This document is a Stormwater Pollution Prevention Plan (SWPPP) Information form supplied by the Ada County Highway District (ACHD) to contractors for the 2026 Arterial and Collector Capital Maintenance project located on Poplar Street between Cole Road and Curtis Road in Boise, Idaho. The project encompasses 6.6 acres of total property with 6.1 acres of anticipated construction disturbance, with a maximum of 6.1 acres disturbed at any one time. The project does not discharge stormwater into a Municipal Separate Storm Sewer System (MS4) and has no surface waters located within 50 feet of construction disturbances. Ground-disturbing stormwater controls planned for the site include new pipes, sand and grease traps, seepage beds, headwalls, and irrigation boxes. The contractor is responsible for preparing the SWPPP Report and Notice of Intent (NOI) using the information provided in this template.

Regarding environmental compliance, the project determined through U.S. Fish and Wildlife Service database (IPaC) accessed on November 18, 2024, that the Yellow-billed Cuckoo (listed as threatened) and Monarch Butterfly (candidate species) may occur in the region; however, the project location is outside the designated critical habitat for the Yellow-billed Cuckoo and no critical habitat exists for the Monarch Butterfly, resulting in no anticipated adverse impacts. The project is not located on Indian country lands or properties of religious or cultural significance to Indian tribes. Historic property surveys have not previously been conducted on the site, and the contractor must determine whether installation of subsurface earth-disturbing stormwater controls will affect historic properties, with notification to the State Historic Preservation Officer (SHPO) or Tribal Historic Preservation Office (THPO) as applicable.

View the file

Other files

File Type Posted
2026_Arterial_and_Collector_Capital_Maintenance.pdf PDF
Special_Provisions.pdf PDF
Sample_Agreement.pdf PDF
Plan_Sheets_1_-_71.pdf PDF
Cross_Sections.pdf PDF
CAD_FILE_-_FOR_VIEWING_PURPOSES_ONLY.dwg DWG drawing
Bid_Bond.pdf PDF
2026_Arterial_&_Collector_Maintenance_(Poplar)_524019__NMID_LA-Recorded.pdf PDF
Utility_Information_Sheet.pdf PDF
Vicinity_Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACHD Supplied SWPPP Information This information is provided to the Contractor to aid in the preparation of the SWPPP Report and NOI.

1. Project/Site Information

i. Project Name: 2026 Arterial and Collector Capital Maintenance Poplar St, Cole Rd to

Curtis Rd

ii. Project Street/Location:

i. From Cole Road and Poplar Street Intersection to Poplar Drive and Curtis Road Intersection in Boise, ID

iii. Project Latitude/Longitude:

Project Street/Location Latitude Longitude Cole Road and Poplar Street Intersection 43.623661 -116.271861 Poplar Drive and Curtis Road Intersection 43.623453 -116.253719

i. Method for determining latitude/longitude:

USGS topographic map (specify scale: ) EPA Web site GPS Other (please specify): Google Earth

iv. Additional Project Information:

i. Is the project/site located on Indian country lands, or located on a property of religious or cultural significance to an Indian tribe? Yes No

ii. If yes, provide the name of the Indian tribe associated with the area of Indian country (including the name of Indian reservation if applicable), or if not in Indian country, provide the name of the Indian tribe associated with the property: N/A

2. Discharge Information

i. Does your project/site discharge stormwater into a Municipal Separate Storm Sewer

System (MS4)? Yes No

ii. Are there any surface waters that are located within 50 feet of your construction disturbances? Yes No

iii. Names of Receiving Waters:

Name(s) of the first surface water that receives stormwater directly from your site and/or from the MS4 (note: multiple rows provided where your site has more than one point of discharge that flows to different surface waters)

1. N/A

Is this surface water listed as “impaired”?

If you answered yes, then answer the following:

What pollutant(s) are causing the impairment?

Has a TMDL been completed?

Title of the

TMDL

document

Pollutant(s) for which there is a

TMDL

1. YES NO N/A YES NO N/A N/A

iv. Describe the method(s) you used to determine whether or not your project/site discharges to an impaired water: IDEQ Website. https://www.deq.idaho.gov/water-quality/surface-water/total-maximum-daily-loads/

v. Are any of the surface waters to which you discharge designated by the state or tribal authority under its anti-degradation policy as a Tier 2 (or Tier 2.5) water (water quality exceeds levels necessary to support propagation of fish, shellfish, and wildlife and recreation in and on the water) or as a Tier 3 water (Outstanding Natural Resource Water)? (See Appendix F). Yes No If yes, name(s) of receiving water(s) and its designation (Tier 2, Tier 2.5 or Tier 3): N/A

3. Nature of the Construction Activity

i. Size of Construction Project: What is the size of the property (in acres), the total area expected to be disturbed by the construction activities (in acres), and the maximum area expected to be disturbed at any one time?

