STATEMENT OF WORK_Security Gate Fabrication and Installation.pdf
PDF 440 KB Posted
- Attached to
- Security Gate Fabrication and Installation
- Solicitation number
- D-25-IG-9999
About this file
This Statement of Work details requirements for Vehicle Security Gate Installation and Configuration for the Drug Enforcement Administration (DEA). The contract requires a contractor located in Virginia Association of Counties (VACo) Region 7 to install a security gate system within eight weeks of award, including constructing two 2.5' squared stone columns, a 14' wide and 6' tall gate with 2"x2" railings, Viking F1 gate operators, detection loops, a cellular entry unit with advanced features like live camera feed and motion detection, and a goose neck pedestal. The contractor must provide all labor, materials, equipment, and ensure compliance with manufacturer specifications and safety requirements.
The solicitation (Number D-25-IG-9999) is 100% set-aside for Small Business concerns under NAICS 561621, with quotes due by August 6, 2025, at 12:00 PM EST. The government intends to award a single firm-fixed price purchase order to the lowest-price technically acceptable offeror. Interested parties must submit any questions by August 5, 2025, at 10:00 AM EST to Laura Over at laura.e.over@dea.gov, with all submissions to be sent electronically to the same email address.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| STATEMENT OF WORK_Security Gate Fabrication and Installation.pdf | ||
| REQUEST FOR QUOTE_D-25-IG-9999.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
VEHICLE SECURTY GATE INSTALLATION AND CONFIGURATION
General requirements, specifications and components:
The Drug Enforcement Administration requires contracted services for Vehicle Security Gate Installation and Configuration. The Contractor shall be located in and able to service rural areas in Virginia Association of Counties Regions (VACo) Region 7. Location of service will be provided by the Government upon award of this order.
1.0 REQUIREMENTS: The Contractor capable of performing the Government’s need shall meet the following requirements no later than eight (8) weeks from time of award:
PRE-CONSTRUCTION/SITE REVIEW
1. Pre-construction meeting. Conduct pre-construction meeting with Government personnel.
2. Utility Coordination. Contact applicable utility company, company information will be provided by the Government upon award of this order, to:
a. Identify utility connection locations and ensure they are marked as needed;
b. Determine if there are any obstructions that require work arounds;
c. Determine final placements of gate components (Columns/Gate Panels/Entry
Unit/Free Exit Vehicle Detection Loop/etc.).
3. Material Fabrication and Sourcing. The Contractor is responsible for ordering, purchasing, securing, transporting, and delivering of all materials, including any items requiring fabrication (i.e. Gate Panels).
4. Submit a Construction plan. The Contractor’s Construction plan will be reviewed and approved by the appropriate Government personnel prior to work beginning. The Contractor’s construction plan shall include an accurate and complete timeline and completion date including, but not limited to, any lead time ordering, required interdependencies (as applicable), apparent issues, etc. The Contractor’s timeline, established completion date, and performance execution shall be as expeditious as possible (meeting and exceeding the established delivery date if possible) while still meeting the stated requirements. The Contractor shall provide all salient information needed for the Government to approve the Construction Plan.
CONTRUCTION:
1. Complete all necessary construction activities in accordance with the approved Construction Plan include labor, materials, equipment, and all other kit required to meet the Government’s requirement. The Contractor is responsible for all safety measures for their personnel while on site. The Contractor is responsible for all equipment functionality, quality, and safety testing and ensure that any programmed function is programmed in accordance with the Government’s specifications.
2.0 SPECIFICATIONS:
1. Labor: The Contractor shall provide all labor required for the completion of the gate fabrication and installation except for those functions that are subcontracted out due to the specialty nature of the work (i.e. Gate panel fabrication, etc.)
2. Vehicle Security Gate: See Addendum 1. The Contractor shall match the style of the gate as shown in the photo provided in Addendum 1, as closely as possible. The Contractor shall provide ensure gate panels are a minimum of 2”x2” top and bottom railings with an opening of 14’ and a height of 6’. The Contractor is responsible for is responsible for priming, painting, installing the gate panels using appropriate (heavy rated) hinges and a minimum of 6” square steel posts delivered to the site and sunk in concrete.
3. Columns: The Contractor shall match the style of the columns as shown in the photo provided in Addendum 1, as closely as possible. The Contractor shall construct 2, 2.5’ squared, 6’ tall columns with stone caps built to match the stone of the existing property. The Contractor shall supply and install the conduit for the gate and carriage lights within the columns. Carriage lights and the installation of carriage lights will be provided by the customer.
4. Gate Operator: Minimum 2 Gate Operators – Viking F1 Vehicular Swing Gate Operator. The Contractor shall provide all necessary loop detector materials and equipment and installation including tubing in the surrounding area for vehicle detection. Detection loops shall be installed inside and outside of the gate. The Contractor shall backfill all interconnection trenches following detection loop installation with existing gravel.
5. Surge Suppressor: The Contractor shall provide dedicated equipment panel (2) and telephone entry (1) surge protective devices, and ground rod package. Equipment panel surge suppression shall be at a minimum 120/240v, approved for 20A circuit breakers, Diagnostic LED Indicated ground presence, system power and SPD Function, Weatherproof enclosure. Telephone entry surge suppression shall at a minimum protect the power supply, telephone line, and data/release circuits.
6. Cellular Entry Unit: (Equal to AES Opyn Advanced IP-4G Video Telephone entry system) The Contractor shall provide and install a cellular entry unit that includes live camera feed through a cellular phone application, motion detection alerts, 2x relays, night vision, LED luminance, voice control/activated (Alexa/Google) assistant integration, tamper alarm, image/video download, multiple device accounts, customizable voicemail, QR codes, keypad codes, and activity log.
7. Goose Neck Pedestal (Curb Mount): The Contractor shall provide and install the curb mount goose neck pedestal housing the applicable video entry equipment.
8. Ancillary machinery, equipment, and supplies: The Contractor shall provide all machinery, equipment, and supplies required to fulfill the outlined requirement. This includes but is not limited to machinery, fuel, oil, transportation to and from site, minor hardware, electrical components, shop towels/rags, tools and meter usage as needed.
SAFETY AND COMPLIANCE: The Contractor shall comply with all manufacturer specifications and safety requirements.
QUALITY CONTROL: The Contractor shall ensure that the site is left unharmed and will meet with a Government representative to confirm completion of all requirements prior to departing the work site.
SECURITY: All contractor personnel shall be vetted in accordance with Government security requirements prior to performing work on the property. The contractor shall coordinate with the Government to ensure this requirement is met prior to the start of performance.
ADDENDUM 1