This is a Statement of Work (SOW) for construction of a recreational court complex at Kirtland Air Force Base, New Mexico, dated July 15, 2026 (Revision 2). The project involves demolition and removal of 120 feet by 130 feet (15,600 square feet) of existing asphalt, followed by installation of new concrete with fiber mesh reinforcement measuring 120 feet by 130 feet by 4 inches thick. The contractor must install nine new pole footings (2 feet wide by 2 feet deep with rebar cages), six new poles for three pickleball courts with netting, two new poles for a volleyball court with netting, and footing and pole base for a basketball half court. Additional work includes reinstalling existing fencing, providing and installing wind/privacy netting on all four sides, installing court striping for all three sports, providing all poles and associated equipment, and installing an electrical outlet near the basketball court. The project location is the Northwest corner of Wyoming Boulevard and D Avenue, Kirtland AFB, New Mexico.

The on-site performance period is 90 workdays for all work in Building 20130, with all work to be completed in a professional manner without delay. The contractor is responsible for furnishing all materials, labor, coordination, and supervision necessary to accomplish the work and shall comply with current versions of the International Building Code, National Electric Code, ADA standards, Air Force Instructions (AFI 91-202, AFI 91-203), and AFOSH Standards (29 CFR 1910 and 1926). The contractor must perform daily cleanup of demolition materials and dispose of waste off-base in accordance with local, state, and federal regulations. Contractor activities must follow Federal, AFOTEC, and Kirtland AFB regulations for security, safety, traffic, fire, and personnel clearances. Project managers are Robert Montaño (office 505-846-1572, cell 505-307-2459) and Victor Napolitano (office 505-846-5106, cell 505-263-3772) of the Engineering, Facilities and Logistics Division (AFOTEC/A-4F).

View the file

Other files

File Type Posted
Statement of Work (SOW) Exercise Court 31 Jul 26.pdf PDF
Questions And Answers 1 - FA704626QRJS2 - Exercise Court.pdf PDF
1000001952.jpg JPG image
Visitor-Prenotification-Form.pdf PDF
WD NM20260044 18 May 2026.pdf PDF
1000001956.jpg JPG image
1000001954.jpg JPG image
1000001950.jpg JPG image
1000001957.jpg JPG image
1000001951.jpg JPG image
1000001949.jpg JPG image
1000001960.jpg JPG image
1000001955.jpg JPG image
1000001953.jpg JPG image
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Date: 15 Jul 2026 Revision: 2 Original Date: 18 May 2026

Project Title: Pickleball/Basketball/Volleyball recreational court complex. Recreational court complex is located on the North West corner of Wyoming Blvd. and D Ave. Demo and remove 120’ by 130’ (15,600) sq ft of existing asphalt. Demo existing fence for construction access.

Reinstall fence and provide/install wind/privacy netting to all 4 sides of the fence upon project completion. Install 120’ x 130’ x 4” of concrete with Fiber mesh reinforcement. Install 9 new pole footings 2 feet wide by 2 feet deep with rebar cages. Install 6 new poles for 3 pickleball courts with nettings. Install 2 new poles for volleyball court with netting. Install footing and pole base for basketball half court. Provide all poles, striping material, pickleball coating and basketball goal.

Install striping for pickleball, basketball and volleyball courts. Install electrical outlet near basketball court placed next to fencing.

The contractor shall furnish all materials, labor, coordination and supervision necessary to accomplish the work in the recreational court complex located on the NW corner of Wyoming Blvd. and D Ave., Kirtland AFB, NM. Work shall be performed in a neat, substantial and a workmanlike manner.

1. Division 01 GENERAL CONDITIONS

1.1. All work shall meet the current versions of International Building Code, National Electric Code, ADA and all applicable commercial codes and standards.

1.2. Maintain the work site in a clean and orderly manner so that the safest possible site is provided for workers.

1.3. QUANTITIES: The Contractor shall field verify project requirements. A site visit where conditions may be field verified by the Contractor will be arranged by AFOTEC/A-4F.

