This is a Supplemental Scope of Work and Installation Specifications document for the Village of Schaumburg, Illinois, related to the landscape plant material installation contract (2026-IFB-068). The scope of work encompasses the installation of landscape plant materials including shrubs, trees, perennials, ornamental grasses, annuals, bulbs, and ground cover at building sites, roadside beds, and median plantings throughout the Village. The successful bidder will be responsible for all labor, equipment, and materials necessary for proper handling, installation, and post-installation care of Village-furnished plant materials. Installation of shrubs, perennials, and ground cover shall occur between April 1 and November 25 annually, with completion required within one week of Contract Administrator notification. Spring annuals are scheduled for April 1-24, summer annuals for May 10-31, fall annuals for September 7-20, and spring bulbs for November 1-25. Sealed bids must be submitted via the Village's e-Procurement Portal (OpenGov) no later than Friday, December 11, 2026, at 10:00 a.m.
Pricing is structured on a per-unit installation basis as described in the specifications. The Village of Schaumburg shall supply all plant material and make it available for pickup at the Public Works Complex or other designated sites within Village limits. The contractor is responsible for transporting plant materials to installation sites, contacting underground utility locating services (J.U.L.I.E.), and providing all watering equipment including a mobile watering unit for a fourteen-day post-installation period. The contractor must supply soil amendments, potting soil (professional grade), all equipment for bed preparation and installation, and arrange disposal of all debris and old plant material. Water is available at no cost at the Public Works Complex for watering purposes. Work is permitted between 7:00 a.m. and 8:00 p.m., Monday through Friday, with restricted hours of 9:00 a.m. to 2:30 p.m. for high-traffic roadway work. The Director of Engineering & Public Works serves as the Contract Administrator with authority to direct work priorities, cancel work due to hazardous conditions, and adjust planting schedules based on weather conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Landscape_Plant_Material_Installation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work: The successful bidder will be responsible for the installation of landscape plant material for the Village. Types of plant material include shrubs, trees, perennials, ornamental grasses, annuals, bulbs and ground cover. Locations shall include building sites, roadside beds, median plantings (i.e. Schaumburg Road, Higgins Road, and any other designated area in the Village limits).
Cost of installation shall be on a per unit basis as described in the specifications.
Contract Administration: For the purpose of this contract, the term Contract Administrator shall refer to the Director of Engineering & Public Works (hereafter Director) or his authorized representative. The Contract Administrator is responsible for the monitoring and verifying of work completed for payment under this contract. This will include directions as to the priority order in which the work is to be carried out.
The Contract Administrator may direct that the work of the contractor not proceed on any given day, despite work being scheduled by the contractor if, at the sole discretion of the Contract Administrator, the performance of work is obviously hazardous, or will result in damage to Village property due to site conditions. In the event that planned activities are cancelled by the Contract Administrator, the contractor shall re-schedule work when conditions are more favorable.
Contractor's Representatives: The contractor shall provide and have a competent supervisor on the job, at all times, who shall have full authority to act for the contractor, and to receive and execute directives from the Contract Administrator. Any instructions given to such supervisor executing work for the contractor shall be binding on the contractor as though given to the contractor personally. Failure of the supervisor to act on said directives shall be sufficient cause to give notice that the contractor is in default of the contract unless such directives would create potential personal injury or safety hazards. The contractor's supervisor must be proficient in the use and interpretation of the English language.
Work Hours: Work is allowed between the hours of 7:00 a.m. and 8:00 p.m., Monday through Friday. Work on Saturdays, Sundays, and holidays, is prohibited unless specific approval is given in writing by the Contract Administrator, in response to a written request.
Work on high traffic roadways, which causes the contractor to close a lane of traffic in order to facilitate operations, shall only be conducted between the hours of 9:00 am and 2:30 pm, Monday through Friday.
SPECIFICATIONS
The Village's Engineering & Public Works Department shall supply all plant material. It shall be available for pickup at the Public Works Complex or other designated site within Village limits. It shall be the contractor's responsibility to transport plant material from the Public Works Complex to the installation sites.
The contractor shall be responsible for the notification of underground utilities (contacting J.U.L.I.E.). No planting shall begin in an area until all utilities have been located.
The contractor shall thoroughly water all plant material immediately after installation and for a period of fourteen (14) days from the date of installation. Watering shall be scheduled in a consistent manner in order to maintain a healthy growing environment. This shall be determined by weather conditions and under instruction of the Contract Administrator. If plant material is lost due to drought during this time the contractor will be held responsible for the plant replacement.
Contractor must supply all watering equipment and possess a mobile watering unit. Many locations have no water sources available on site. It shall be the sole responsibility of the contractor to get water to those sites. Water is available, at no cost to the contractor, at the Public Works Complex for the sole purpose of watering Village owned flower beds, planters, and pots. Where feasible, the use of Village owned quick-connects or building water sources are available per direction and approval by the Contract Administrator. The contractor must supply the quick-connect attachment.
The contractor shall be notified of areas under irrigation, i.e. medians or planted roadways.
Disposal of all old plant material, pots, flats, and other debris will be the responsibility of the contractor.
