This is a Supplemental Bid Schedule for Solicitation No. W912DQ26BA010 for the FY 26 OD Roadwork Project. The document presents eight Contract Line Items (CLINs) with detailed supplemental bid items for roadwork services at various locations including Tuttle Creek Lake and Smithville Lake facilities.
CLIN 0001 covers crack fill and chip seal work at Tuttle Creek Lake Administration Building Parking Lot with three supplemental bid items (SB 1-3) totaling quantities in linear feet and square yards. CLIN 0002 addresses crack fill and chip seal at Tuttle Creek Lake Outlet Park Road with four items (SB 4-7). CLINs 0003-0008 are focused on Smithville Lake projects, including loop road reconstruction (CLIN 0003), crack filling and surface sealant work on Litton Way (CLIN 0004), surface sealant and striping of the Administration Parking Lot (CLIN 0005), surface sealant and striping of Smith's Fork Road (CLIN 0006), surface sealant and striping of Smith's Fork Parking Lot (CLIN 0007), and surface sealant work at MO HWY DD Parking Lot (CLIN 0008). Quantities are specified in linear feet (LF), square yards (SYD), or each (EA). The schedule includes columns for unit price and extended price, which bidders must complete. The document notes that work not specifically listed should be priced using the most closely related supplemental item. All CLINs except CLIN 0001 are marked as optional. The procuring activity is the U.S. Army Corps of Engineers (W912DQ prefix indicates Omaha District).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN/
Supp. Bid Qty Unit
Unit
Price Extended
SB 1 4,000 LF
SB 2 3,744 SYD
SB 3 444 SYD
(OPTION)
SB 4 6,000 LF
SB 5 100 SYD
SB 6 15,900 SYD
SB 7 107 EA
(OPTION)
CLIN 0003 - Smithville Lake, Loop Road Reconstruction
SB 8 2966 SYD
SB 9 2966 SYD
(OPTION)
SB 10 125,000 LF
SB 11 33,800 SYD
SB 12 1 EA
SB 13 31 EA
(OPTION)
SB 14 4,500 SYD
SB 15 1 EA
SB 16 32 EA
(OPTION)
SB 17 11,300 SYD
SB 18 1 EA
(OPTION)
SB 19 4,440 SYD
SB 20 1 EA
SB 21 80 EA
CLIN 0003 Total:
CLIN 0004 Total:
CLIN 0005 Total:
CLIN 0006 Total:
CLIN 0006 - Smithville Lake, Surface Sealant and Striping of Smith's Fork Road
Surface Sealant
Striping of Smith's Fork Road
CLIN 0005 - Smithville Lake, Surface Sealant and Striping of Adminstration Parking Lot
Surface Sealant
Striping of Administration Building Parking Lot
Removal and Reinstallation of Parking Curbs
Removal and Reinstallation of Parking Curbs
Full Depth Reclamation of Existing Pavement
HMA Pavement (4 - inch)
CLIN 0004 - Smithville Lake, Crack Filling, Surface Sealant, and Striping of Litton Way
Crack Fill
Surface Sealant
Striping of Litton Way and Litton Way Parking Lot
FY 26 OD Roadwork Project
Type of Work
Supplemental Bid Schedule for Solicitation No. W912DQ26BA010
CLIN 0002 - Tuttle Creek Lake, Crack Fill and Chip Seal of Outlet Park Road and Parking Areas
Chip and Seal "Surface Patch" (KDOT CM-K)
Crack Fill
Chip and Seal (KDOT CM-K)
CLIN 0002 Total:
Removal and Reinstallation of Parking Curbs
6" Pavement Patching
CLIN 0001 - Tuttle Creek Lake, Crack Fill and Chip Seal of Administration Building Parking Lot
Crack Fill
Chip and Seal (KDOT-K)
CLIN 0001 Total:
Removal and Reinstallation of Parking Curbs
CLIN 0007 - Smithville Lake, Surface Sealant and Striping of Smith's Fork Parking Lot
Surface Sealant
Striping of Smith's Fork Parking Lot
CLIN 0007 Total:
(OPTION)
SB 22 1,700 SYD
SB 23 1 EA
SB 24 59 EA
Note: Any work not specifically noted should be priced with the most closely related supllemental item.
Surface Sealant
Removal and Reinstallation of Parking Curbs
Total for all CLINS:
CLIN 0008 Total:
CLIN 0008 - Smithville Lake, Surface Sealant of MO HWY DD Parking Lot
Striping of MO HWY DD Parking Lot
File details come from the government source that posted it. Updated .