This combined synopsis/solicitation for construction services prepared in accordance with the format in subpart 12.6 of the Federal Acquisition Regulation (FAR) as supplemented with additional information included in this notice. This synopsis/solicitation is being advertised as
Small Business Set-Aside only. This announcement constitutes the only solicitation; no separate written solicitation will be issued.
The solicitation number is 30321PR260000003. Applicable North American Industry
Classification Standard (NAICS) codes are:
237120 - Oil and Gas Pipeline and Related Structures Construction
This requirement is for a fixed price contract. The contract will be awarded using simplified acquisition procedures in accordance with FAR part 13 and part 15
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, Best Value.
When submitting your proposals, request a price breakdown of the following:
a. Cost of materials and equipment
b. Cost of labor
Contract will be awarded to the vendor who can provide Best value which includes all labor, material, cost and equipment required within the SOW. Cost and Past Performance factors will also be considered when selecting the award.
Anticipated award date: 10 business days after close of solicitation, OOA 20 March 2026
Quotes are to be received no later than close of business (3 p.m.) on 10 March 2026 and are to be sent via e-mail to angel.melendez@uscg.mil
Quotations sent via the US Postal Service or hand delivered should be sent to:
Commanding Officer
USCG Base Miami Beach (P&C)
Attn: Angel Melendez
12100 SW 152nd ST
Miami, FL 33177.
Telephone requests of quotes, will not be accepted, a formal notice of changes (if applicable) will be issued in SAM (www.sam.gov).
Wage determinations: FL20240184 01/05/2024 mailto:angel.melendez@uscg.mil http://www.sam.gov/
SCOPE OF WORK:
CONTRACT SPECIFICATIONS
STATION SAND KEY FUEL DISPENSERS
AT
UNITED STATES COAST GUARD
Station Sand Key, Clearwater, FL
PROJECT NUMBER 31562475
February 2026
SUMMARY OF WORK
PART 1 GENERAL
GENERAL DESCRIPTION
General Work Requirements
1. PROJECT OVERVIEW
The Contractor shall provide all labor, supervision, materials, equipment, tools, testing, permits, and incidentals necessary to perform a complete overhaul, rehabilitation, and modernization of the fuel storage and dispensing system at USCG Station Sand Key.
The objective is to restore the fuel system to full operational status in compliance with:
Federal, State of Florida, and Pinellas County regulations
EPA Underground Storage Tank (UST) requirements
FDEP storage tank system regulations
NFPA 30 & NFPA 30A
UFC (Unified Facilities Criteria)
USCG Civil Engineering Unit standards
Shape
2. EXISTING SYSTEM DESCRIPTION
The existing system generally consists of:
Diesel fuel storage tank(s) (UST or AST – verify field conditions)
Fuel transfer pump(s)
Dispensing station(s)
Fuel piping (underground and/or aboveground)
Leak detection system
Tank monitoring and alarm system
Spill containment and overfill prevention
Electrical controls and emergency shutoff
The Contractor shall verify all existing conditions prior to mobilization.
Shape
3. SCOPE OF SERVICES
3.1 Pre-Construction Services
Conduct site investigation and system condition assessment
Perform tank tightness testing (if required)
Provide as-built verification
Develop phased construction plan to minimize operational disruption
Prepare and submit shop drawings and submittals
Obtain required permits and approvals
Shape
3.2 Fuel Tank Work
Contractor shall:
Decommission and remove existing fuel storage tank(s), OR Clean, inspect, and rehabilitate tank (if tank is to remain)
If replacing:
Furnish and install new double-wall UL-listed steel or fiberglass tank
Provide corrosion protection system (if UST)
Install anchoring system (if required by water table conditions)
Install new spill bucket and overfill protection
Shape
3.3 Fuel Piping Replacement
Remove existing underground piping
Install new double-wall fiberglass or coated steel piping
Provide secondary containment
Install flex connectors at tank and dispenser
Pressure test piping per code
Provide tracer wire (if non-metallic piping)
Shape
3.4 Pump & Dispenser Replacement
Remove and replace fuel transfer pumps
Install explosion-proof motors (Class I, Division 1 rated)
Install new fuel dispensers with:
Metering system
Hose reels (if required)
Automatic shutoff nozzles
Calibrate meters to weights and measures standards
Shape
3.5 Electrical & Controls
Replace or upgrade control panels
Install new emergency shutoff switches
Install new fuel management system (if required)
Upgrade conduit and wiring to NEC compliance
Install grounding and bonding system
Integrate leak detection monitoring
3.6 Environmental & Compliance
Provide soil sampling if excavation required
Properly dispose of contaminated materials
Provide certified tank cleaning
Maintain spill prevention measures
Provide SPCC compliance updates
Submit closure documentation (if tank removal occurs)
Shape
3.7 Concrete & Site Restoration
Demolish and replace damaged concrete pads
Install new equipment pads
Restore pavement and striping
Restore landscaping as required
Shape
3.8 Testing & Commissioning
Contractor shall perform:
Hydrostatic tank testing
Piping pressure testing
Leak detection system testing
Electrical system testing
Dispenser calibration
Full operational functional testing
Provide written test reports.
