Statement of Work- USCGC Campbell.docx
DOCX document 17 KB Posted
- Attached to
- Planning & Execution Design Workshop for USCGC Campbell Federal contract opportunity
- Solicitation number
- 70Z04026Q60431Y00
About this file
This is a Statement of Work (SOW) for a planning and execution design workshop supporting the U.S. Coast Guard Yard's USCGC Campbell (WMEC-909) availability project. The contractor is tasked with developing a realistic and executable plan to deliver the availability within a non-negotiable 10.5-month timeline using the Focus & Finish methodology, an approach currently deployed by NAVSEA at Norfolk Naval Shipyard for accelerated availability delivery. The effort will account for major constraints including preparatory work readiness, supply chain challenges, technical and commercial change order approvals, and resource contention within and outside the shipyard.
The planning and execution design effort will be completed over two to three consecutive weeks and will include establishing ambitious target timelines, confirming project breakdown into workstreams and execution buckets, analyzing work content and dependencies, determining workstream staggering requirements, challenging bucket durations to fit target timelines, identifying and mitigating constraints and risks, designing execution management processes, and mapping the technical plan to the Focus & Finish approach. The Coast Guard intends to award this work as a sole source contract to Realization Technologies, Inc., based on their unique expertise and prior successful deployment of the Focus & Finish methodology across NAVSEA, NAVAIR, USAF, USMC, commercial airlines, and other project environments.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| JOTFOC - 2126406Y6166A48002.pdf | ||
| FAR Clauses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Planning and Execution Design for USCGC Campbell (WMEC-909) Availability
1. Background A 10.5-month delivery is a non-negotiable requirement for the USCGC Campbell availability. To meet this requirement, the shipyard must develop an executable plan that accounts for the major constraints and uncertainties that can affect completion.
These include constraints in preparatory work, supply chain readiness, technical and commercial approval of change orders during execution, and contention for resources shared with other efforts both inside and outside the shipyard.
Traditional planning and execution approaches often rely on detailed schedules to manage constraints, then change priorities as delays and changes occur during execution. This creates significant waiting time in both the schedule and execution, while also causing constant churn in priorities.
The Campbell availability therefore requires a different planning and execution approach: one that minimizes waiting time and priority churn while protecting the 10.5-month delivery requirement.
2. Purpose The purpose of this Planning and Execution Design workshop is to support the U.S. Coast Guard Yard in developing a realistic and executable plan for USCGC Campbell, along with the execution enablers and risk mitigations required to protect the 10.5-month delivery requirement.
This effort will be based on the Focus & Finish approach. Focus & Finish is currently being deployed by NAVSEA at Norfolk Naval Shipyard against a similar backdrop: the need to deliver availabilities faster and on time. Realization initially developed this approach for aircraft MRO in NAVAIR, and later deployed it in the USAF, USMC, commercial airlines, and other project environments.
3. Plan of Action The planning and execution design effort will be completed over two to three consecutive weeks.
The effort will include the following steps:
1. Establish ambitious target timelines for the Campbell availability.
2. Confirm the project breakdown into workstreams and execution buckets.
3. Understand the work content, dependencies, and assumptions within each workstream and bucket.
4. Determine how the workstreams should be staggered, including what to stagger on and how much stagger is required.
5. Challenge bucket durations within each workstream to determine how the plan can fit within the target timelines.
6. Identify constraints, risks, and obstacles, and define how they will be elevated, mitigated, or overcome.
7. Design the execution management processes required to maintain focus during execution.
8. Map the technical plan to the Focus & Finish plan.