height Approx= 15ft run from 3 to 12 ft in height Approx= 10 ft run from 15ft in height NOTE: All Fence must be from floor to ceiling with top guard

DDCT Bldg. 15 Fire Exit Gate (Install) :

Not to scale:

Roll Up Door

= Fire Exit Gate Note: Must meet

UFC 4-440-01

DDCT Bldg. 15 Speed Door (Ventilated Roll Up Door):

Curtain Door: PVC Mesh, Motorized Roll Up, Wall Mount: Example

Not to scale:

Information:

- Power Permit

- Running electric to Speed Door (Bldg. 15)

- Fire Permit

- Bracing

- Top Guard

- Triple Strand Barbed Wire

- Structure for Fire Exit Door *Other things may arise*

Misc. Required Work: