Gulf Islands National Seashore Ocean Springs, Mississippi

PMIS# 313368

PEPC# 98294

STATEMENT OF OBJECTIVES:

DAVIS BAYOU MARINA RESTROOM HURRICANE ZETA

REPAIRS

DATED:

March 2021

NATIONAL PARK SERVICE

STATEMENT OF OBJECTIVES (SOO)

SOO Format

1. Background

2. Objectives

3. Place of performance

4. Period of performance

5. Scope

6. Safety

7. Tasks

8. Submittals

9. Government-Furnished Property (GFP)

10. Security Considerations

11. Special Material Requirements

12. Other Unique Requirements and Considerations

13. Quality Assurance Requirement

14. Project Personnel

15. Attachments

1. BACKGROUND

Gulf Islands National Seashore (GUIS) is a unit of the National Park Service and is head quartered in Gulf Breeze, FL. This contract is to repair hurricane damaged facilities at Gulf Islands National Seashore Mississippi District, Davis Bayou. On October 28, 2020, Hurricane Zeta made landfall just west of Gulf Islands National Seashore Mississippi District. Storm surge of 13 feet inundated the Park unit causing flood damage, debris and fallen trees. Damages caused the Park Management Team to close the park to visitors. This project is to restore the marina restroom at Davis Bayou and return the facility to operational status for visitors. Davis Bayou is located near Ocean Springs, Mississippi.

2. OBJECTIVES:

The work of this contract will include the provision of all labor, equipment, supervision and materials to accomplish a turnkey repair of the marina restroom facility at the Davis Bayou Area, Mississippi District, Gulf Islands National Seashore, including but not limited to:

• Roll up door replacement

• Removing and replacing sinks

• Partition wall and door installation

• Masonry wall repairs

• Caulking and painting

• Removal and proper offsite disposal of waste created in the demolition and repair process.

• Cleaning and prepping interior surfaces to remove any mold/mildew before application of any paint, sealant, wallboard, flooring, or subflooring.

3. PLACE OF PERFORMANCE:

Gulf Islands National Seashore, Mississippi District, Davis Bayou. Davis Bayou is located near Ocean Springs, Mississippi.

4. PERIOD OF PERFORMANCE:

All work specified herein shall commence after the notice to proceed is received from the Contracting Officer; and completed within a 2-month (60 day) period.

5. SCOPE:

The project consists of repairing damage to facilities caused by Hurricane Zeta. The contractor shall deliver the following services and provide an itemized cost breakdown to include materials/equipment, labor, administrative, and other fees. The contractor shall have an on-site superintendent/foreman present at all time when work is being performed.

In accordance with the terms and conditions herein, the prime contractor or sub-contractors shall perform the work of this contract for the National Park Service (NPS).

The contractor shall complete the following items:

1. Provide all material, equipment, parts and labor required to perform all of the work of this contract

2. Use paint that has mold inhibitor.

3. All equipment, material, and waste removed or generated by work of this contract shall be properly disposed of offsite by the contractor.

4. Contractor shall verify the quantity of materials needed to complete the task identified in this SOO.

5. Contractor shall protect their work at all times including protection against theft or damage. Upon completion of work, the Contractor shall remove all paint from glass and other surfaces. All excess materials, rubbish or other waste/debris shall be properly disposed of and the site returned to a clean and orderly condition.

6. Contractor shall provide a work site and environment that is safe for employees, visitors, and NPS staff. If needed, the work area will be cordoned off and secured.

7. Contractor and employee parking and equipment storage areas will be designated by the Park. No company signs shall be installed on government property. Smoking and eating shall be performed in areas designated by the Park. Employees shall wear appropriate clothing at all times.

8. Contractors shall notify NPS staff of scheduled site visits to ensure access to secure areas.

9. The Davis-Bacon Act applies for this contract.

6. SAFETY:

All work performed on government property shall be accomplished in accordance with OSHA, EPA, Federal, State and local regulations and requirements. Prior to starting work on government property, the contractor shall submit to Gulf Islands National Seashore for approval a copy of their company safety plan pertaining to this particular contract. Although not all inclusive, the safety plan shall address at a minimum the following areas:

1) Heavy equipment operations (if required)

2) Fall Protection Plan

3) Public/visitor safety (barriers/signage, etc…)

4) Traffic safety plan (if required)

5) Trenching/sloping of soil (if required)

6) Personal protective equipment to be used

7) Hazardous materials (HAZMAT) to be used

a. Copies of Safety Data Sheets (SDS) must be provided to the Park

b. Storage of HAZMAT

8) Emergency response protocols

9) Personnel training requirements

10) OSHA DART rate

a. OSHA 300A Summary for the last three years

Contractor shall use “green” products whenever possible and all HAZMAT must be pre-approved for use by the GUIS Collateral Duty Safety Coordinator. The contractor shall be responsible for the safety and security of the site to ensure unauthorized personnel (park visitors & employees) do not enter the construction area.

7. TASKS:

COMMUNICATION

A). Contractor shall notify the Contracting Officer’s Representative (COR) between 7:00 and 7:15 am on the morning work will be performed, or inform the COR why services cannot be performed that day. The COR is Ernest Echoles, office number: 228-230-4115, cell phone: 228- 323-5356.