4. DELIVERABLES
Contractor shall provide:
Shop drawings
Product data submittals
As-built drawings (hard copy & digital)
O&M manuals
Warranty documentation (minimum 1-year workmanship, 10-year tank warranty typical)
Training for USCG personnel
Shape
5. PHASING & OPERATIONS
Maintain station fueling capability throughout project OR
Provide temporary fuel supply solution
Coordinate shutdowns with Commanding Officer
Restrict work to approved hours
Maintain site security per USCG requirements
Shape
6. SAFETY REQUIREMENTS
Contractor shall:
Submit Site-Specific Safety Plan
Comply with OSHA 29 CFR 1910 & 1926
Provide confined space procedures (if tank entry required)
Implement Hot Work Permits
Maintain fire watch during welding
Follow USCG base access requirements
7. QUALITY CONTROL
Contractor shall implement a Quality Control Plan
Provide qualified fuel system technicians
Use licensed storage tank contractor (State of Florida certified)
Maintain daily quality control reports
Shape
8. WARRANTY
Minimum 1-year labor warranty
Manufacturer tank warranty (10–30 years depending on system)
Pump and dispenser warranty per manufacturer
Shape
9. ESTIMATED PROJECT DURATION
Design & Submittals: 30–60 days
Procurement: 45–90 days
Construction: 60–120 days
Testing & Commissioning: 1–2 weeks
Total Estimated Duration: 4–8 months (depending on scope and environmental findings)
Shape
10. OPTIONAL ADD ALTERNATES
Fuel polishing system
Generator backup power
Automated fuel tracking system
Additional storage capacity
Secondary containment canopy
Cathodic protection monitoring system
END OF SCOPE OF WORK
Site visit: It is highly recommended and encouraged that interested party’s contact Mr. James Pinto for a site visit which will be held on Friday Febuary 27, 2026 at 09:00AM EST. For scheduling contact Mr. Pinto via email James.E.Pinto@uscg.mil Or via phone at (727) 596-8666 X 105.
Performance Period: Performance of work is expected to commence NLT 10 days after award is made.
Extension period must be approved by the Contracting Officer for any unforeseen delays.
**All Questions and Answers will not be accepted after 04 Mar 2026 at 10:00AM
EST. APPLICABLE FAR CLAUSES
FAR 52.213-4: 52.213-4 Terms and Conditions-Simplified
Acquisitions (Other
Than Commercial Items).
ATTACHED BY REFERENCE
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS
52.236-2 DIFFERING SITE CONDITIONS (APRIL 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS
AFFECTING THE WORK (APRIL 1984)
52.236-27 SITE VISIT (CONSTRUCTION) {FEB 1995)
Work hours: Monday through Friday, 0730 – 1800 (7:30 am – 6 pm) No weekends or Holidays authorized.
See attached applicable FAR Clauses by reference.
Offerors may obtain full text version of these clauses electronically at:
www.arnet.gov/far
The following Homeland Security Acquisition Regulations (HSAR) are incorporated as addenda to this solicitation: HSAR 3052.209-70 Prohibition on
Contracts with Corporate Expatriates (Jun 2006); Contracting Officers Technical
Representative (Dec 2003) (COTR) HSAR 3052.237-72. Copies of HSAR clauses may be obtained electronically at http://www.dhs.gov.
http://www.arnet.gov/far http://www.dhs.gov/
Vendors providing an offer must be registered in SAM (System for Award Management) prior to close of this solicitation. https://www.sam.gov/portal/public/SAM/. The vendors
SAM registration must be in an “ACTIVE” status prior to award.
Location of Work: 1375 Gulf Blvd.
Clearwater FL, 33767 POC: Zachery Little Zachery.T.Little@uscg.mil
(206) 820-4819
James Pinto James.E.Pinto@uscg.mil
(727) 596-8666 X 105
File details come from the government source that posted it. Updated .