PLANT INSTALLATION SCOPE
Plant installation shall include all labor, equipment, and materials necessary to properly install Village-furnished trees, shrubs, perennials, ornamental grasses, bulbs and other designated landscape plant materials. The Village shall be responsible for providing the plant material. The Contractor shall be responsible for all work associated with proper handling and installation. Work shall include, but not be limited to:
1. Proper handling, unloading, and placement of plant materials to prevent damage prior to and during installation.
1. Layout and placement of plant materials in accordance with approved plans or as directed by the Village.
1. Excavation of planting holes to the appropriate width and depth based on the plant material and root ball size.
1. Inspection of root systems and removal of damaged, broken, or circling roots as appropriate.
1. Removal of containers, burlap, twine, and wire baskets, as applicable, in accordance with accepted planting practices.
1. Proper placement of plant material at the appropriate planting depth, ensuring the root flare is exposed and not buried.
1. Backfilling planting holes with suitable soil and properly firming soil around the root ball to eliminate significant air pockets.
1. Proper positioning and stabilization of plant material to ensure trees and shrubs remain upright.
1. Topping off existing landscape beds and planters with suitable planting soil or approved soil amendments as necessary to achieve the appropriate grade and provide adequate growing conditions for the installed plant material.
1. Re-Application of mulch around installed plant material, maintaining appropriate clearance around trunks and stems.
1. Initial watering of all installed plant material.
1. Regular watering the 2 weeks following installation to ensure plant vitality.
1. Site cleanup and removal of excess soil, packaging, and other debris generated during installation.
BED PREPARATION SCOPE
Bed preparation shall include all labor, equipment, and materials necessary to prepare new or existing landscape beds for planting or ongoing maintenance. Work shall include, but not be limited to, the following:
1. Removal and disposal of existing shrubs, unwanted vegetation, and associated root systems.
1. Removal of overgrown, dead, or unwanted perennial plants.
1. Tilling, loosening, and preparation of existing soil, including the incorporation of soil amendments as needed.
1. Establishment of new landscape beds and expansion or reconfiguration of existing beds.
1. Installation or re-establishment of defined bed edges.
1. Application of mulch, where specified or deemed necessary.
1. Repair and restoration of turf areas disturbed during bed preparation.
The Contractor shall remove and properly dispose of all debris generated during the work and leave the site in a clean and presentable condition.
INSTALLATION OF SHRUBS, PERENNIALS, GROUND COVER
Tree, shrub, perennial, and groundcover installations shall take place between April 1 and November 25 of each year. Upon notification for installation by the Contract Administrator, the contractor shall complete the installation in a timely manner, one (1) weeks after notification.
The contractor shall:
1. Completely remove all debris and any existing plant material (dead or alive) present. This includes removal above and below ground structures.
1. Remove excess mulch in planting area prior to planting.
1. Properly prepare the hole or bed. This includes the addition of an organic soil amendment (i.e. peat moss, mushroom compost) as directed by the Contract Administrator.
1. Install plant material per appropriate horticultural practices as directed by the Contract Administrator.
1. The contractor shall be responsible to remove all planting debris, leaving the plantings and surrounding area in a clean fresh appearance.
Below is an estimate of plant material to be installed: Numbers will vary year to year due to specific village needs.
INSTALLATION OF ANNUALS
The Contract Administrator shall supply the contractor with a list of locations and detailed plans for each bed, planter and pot.
Planting schedule shall be as follows: (Note: Should weather conditions warrant, the Contract Administrator may adjust planting dates.)
| SPRING ANNUALS (i.e. pansies) |
| April 1 – April 24 |
| SUMMER ANNUALS (i.e. salvia) |
| May 10 – May 31 |
| FALL ANNUALS (i.e. mums) |
| September 7 – September 20 |
| SPRING BULBS (i.e. tulips) |
| November 1- November 25 |
BED PREPARATION, INSTALLATION, AND MAINTENANCE
1. Complete removal of all debris or any existing plant material (dead or alive) present. This includes any existing annuals or tulips, both above and below ground structures.
1. Cultivate bed with a roto-tiller to a minimum depth of 6" with the addition of a 2" layer of a soil amenity per direction of the Contract Administrator. Soil amenities shall include mushroom compost, peat moss or composted leaves, which shall be provided by the contractor.
1. Annuals shall be installed per direction of the Contract Administrator regarding spacing (i.e. 6" – 15" staggered, depending on plant material).
1. Contractor must dispose of all debris (pots, etc.); clean all walk ways and turf areas adjacent to planting beds.
1. After installation of each site, the contractor shall notify the Contract Administrator in writing of the type, number, and size of plant material installed in each bed planter or pot.
1. Any plant material not used must be returned to the Public Works Complex, or designated location.
PLANTERS AND POTS SPECIFICATIONS
1. Cultivate soil, level soil to 1" from top of planter or pot. Should additional soil be needed, contractor must supply. Potting soil must be professional grade (i.e. Sunshine brand) per approval of Contract Administrator.
1. All other planting practices per bed installation shall be followed.
FALL BULB PLANTING
The contractor shall be provided with bulbs which shall be available at the Public Works Complex. Plans for each bed in all locations shall be provided by the Contract Administrator.
These areas will include all annual beds, perennial beds and road medians.
The planting schedule shall be as follows: (Note: Should weather conditions warrant, the Contract Administrator may adjust planting date.)
Based on each bulb installed:
The contractor shall:
1. Remove all debris and any leftover plant material in the bed.
1. Cultivate and level soil to be free of soil clumps.
1. Install bulbs per requested spacing using recommended horticultural practices.
1. Level soil, edge bed, and clean off all walkways and turf areas adjacent to beds prior to leaving site.
1. Any bulbs not used shall be returned to the Public Works Complex unless otherwise instructed by the Contract Administrator.