About this file
This is a Subcontractor Selection Plan excerpt from a Construction Manager at Risk (CMAR) contract for the City of Phoenix related to the Phoenix Sky Harbor Operations and Police Facility project. The plan establishes the framework for how the Contractor will select major subcontractors and suppliers, with qualifications submissions due by 12:00 pm on Friday, September 25, 2026, via the City's Procurement Portal. The Contractor is responsible for developing and submitting a comprehensive selection plan to the City for approval that identifies which trades will be selected based on qualifications alone and which will be selected through a combination of qualifications and competitive bidding. The plan must also identify any subcontractors not selected through a formalized qualifications-based process.
The selection process allows for qualification-based selection of subcontractors and suppliers when the Contractor can demonstrate it is in the project's best interest, with such selections encouraged during the design phase to maximize early subcontractor involvement before the Guaranteed Maximum Price (GMP) proposal submission. During the construction services phase, major subcontractors and suppliers must be competitively bid unless they were previously selected by qualifications alone. The Contractor retains sole responsibility for the performance of all selected subcontractors and suppliers and must receive City approval for all selections. Subcontractors must not be selected based on price alone, and the Contractor must negotiate costs with each selected subcontractor and supplier regardless of the selection method used.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT A
CITY OF PHOENIX SUBCONTRACTOR SELECTION PLAN
(EXCERPT FROM CMAR CONTRACT)
MAJOR SUBCONTRACTOR AND MAJOR SUPPLIER SELECTIONS
The selection of major Subcontractors and Suppliers may occur before Construction Services. Major Subcontractors and Suppliers may be selected based on qualifications alone or a combination of qualifications and price. Subcontractors must not be selected based on price alone. The selection of major Subcontractors and Suppliers is the Contractor’s responsibility. In any case, the Contractor is solely responsible for the performance of all selected Subcontractors and Suppliers.
The Contractor must prepare a Subcontractor and Supplier selection plan and submit the plan to the City for approval. This selection plan must identify trades that may be selected by qualifications only and trades that to be selected by qualifications and competitive bid. This plan must also identify all Subcontractors that are not selected through a formalized qualifications-based selection process. The Subcontractor and Supplier selection plan must be consistent with the selection requirements included in this Contract.
Selection by qualifications only - the City may approve the selection of a Subcontractor(s) or Suppliers(s) based only on their qualifications when the Contractor can demonstrate it is in the best interest of the Project.
Qualification-based selection of a Subcontractor(s) or Supplier(s) should only occur during the design phase to achieve maximum benefit of Subcontractor’s involvement before submittal of a GMP Proposal.
The Contractor must follow the approved Subcontractor selection plan when evaluating qualifications of Subcontractor(s) or Supplier(s), and the Contractor must provide the City with its review and recommendation.
The Contractor must receive City approval of the selected Subcontractor(s) and Supplier(s).
The Contractor must negotiate costs for services/supplies from each Subcontractor and Supplier selected under this method.
Selection by qualifications and competitive bid - the Contractor must follow the Subcontractor selection plan when evaluating qualifications of a Subcontractor or Supplier, and the Contractor must provide the City with its process to prequalify prospective Subcontractors and Suppliers. During Construction Services, all Work for major Subcontractors and Suppliers must then be competitively bid unless a Subcontractor or Supplier was selected by qualifications only.