TOTAL AREA OF PROPERTY 6.6 acres.

TOTAL AREA OF CONSTRUCTION DISTURBANCES 6.1 acres.

MAXIMUM AREA TO BE DISTURBED AT ANY ONE TIME 6.1 acres

4. Endangered Species Protection:

i. Eligibility Criterion: ☒A ☐B ☐C ☐D ☐E

ii. Include documentation supporting your determination of eligibility.

Supporting Documentation Provide documentation for the applicable eligibility criterion you select in Appendix D, as follows:

For criterion A, indicate the basis for your determination that no federally-listed threatened or endangered species or their designated critical habitat(s) are likely to occur in your site’s action area (as defined in Appendix A of the permit). Check the applicable source of information you relied upon:

Specific communication with staff of the U.S. Fish & Wildlife Service or National Marine Fisheries Service.

Publicly available species list.

(USFWS) information, Planning and Conservation System (IPaC). The system was accessed, and a report generated on November 18th, 2024. Due to the nature of the project, no adverse impact is anticipated. The following species were presented in the report:

• The Yellow-billed Cuckoo (Coccyzus americanus) is listed as threatened. The Monarch Butterfly (Danaus plexippus) is listed as a candidate.

• There is a final critical habitat for the Yellow-billed Cuckoo, but the project location is outside of these critical habitats. There is no critical habitat for the Monarch Butterfly.

Other source:

For criterion B, provide the Tracking Number from the other operator’s notification of permit authorization: N/A Provide a brief summary of the basis used by the other operator for selecting criterion A, B, C, D, E, or F: N/A

For criterion C, provide the following information:

https://www.deq.idaho.gov/water-quality/surface-water/total-maximum-daily-loads/ https://www.deq.idaho.gov/water-quality/surface-water/total-maximum-daily-loads/

Also, provide a brief summary of the basis used for determining that your site’s discharges and discharge-related activities are not likely to adversely affect listed species or critical habitat: N/A

For criterion D, E, or F, attach copies of any letters or other communication between you and the U.S. Fish & Wildlife Service or National Marine Fisheries Service concluding consultation or coordination activities. N/A

5. Historic Preservation:

Step 1 Do you plan on installing any of the following stormwater controls at your site? Check all that apply below, and proceed to Appendix E, Step 2.

Dike Berm Catch Basin Pond Stormwater Conveyance Channel (e.g., ditch, trench, perimeter drain, swale, etc.)

Culvert Other type of ground-disturbing stormwater control: New pipes, sand & grease traps, seepage beds, headwalls, irrigation boxes.

(Note: If you will not be installing any ground-disturbing stormwater controls, no further documentation is required for Section 3.2 of the Template.)

Step 2 If you answered yes in Step 1, have prior surveys or evaluations conducted on the site already determined that historic properties do not exist, or that prior disturbances at the site have precluded the existence of historic properties? YES NO

If yes, no further documentation is required for Section 3.2 of the Template.

If no, proceed to Appendix E, Step 3.

Step 3 If you answered no in Step 2, have you determined that your installation of subsurface earth-disturbing stormwater controls will have no effect on historic properties?

YES NO

If yes, provide documentation of the basis for your determination.

If no, proceed to Appendix E, Step 4.

Step 4 If you answered no in Step 3, did the State Historic Preservation Officer (SHPO), Tribal Historic Preservation Office (THPO), or other tribal representative (whichever applies) respond to you within 15 calendar days to indicate whether the subsurface earth disturbances caused by the installation of stormwater controls affect historic properties? YES NO

If no, no further documentation is required for Section 3.2 of the Template.

If yes, describe the nature of their response:

Written indication that adverse effects to historic properties from the installation of stormwater controls can be mitigated by agreed upon actions.

No agreement has been reached regarding measures to mitigate effects to historic properties from the installation of stormwater controls.

Other:

File details come from the government source that posted it. Updated .