1.4. REGULATIONS AND REQUIREMENTS: Contractor activities shall follow Federal, AFOTEC and Kirtland AFB regulations and directives for security, safety, traffic, fire, and personnel clearances.

1.5. PROTECTION AND CLEAN UP: Protect adjacent areas with appropriate coverings.

Clean the job area at the completion of each workday, including intervening spaces used for transporting goods and materials. Protect floors, walls and ceilings in areas affected by the work.

1.6. DEMOLITION: Demolition material and waste generated under this contract shall be removed from the building daily by the Contractor. Disposal of these materials and wastes shall be off-base in accordance with all local, state and federal regulations.

1.7. SUBMITTAL REQUIREMENTS: The Contractor shall obtain approval for submitted materials prior to incorporating them into the work.

1.8. SAFETY: Compliance with the current versions of Air Force Instructions (AFI) 91-202, AFI 91-203, and AFOSH Standards, 29 CFR 1910 and 29 CFR 1926 is mandatory. Contractor shall provide as a minimum, signs, barriers, and or caution tape as a safety precaution around the work site. Contractors are subject to inspections of job sites by the Department of Labor.

Resolution of Department of Labor Citations for Violations of Occupational Safety and Health Standards is a contractor responsibility.

1.9. DAMAGES: Features outside of the work area that are damaged by the Contractor shall be repaired and finished to match existing area at the Contractor’s expense. The Contractor shall be responsible for replacement of any items damaged during the construction performance period of this contract.

1.10. PERFORMANCE: The on-site performance period is 90 workdays for all work in Building 20130. All work shall be completed in a professional manner and without delay once the on-site work period is started.

1.11. CHANGES: Changes to this Statement of Work shall be requested in writing to and approved prior to execution. The Contractor shall notify the AFOTEC/A-4F of differing site conditions as they are found and obtain approval for any changes required.

1.12. SALVAGE: All salvageable materials and equipment shall be the property of the Contractor unless otherwise noted in this SOW and/or drawings. The Contractor is responsible for the removal of all salvageable materials and equipment from the job site.

1.13. MATERIALS: All materials shall meet applicable specifications, standards, and codes.

1.14. EXECUTION: All work shall be performed in accordance with manufacturers’ published specification, shall meet accessibility standards (ADA) and shall conform to applicable current versions of International Building Code and all applicable local commercial codes.

1.15. POINT OF CONTACT:

1.15.1. Project managers for this project are Robert Montaño of Engineering, Facilities and Logistics Division (AFOTEC A4F), office # 505-846-1572, cell # 505-307-2459, e-mail robert.montano.2@us.af.mil and Victor Napolitano of Engineering, Facilities and Logistics Division (AFOTEC/A-4F), office # 505-846-5106, cell # 505-263-3772, e-mail victor.Napolitano.1@us.af.mil.

1.16. REFERENCES:

1.16.1. NFPA 101, 2009, Life Safety Code

2. Division 02 SITE CONSTRUCTION

2.1. Protect existing surfaces from damage.

3. Division 03 CONCRETE.

4. Division 04 MASONRY (Not used).

5. Division 05 METALS (Not used).

6. Division 06 WOODS & PLASTICS (Not used.)

7. Division 07 THERMAL & MOISTURE PROTECTION (Not used).

8. Division 08 DOORS & WINDOWS.(Not used)

9. Division 09 FINISHES.(Not used)

10. Division 10 SPECIALTIES (Not used).

11. Division 11 EQUIPMENT. (Not used).

mailto:robert.montano.2@us.af.mil mailto:victor.Napolitano.1@us.af.mil

12. Division 12 FURNISHINGS. (Not used).

13. Division 13 SPECIAL CONSTRUCTION (Not used).

14. Division 14 CONVEYING SYSTEMS (Not used).

15. Division 15 MECHANICAL (Not used).

16. Division 16 ELECTRICAL.

16.1 Equipment, material, installation, and workmanship shall be in accordance with mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.

END SCOPE OF WORK