This pre-solicitation notice is for a firm fixed-price construction contract to reconstruct an approximately 2,800 foot long access road on behalf of the Otoe-Missouria Tribe of Oklahoma. The Bureau of Indian Affairs will award the contract to provide grading, drainage, paving and construction of drainage structures for Propane Road in Red Rock, Oklahoma. The project magnitude is between $500,000 to $1,000,000. The solicitation will be set aside exclusively for Indian Economic Enterprises as defined by the Buy Indian Act. Bids are due on January 6, 2023 and the award is anticipated to be made by February 15, 2023. The selected contractor must complete all work within 120 days of notice to proceed and will be subject to Oklahoma construction wage rates, bonding requirements and other standard contract clauses.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT TITLE: OTOE-MISSOURIA TRIBE OF OKLAHOMA, PROPANE TANK ACCESS ROAD PROJECT PRE-SOLICITATON NOTICE: As required by FAR 36.213-2; this is a Pre-Solicitation Notice. The Actual Solicitation will be posted after December 1, 2022; where all documents can be found on sam.gov under Contracting Opportunities, Solicitation Number 140A0323B0001.

CONTRACT TYPE: The Government contemplates award of firm fixed-price contract resulting from this solicitation.

SOCIOECONOMIC PROGRAMS: This procurement is being set-aside exclusively for Indian Economic Enterprises (IEE) as defined under the Buy Indian Regulations 48 CFR PART 1480. Only those vendors that are registered in sam.gov as a Native owned business under the stated NAICS Code can submit a bid. All bidders will need to be registered and active at the time bids are due. Those not registered will be eliminated and determined as non-responsive. Potential contractors will be required to complete the IEE Certification Form and submit it with their bid.

BACKGROUND:

The Bureau of Indian Affairs has a requirement to build Propane Road on behalf of the Otoe-Missouria Tribe The existing road is a dirt road, 2,806 feet in length, that is impassable much of the year due to erosion and muddy conditions and needs to be reconstructed to provide safe and convenient access to the Otoe-Missouria Tribal Complex from the west.

The Tribe does not have the ability to contract this project under P.L. 93-638, Subpart J, therefore the Bureau of Indian Affairs is soliciting this work to be done on behalf of the Tribe. The Tribe does have a TERO Ordinance that will apply.

DESCRIPTION: Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the grading, drainage, paving and construction of the drainage structures at Propane Road as defined in the Contract documents.

PROJECT LOCATION: The work to be performed under this contract will be performed at the project site located in Red Rock, Oklahoma, Noble County. Propane Road is located about 0.3 miles southwest of the Otoe-Missouria Tribal Complex at 8151 US-177, Red Rock, OK 74651.

MAGNITUDE OF PROJECT: As required under FAR Part 36.204, Project Magnitude is between $500,000 - $1,000,000.

NAICS CODE: For informational purposes, the North American Industry Classification Code (NAICS) is 237310 - Highway, Street, and Bridge Construction with a size standard of $39.5mil.

SITE VISIT: A formal site visit will be scheduled, with details outlined in the Solicitation under Section L.

BONDING: FAR Clause 52.228-15, Performance and Payment Bonds-Construction, will apply, along with FAR Clause 52.228-1 Bid Guarantee.

CONSTRUCTION WAGE RATES: Contractor will also comply with the Construction Wage Rates for Noble County, Oklahoma, OK20220021 dated February 24, 2022.

PERMITS: Applicable Permits, archeological and environmental clearances have been acquired.

DATES: Bid Opening is set for January 6, 2023, at 2:00 pm CT. The Government anticipates the award to be made by February 15, 2023. Notice to Proceed will be issued once bonding and insurance is provided, with 120 days to complete all work after Notice to Proceed (NTP) is issued.