Statement of Work (SOW).pdf
PDF 190 KB Posted
- Attached to
- Underwater Hull Cleaning
- Solicitation number
- N0040626Q0551
About this file
Summary
This is a Statement of Work (SOW) for underwater hull cleaning services on a naval vessel scheduled for September 21 through October 7, 2026. The work item, identified as SOR 26-013 Category "A," is a preparatory cleaning operation to support an Underwater Inspections in Lieu of Drydocking (UWILD) survey to be conducted at a separate location and date. The vessel is a T-AKE class ship measuring 688 feet 11 inches in length and 654 feet in breadth, with forward and aft drafts of 22 feet 10 inches and 27 feet 9 inches respectively. The work involves one propeller and one rudder. No government-furnished equipment, materials, or services are provided; the contractor bears full responsibility for all diving operations and equipment.
The contractor must conduct comprehensive underwater hull cleaning to completely remove all marine fouling from the entire submerged hull, propeller, rotating coupling covers, fairwaters, rope guards, rudder, bilge keels, gratings, screens, and splitter bars on hull penetrations. The waterline area must be cleaned 12 inches above the waterline, with cleaned surfaces conforming to NSTM Chapter 081. Critical pre-cleaning activities include a Pre-Survey Planning Meeting with ship representatives, vessel operations team (OMT) representatives, and diving personnel to verify safety procedures, diver qualifications, communication protocols, emergency procedures, and environmental conditions. The contractor must inspect and document hull conditions before and after cleaning using Level I inspection standards per the Underwater Ship Husbandry Manual. Upon completion, the contractor shall submit condition reports in PDF format and provide a video recording with audio commentary of all external underwater areas on DVD, with copies distributed to the vessel's Chief Engineer and uploaded to the MSC Technical Library. The work requires strict compliance with high-voltage electrical system safety protocols and lockout/tagout procedures specific to T-AKE class vessels.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - N0040626Q0551_Redacted.pdf | ||
| 1.3.5 Under SAT SSJ_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRYDOCKING
ITEM NO. SOR 26-013 CATEGORY "A"
Underwater Hull Cleaning
SOR 26-013 - 1
1.0 ABSTRACT
The purpose of this item is to conduct an Underwater Hull Cleaning in preparation for the vessels upcoming UWILD that will be conducted at another location on another date.
Location: TO BE SENT SEPARATELY
Period of Performance: 21 Sep 2026 – 07 Oct 2026
2.0 REFERENCES
NOTE: PPE verify and update references as required for the applicable vessel prior to submission.
2.1 NAVSEA Drawing No. 801-8388177, Docking Plan
2.2 NAVSEA Drawing No. 085-7488873, Shell Expansion
3.0 ITEM LOCATION/DESCRIPTION
3.1 Location/Quantity
3.1.1 Locations: Underwater hull
3.1.2 Quantity: One
3.2 Item Description/Manufacturer’s Data
Vessel length: 688 ft 11 in
Vessel breadth: 654 ft
Vessel draft (fwd): 22 ft 10 in
Vessel draft (aft): 27 ft 9 in
# of Rudders One
# of Propellers One
SOR 26-013 - 2
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE: None
5.0 NOTES
5.1 This work item is applicable to vessels who have
approval from ABS to conduct ABS Rules for Survey After Construction, Part 7, Appendix, Section 1, Underwater Inspections in Lieu of Drydocking Surveys. If a vessel has any outstanding recommendations for repairs to the propeller, rudder, stern frame, underwater structure, or sea valves it may not be eligible for UWILD.
5.2 THIS SHIP CONTAINS HIGH VOLTAGE (HV) ELECTRICAL
SYSTEMS. OBEY ALL POSTED AND VERBAL INSTRUCTIONS REGARDING
SAFETY AND EXCLUSION FROM HIGH VOLTAGE AREAS. AT NO TIME
APPROACH, WORK ON, OR ENTER A HIGH VOLTAGE AREA WITHOUT PROPER
AUTHORIZATION.
5.3 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT
FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE
CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK, AND
WHITE. ASSUME ALL ELECTRICAL CABLES ARE ENERGIZED UNTIL TESTED
AND PROVEN OTHERWISE. TEST ALL ELECTRICAL CABLES TO ENSURE THEY
ARE DE-ENERGIZED PRIOR TO WORKING ON THE ITEM.
5.4 POP LOCATION: TO BE SENT SEPARATELY September 21, 2026
through October 7, 2026.
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional
7.0 STATEMENT OF WORK REQUIRED
7.1 Conduct an Underwater Cleaning sufficiently to support
an ABS UWILD that will be conducted on a later date at another location.
