About this file

This is a Subcontractor Summary worksheet instruction document issued by the City of St. Petersburg, Florida, for use in response to a solicitation for Police Department Ballistic Door Installation. The worksheet requires prime contractors to disclose all intended subcontractors and certify whether subcontractors will be used on the project. For this shelter-related project, up to 80 percent of the contract work may be subcontracted. The document requires bidders to provide complete legal names, primary business addresses, contact information for project supervisors, trade classifications, and subcontract amounts for each intended subcontractor. Subcontractors are classified as either first or second tier, with restrictions limiting multiple-tier subcontracting unless otherwise specified in contract documents.

Once a prime contractor is awarded the project and the pre-construction meeting is held, subcontractors may not be changed or substituted except under specific circumstances including failure to execute a contract, lack of appropriate licensing, bankruptcy or insolvency, ineligibility to perform work, failure or refusal to perform the subcontract, substantially unsatisfactory work performance, or substantial delays to project progress. Small Business Enterprise (SBE) or Minority Women Business Enterprise (MWBE) subcontractors used to meet SBE percentage requirements must be replaced with SBE subcontractors if removed, unless the prime contractor demonstrates SBE requirements are met through alternative means. Requests for subcontractor changes must be submitted in writing to the Procurement & Supply Management Contracts Compliance Manager. The worksheet must be completed and submitted with the bid as a mandatory requirement.

View the file

Other files

File Type Posted
Police_Department_Ballistic_Door_Installation.pdf PDF
Ballistic_Door_Plans.pdf PDF
Proposed_Area.jpg JPG image
Agreement.pdf PDF
Quote_Addendum.docx DOCX document
Subcontractor_Summary_Spreadsheet.xlsx XLSX spreadsheet
Performance_&_Payment_Bond_.DOCX DOCX document
Subcontractor_Utilization_Plan.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

City of St. Petersburg
Subcontractor Summary Instructions

WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID

1. The Subcontractor Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules.

2. Enter the name of your company in the Prime Contractor field.

3. Enter the name and date of Prime Contractor employee completing this form.

4. Provide all information requested on each intended subcontractor. If subcontractors will NOT be used for this project, provide a written statement on the Subcontractor List indicating the same.

5. Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:

A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;

B. Subcontractor is not appropriately licensed to perform the scope of work;

C. Subcontractor becomes bankrupt or insolvent;

D. Subcontractor is ineligible to perform the work on the project;

E. Subcontractor fails or refuses to perform its subcontract;

F. Engineer determines the work performed by the subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;

G. Subcontractor is substantially delaying or disrupting the progress of the work.

Requests for changes to the Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at Stephanie.Swinson@stpete.org.

6. SBE subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.

7. Restrictions on subcontracting percentage and use of multiple-tier subcontractors do not apply to FDOT LAP or federally funded projects.

Subcontractor Worksheet

City of St. Petersburg
Subcontractor Summary
Project Name:
Project Number:
Percentage of Contract Which May be Subcontracted: 80% for Shelter Bid
Name of Prime Contractor:Cells below will be "hidden" on the worksheet since they are only for Procurement's use.
Name/Date of Individual Completing this Form:
City of St. Petersburg SBE or MWBE Contractor Yes or NoSubcontractor's Name (Provide complete Legal Name)Subcontractor's Primary Business AddressName/Phone Number and Email Address of Subcontractor's Employee Responsible for Project SupervisionFirst or Second Tier Subcontractor*Trade Classification(s) Being Subcontracted (List One Trade per Line)Subcontract Amount ($)Added (A) Deleted (D)Reason CodeCity Approver/DateAdd (A) and Delete (D) Legend
Example: YesXYZ Contractors, Inc.123 N. Burlington Ave., St. Petersburg, FL 33701Joe Jones - 727-555-555 Email - XYXCon@yahoo.comFirstElectrical13,234.00DBEmployee XYZ/03-01-19A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subcontractor is not appropriately licensed to perform the scope of work;
C. Subcontractor becomes bankrupt or insolvent;
D. Subcontractor is ineligible to perform the work on the project;
E. Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications;

G. Subcontractor is substantially delaying or disrupting the progress of the work.

Total: 0.00

*Only first and second tier subcontractors are permitted unless noted otherwise in the Contract Documents.Contract Amount
0.00Amount Allowed to be Subcontracted

&8Rev. January 2020 &10Page 1 of &P