B). Work shall be performed during daylight hours between 7:00 am and 3:30 pm Monday through Friday as per the established schedule. Weekend and holiday work will not be permitted, unless due to inclement weather, equipment problems, etc. without the prior approval by the park Contracting Specialist.

C). Schedule changes shall be cleared through the Contracting Officer

SPECIFIC REQUIREMENTS

Under this contract, the contractor shall complete the following tasks and requirements:

• Marina Restroom (MS25) o Install new wall mounted sink to match existing sink complete with ABAAS compliant faucet, water supply lines, and drain lines. (Masonry patch required for new sink install).

o (Men’s) Demo, and remove 2’ x 6’- 4” masonry partition wall.

o (Men’s) Install 1 ABA compliant Phenolic toilet partition with hardware .

o (Women’s) Demo and remove 2’ x 6’- 4” masonry partition wall; replace with 4’-

6” x 2’ ABAAS compliant Phenolic partition/stall door and hardware.

o Remove existing roll up door and hardware and replace with lockable 96” x 104” exterior aluminum grille roll up door and hardware.

o Caulk and Paint interior of the whole facility.

8. SUBMITTALS:

Before notice to proceed

• Provide product submittals for new units to be installed for approval by COR.

• Provide a written narrative summary of how the contractor will execute the project with a timeline. This document will be referred to as the implementation plan.

• Provide safety plan as identified in Section 6.

• Provide waste disposal plan. All recyclable items such as metal doors, window frames, glass, wood, or cardboard packaging shall be recycled. All debris shall be disposed of properly according to EPA, State, Local, and Federal guidelines.

Before contract close out

• If applicable, provide one (1) hard-bound copy of Operation and Maintenance (O&M)

Manuals to the park for all equipment installed. O&M manuals are to include the manufacturer’s specifications and instructions for all new equipment.

• Provide one (1) hard-bound copy of all warranty information for new equipment. Must include list of all model and serial numbers as applicable.

• Provide statement(s) of proper disposal of construction debris and hazardous materials (if applicable).

9. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION

(GFP, GFM, GFE, OR GFI):

None.

10. SECURITY:

The information developed under this Statement of Objectives is the property of the U.S.

government and shall be kept in strict confidence. Proprietary or copyrighted material may not be included into the contract information CDs unless otherwise approved in writing by the Contracting Specialist.

11. SPECIAL MATERIAL REQUIREMENTS:

• Interior Paint color and finishes shall match the existing paint finish.

• Paint and primers shall be mold and mildew resistant latex

• Color and style of partitions shall be approved by COR.

• At least three (3) options presented to the COR for approval prior to installation.

12. OTHER UNIQUE REQUIREMENTS:

None

13. QUALITY ASSURANCE REQUIREMENT:

The government will periodically evaluate the contractor’s performance in accordance with the statement of work. All new equipment must conform to the manufacturer’s instructions and guidelines for installation and start-up.

While performing work, the contractor shall comply with the latest applicable versions of the following:

• International Family of Codes, primarily the IBC (International Building Code)

• American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE) Standards and Guidelines

• National Environmental Balancing Bureau (NEBB)

• Associated Air Balance Council (AABC)

• NFPA 101 (National Fire Protection Association's Life Safety Code)

• Federal, State and Local Building Codes, Standards and Policies

• Local codes only if required by utility companies for service connections.

• National Electrical Code (NEC)

• Occupational Safety and Health Administration (OSHA) requirements

Additional Requirements:

• Any damages to areas not specified in this document shall be fixed and repaired at no cost to the government.

• Any unused conduit, plumbing, ductwork, or other misc. equipment shall be removed from the worksite by the contractor and at the contractor’s expense.

• All new equipment must conform to the manufacturer’s instructions and guidelines.

14. PROJECT PERSONNEL:

Contracting Officer (CO):

Evans Andre Ward O: 850-934-2614 C: 850-232-4630 Email: andre_ward@nps.gov

Contracting Officer Representative (COR):

Ernest Echoles Facility Manager O: 228-230-4115 C: 228-323-5356 Email: ernest_echoles@nps.gov

Chief of Facility Management (CFM):

Gary Stansberry Chief of Facilities O: 850-934-2610 C: 850-232-3625 Email: gary_stansberry@nps.gov

15. EXHIBITS:

A – Map B – Photos C – Schedule of Values

1 Marina Restroom GUIS FY21 Incident Damage Survey – Data.pdf 2 Marina Restroom GUIS FY21 Incident Damage Survey – Data.pdf mailto:ernest_echoles@nps.gov mailto:gary_stansberry@nps.gov Ian Pierson A - map B - photos

C - SOV

Gulf Islands National Seashore, Davis Bayou Area is located near Ocean Springs, Mississippi.

Davis Bayou Marina Restroom is located near the Government Boat Dock at the end of Park Road.

1 Marina Restroom GUIS FY21 Incident Damage Survey – Data.pdf

2 Marina Restroom GUIS FY21 Incident Damage Survey – Data.pdf

Statement of OBJECTIVES (SOO)
1. Background
2. Objectives:
3. Place of Performance:
4. Period of Performance:
5. Scope:
6. Safety:
7. Tasks:
8. submittals:
9. Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI):
10. Security:
11. Special Material Requirements:
12. Other Unique Requirements:
13. Quality ASSURANCE Requirement:
14. Project Personnel:
15. EXHIBIT S: