This Statement of Work outlines the requirements for the U.S. Coast Guard (USCG) Base Portsmouth Electronic Support Division (ESD) to procure, deliver, install, and commission a new 18 kVA / 15.0 kW Uninterruptible Power Supply (UPS) system with an associated Maintenance Bypass Switch (MBS). The project encompasses five stages: site survey and preparation, decommissioning of the existing Best Power Technology Model FE18KVA/10C UPS and battery cabinets, installation of the new equipment meeting specified electrical requirements (single-phase 208/240 VAC input, 120/208/240 VAC output, 120V DC input at 151A, and 0.400kV TVSS rating), full functional testing and commissioning with load testing per manufacturer guidelines, and final cleanup with environmentally compliant disposal of legacy equipment and batteries. A mandatory post-award conference must occur no later than 15 business days after award, and all work must be completed within 60 calendar days from the date of award. Work shall be performed at USCG Base Portsmouth, 4000 Coast Guard Blvd, Portsmouth, Virginia 23703, during standard hours of 0700 to 1600 EST Monday through Friday, excluding federal holidays. The contractor must provide familiarization training for USCG ESD personnel on system operation, bypass procedures, and alarm acknowledgement.
This solicitation is designated as a Total Small Business Set-Aside under NAICS code 811210 (Electronic and Precision Equipment Repair and Maintenance). All labor, materials, equipment, delivery, and travel costs must be included in the overall cost proposal. The contractor must comply with all applicable federal regulations including the National Electrical Code (NFPA 70), OSHA safety standards, EPA environmental regulations, and USCG Base Portsmouth Environmental Policy (INST 5100-5105). A minimum one-year warranty on all labor and materials is required. Security requirements include valid government or state-issued identification for all contractor personnel, with pre-vetting required for base access; individuals without Real ID must present acceptable credentials such as RAPIDGate, TWIC, or DoD ID. The contractor must notify the Base Safety Officer (Kelvin.k.Smith@uscg.mil) in writing of operations affecting fire or explosion capabilities and provide Material Safety Data Sheets and permits to the Environmental Protection Specialist prior to work commencement.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW) | v1.0
STATEMENT OF WORK (SOW) FOR Uninterruptible Power
Supply (UPS) Replacement - USCG Base Portsmouth ESD
1.0 GENERAL
1.1 Background
The U.S. Coast Guard Base Portsmouth Electronic Support Division (ESD) maintains critical mission infrastructure that requires continuous, reliable power. The current Uninterruptible Power Supply (UPS), a Best Power Technology Model FE18KVA/10C, has aged and reached the end of its lifecycle. This project addresses the need to replace the old unit to ensure safe, uninterrupted operations for base personnel and equipment.
1.2 Scope
This Statement of Work (SOW) defines the requirements to procure, deliver, install, and commission a new 18 kVA / 15.0 kW Uninterruptible Power Supply (UPS) system and an associated Maintenance
Bypass Switch (MBS). All work will be executed at U.S. Coast Guard (USCG) Base Portsmouth, Electronic
Systems Detachment (ESD). The comprehensive scope encompasses site preparation, safe decommissioning of the existing UPS and MBS infrastructure, installation of the new hardware, full functional testing, and the environmentally compliant disposal of the legacy system and batteries.
1.3Objective
This solicitation seeks a qualified contractor to perform a comprehensive replacement of the UPS at
USCG Base Portsmouth ESD. The resulting system shall be fully integrated into the existing electrical topology, ensuring seamless power backup. All work shall be completed smoothly, safely, and in compliance with all electrical and environmental regulations.
2.0 APPLICABLE DOCUMENTS
The following documents provide specifications, standards, or guidelines that must be complied with:
• Relevant USCG regulations/standards regarding electrical construction and environmental protection: Base Portsmouth Environmental Policy, Base INST 5100-5105.
• National Electrical Code (NEC) / NFPA 70.
• All Manufacturer instructions and safety data sheets of products and equipment used by the contractor.
3.0 SPECIFIC REQUIREMENTS/TASKS
3.1 Stage 1: Site Survey and Preparation
• Verify existing electrical infrastructure, physical footprint, and room cooling capacities prior to installation.
3.2 Stage 2: Decommissioning
• Safely disconnect and remove the existing Best Power Technology (Model: FE18KVA/10C) UPS and all associated internal/external battery cabinets. Disconnect and remove the Maintenance Bypass
Switch (MBS).
3.3 Stage 3: Installation
• Furnish and install and integrate the new UPS system. The new equipment must meet or exceed the following baseline specifications to ensure compatibility with existing infrastructure:
• Capacity: 18 kVA / 15.0 kW, 60 Hz
• AC Input: Single Phase, 208/240 VAC (Capacity: 92/80 A, Power Factor: 0.95)
• AC Output: 120/208/240 VAC (Capacity: 149/84/73 A)
• DC Input: 120V, 151A
• TVSS Rating: 0.400kV (or modern equivalent)
• Equivalent Maintenance Bypass Switch (MBS) to support the system installation. Must match the primary input/output nominal voltage of the system.
3.4 Stage 4: Testing & Commissioning
• Perform full functional testing, load testing, and startup procedures per manufacturer guidelines.
• Provide familiarization training for USCG ESD personnel on standard operation, bypass procedures, and alarm acknowledgement.
3.5 Stage 5: Clean-up and Disposal
• Dispose of the legacy UPS and all batteries in accordance with local, state, and federal regulations
(e.g., EPA, DOT for hazardous materials) at no additional cost to USCG.
• Remove all debris and restore the site to its original clean condition.
4.0 CONTRACTOR PERSONNEL
4.1 Employee Conduct & Identification
Contractor employees must carry valid government or state-issued identification and comply with all
Government regulations.
4.2 Security
Contractors without a Real ID must present acceptable credentials (e.g., RAPIDGate, TWIC, DoD ID). All contractors requiring Base access will be pre-vetted prior to commencement of work.
5.0 OTHER APPLICABLE CONDITIONS
5.1 Period of Performance
The period of performance must not exceed 60 calendar days from the date of award.
5.2 Place of Performance
USCG Base Portsmouth, Electronic Support Division (ESD), 4000 Coast Guard Blvd, Portsmouth, VA
23703.
5.3 Hours of Operation
0700 and 1600 EST, Monday through Friday (except Federal holidays).
5.4 Travel
Travel is required for delivery and installation and shall be included as part of the overall cost.
5.5 Post Award Conference
The Contractor must attend a Post Award Conference with the COR no later than 15 business days after the date of award.
6.0 DELIVERABLES
ITEM SOW
REFERENCE
DELIVERABLE / EVENT Acceptance Criteria
1 5.5 Post Award Conference NLT 15 Days after award
2 3.2 Decommissioning Old UPS and batteries safely removed
3 3.3 Installation of New UPS Equipment installed meeting 18 kVA/15kW specifications
4 3.4 Testing & Training System passes functional tests; personnel trained
5 3.5 Disposal Documentation COR visual inspection and receipt of valid recycling/disposal certificates
7.0 SECURITY/SAFETY & ENVIRONMENTAL
All contractors shall abide by federal safety regulations as published by OSHA. Written notification must be provided to the Base Safety Officer Kelvin Smith (Kelvin.k.Smith@uscg.mil) for operations affecting fire or explosion capabilities. Contractors shall also abide by EPA regulations. Copies of Material Safety
Data Sheets and permits must be provided to the Environmental Protection Specialist prior to starting work.
8.0 WARRANTY
The contractor must provide a minimum one (1) year warranty on all labor and materials.