Submittal Register (Attachment 2).xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Pike Island and Allegheny Hydraulic Cylinders
- Solicitation number
- W911WN24R0002
About this file
This document is a Submittal Register that outlines the submittal requirements for the procurement of Gate Operating Hydraulic Cylinders for the Pike Island L/D and Allegheny River 2 L/D projects.
The key details include:
- The contractor must submit various documents for review and approval, including qualifications of welding inspectors and welders, schematic drawings, red-line revisions of shop drawings, welding procedure specifications, operations and maintenance data, project schedule, product data, and test reports.
- The required submittals are classified as either Preconstruction Submittals, Shop Drawings, or Closeout Submittals, with the Government designated as the approving authority.
- The related federal contract opportunity is for the procurement of the Gate Operating Hydraulic Cylinders, with a solicitation number of W911WN-24-R-0902. The requirement is being issued as a Request for Proposal (RFP) by the Department of the Army Corps of Engineers, Engineering District Pittsburgh.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
| SUBMITTAL REGISTER | TITLE AND LOCATION Pike Island L/D & Allegheny River 2 L/D - Gate Operating Hydraulic Cylinders Purchase | ||||||||||||||
| CONTRACTOR | CONTRACT NUMBER | ||||||||||||||
| ACTIVITY | |||||||||||||||
| No. | TRANS- MITTAL | ||||||||||||||
| No. | ITEM | ||||||||||||||
| No. | SPEC PARAGRAPH | ||||||||||||||
| No. | DESCRIPTION OF SUBMITTAL | TYPE OF SUBMITTAL | CLASSI- FICATION | CONTRACTOR REVIEWER | CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | GOVERNMENT ACTION | ||||||||
| RO or DO | SUBMIT NEEDED BY | APPROVAL NEEDED BY | MATERIAL NEEDED BY | CODE | CORPS RECEIVED DATE | CODE | CORPS RETURNED DATE | ||||||||
| 1. GENERAL | |||||||||||||||
| 1 | 1.6 | Qualifications of Welding Inspectors | PRECON SUBMTL | G RO | |||||||||||
| 2 | 1.6 | Qualifications of Welders and Welding Operators | PRECON SUBMTL | G RO | |||||||||||
| 3 | 1.6 | Schematic and Drawings | SHOP DRAWINGS | G DO | |||||||||||
| 4 | 1.6 | Red-Line Revisions of Shop Drawings | CLOSEOUT SUBMTL | G DO | |||||||||||
| 5 | 1.6 | Thermal Stress Relief | PRECON SUBMTL | G DO | |||||||||||
| 6 | 1.6 | Welding Procedure Specifications | SHOP DRAWINGS | G DO | |||||||||||
| 7 | 1.9 | Operations and Maintenance | OPERATION AND MAINTENANCE DATA | G DO | |||||||||||
| 8 | 1.13 | Project Schedule | PRECON SUBMTL | G RO |
| 2. PRODUCTS | |||||
| 1 | 2.1 | Materials and Mechanical Equipment | PRODUCT DATA | G DO | |
| 2 | 2.1 | Materials | TEST REPORTS | G DO | |
| 3 | 2.1.2 | Welds | TEST REPORTS | G DO | |
| 4 | 2.2 | Shop Assembly and Testing | PRODUCT DATA | G DO | |
| 5 | 2.2 | Shop Tests | TEST REPORTS | G DO |
RANGE : OUTSTANDING OVERDUE REGISTER : MAIN REGISTER SORT : SECTION & ITEM