7.2 Coordinate with ship’s force to have associated
equipment locked and/or tagged out per ship’s lock out/tag out policy. When the maintenance is complete, coordinate with ship’s force to have associated equipment unlocked and/or tagged in per ship’s lock out/tag out policy.
SOR 26-013 - 3
7.2.1 With assistance from the OMT REP tag out all
overboard discharges, pump suctions, cathodic protection systems, jacking gear, and other systems or equipment that could affect divers.
7.3 Conduct a Pre-Survey Planning Meeting with the OMT
REP, Divers Rep, Master, Chief Engineer, and OMT REP in attendance. The meeting agenda and discussion shall, at a minimum, cover:
7.3.1 Verify diver tagout and diver check sheet has been
filled out accurately.
7.3.2 Identify the Diving contractor, the number of
divers to be employed and the type of dive equipment to be used.
Discuss their experience, training and qualifications in underwater photography and NDT if needed.
7.3.3 Discuss means of communication between the bridge, dive team and engine room (direct communications via sound powered phones are preferred).
7.3.4 Discuss procedure/plan for emergencies.
7.3.5 Provide Divers with reference data and instructions
necessary for underwater operations such as means of access to sea chests to inspect the external side of hull connections and sea valves
7.3.6 Discuss divers means to conduct underwater
nondestructive testing for fracture detection, if required.
7.3.7 Discuss the in-water clarity (visibility)to perform
a proper hull cleaning.
7.3.8 Discuss vessels anticipated drafts, pier side
clearance and under keel clearance at the time of the survey.
7.3.9 Discuss impact of tides and currents on divers and
the examination.
7.3.10 Discuss anticipated duration of the hull cleaning
SOR 26-013 - 4
7.4 Prior to performing the underwater hull cleaning the
Contract shall inspect the condition of the underwater hull and ship systems both before and after the cleaning operation as follows:
7.4.1 The contractor, for his own protection, shall
inspect the hull and appendages to determine the condition prior to cleaning and document on the pre-cleaning biofouling inspection data form
7.4.2 In the event underwater inspection reveals only
light fouling, or in the event underwater inspection reveals excessive calcareous fouling, paint deterioration, or other gross defects affecting the operational capabilities of the ship, e.g., propeller damage; the contractor shall inform the MSCREP and Vessels Chief Engineer of the location and request a decision to proceed or cancel the cleaning operation.
7.5 Conduct underwater hull cleaning. The contractor
shall:
7.5.1 Completely remove all marine fouling from the
entire underwater hull; propeller, and rotating coupling cover(s) and fairwater(s) and rope guard(s); rudder(s); bilge keels, all gratings, screens, and splitter bars on hull penetrations, and appendages.
7.5.2 The area along the ship waterline shall be cleaned
to a height of 12 inches above the waterline; based on ships draft during the cleaning operation.
7.5.3 At completion of the cleaning, the cleaned surface
shall conform to NSTM Chapter 081. Extreme caution shall be exercised by the contractor to prevent damage to the coating and ship systems by any of its operations, procedures, or equipment.
7.5.4 Immediately upon completion of cleaning, the
contractor shall inspect the hull and appendages to determine the condition of accessible components. The contractor shall inspect, photograph, and document the general condition of each accessible component and any damage discovered shall be inspected and documented to the detail of a Level I inspection, as defined in the Underwater Ship Husbandry Manual, Chapter 17, SOR 26-013 - 5
“Inspections”, (NAVSEA S0600-AA-PRO-170). The ship’s Chief Engineer, may request the contractor to perform a more detailed Level II inspection of the damage.
7.6 Upon completion of the survey, restore all access
cover plates, threaded plugs, suction grates, remove all blanks, leaving the vessel in a ready for service condition.
7.7 Reports
7.7.1 When examination and servicing reveal any
deficiency a condition report is to be submitted to the OMT REP with recommended repair and parts required. Submit one electronic copy in Portable Document Format (PDF).
7.7.2 Submit a copy of a video tape with audio commentary
of all external areas of the underwater hull, including rudder, propeller, tailshaft, hull protective system, and all other attached appurtenances. Publish the video on DVD in a format readily accessible/playable using Windows™ software applications such as Windows Media Player, or others. Provide one copy to the vessels Chief Engineer. The Vessels Principal Port Engineer will provide the contractor a DoD Safe Link to upload the video to store in the MSC Technical Library.
7.8 Painting: None additional
7.9 Preparation of Drawings: None
8.0 GENERAL REQUIREMENTS: None additional