SV0192-26 Baler Relocation 11-19-25 edit Q-A.pdf
PDF 53 KB Posted
- Attached to
- Baler Relocation
- Solicitation number
- SV0192-26
About this file
This document is a Questions and Answers (Q&A) file for solicitation SV0192-26 regarding a baler relocation project involving two locations: Petersburg and Marianna. The key details include a baler (Bace V73HD model) being moved between sites with specific logistical requirements: no electrical work, ground-level dock access, and strict safety/security protocols requiring the baler to be placed near the rear gate by 3pm and remain in a secured location overnight. The Statement of Work (SOW) was updated to specify that hydraulic fluid will be drained and the cylinder/platen removed prior to transport, with reinstallation at the destination.
The document provides precise dimensional details for passage through doors and gates at both locations: Petersburg has two rollup doors (inner door 119" x 112", outer door 95¾" x 119"), while Marianna has a double-gate (162" x 144") and a rollup door (180" x 144"). No government-furnished equipment is involved, and vendors are directed to consult the manufacturer for precise weight and dimensions. The relocation involves specific handling instructions, including a requirement that the baler be positioned by 3pm and remain stationary until the morning, adhering to institutional safety and security protocols.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Petersburg.JPG | JPG image | |
| Marianna (2).JPG | JPG image | |
| Petersburg (2).JPG | JPG image | |
| Petersburg (3).JPG | JPG image | |
| Marianna (3).JPG | JPG image | |
| Marianna.JPG | JPG image | |
| Baler Pic 6.JPG | JPG image | |
| SV0192-26 Baler Relocation Statement of Work (SOW) 11-19-25 edit.pdf | ||
| SV0192-26 Baler Relocation Statement of Work (SOW).pdf | ||
| SV0192-26 Baler Relocation Solicitation Text.pdf | ||
| Baler Pic 1 - Info Plate.JPG | JPG image | |
| Baler Pic 4.JPG | JPG image | |
| Baler Pic 2.JPG | JPG image | |
| Baler Pic 3.JPG | JPG image |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11/19/2025 Edit
SV0192-26 Baler Relocation
Questions and Answers:
1. There is no electrical work being performed.
2. Both locations of the baler are “ground level” and have dock access.
3. The baler must be placed near the rear gate by 3pm, and it must sit in that secured location until the morning, at which time it may leave the institution. This is a safety and security protocol.
4. The Statement of Work (SOW) was updated to reflect that the hydraulic fluid/oil will be drained and the cylinder/platen will be removed, prior to transport. At the destination, once anchored to the floor, the fluid/oil will be replaced and the cylinder/platen will be reinstalled for the machine to function.
5. There is no government furnished equipment.
6. Please refer to the manufacturer for weight and dimensions. The unit is a Bace
V73HD, as indicated in the picture.
7. Petersburg has 2 rollup doors that must be passed (pictures attached).
Inner door – 119” wide x 112” high Outer door – 95 ¾” wide x 119” high
8. Marianna has a gate and a rollup door that must be passed (pictures attached). (The yellow machine in the picture will be gone when the vendor arrives to place the machine from Petersburg.)
Double-gate – 162” wide x 144” high Rollup – 180” wide x 144” high