Statement_of_Work_-_Roof_Replacement.pdf
PDF 8 MB Posted
- Attached to
- VC AND MAINT SHOP ROOF REPLACEMENT Federal contract opportunity
- Solicitation number
- 140P6425B0010
About this file
The provided document is a Project Specifications document for a roof replacement project at the George Washington Carver National Monument in Diamond, Missouri. The project involves replacing roofing on two buildings: the Visitor Center (VC) and Maintenance Shop (MS). Specifically, the work includes:
- Removing and replacing 17,668 square feet of laminated asphalt shingle roofing and underlayment on the VC Building and breezeway
- Installing 2,900 square feet of EPDM roofing with tapered solid insulation and coverboard on the VC building
- Adding thirty 30x30 flexible walkway pads
- Replacing 3,540 square feet of laminated asphalt shingle roofing and underlayment on the Maintenance Shop building
- Replacing various metal flashings, including step flashing, apron/wall flashing, drip edge, and flashing for roof penetrations
The project requires a 30-year materials warranty, with the first 10 years nonprorated, and includes wind-speed and algae-resistance warranties. The roofing shall use minimum 30-year laminated architectural shingles and 0.060" thick EPDM roofing, with work to be completed within 90 calendar days of the Notice to Proceed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6425B0010_Amd_0001.pdf | ||
| GWCA_Roof_Replacement_-_Questions_and_Answers_0001.pdf | ||
| Sol_140P6425B0010.pdf | ||
| Price_Schedule_-_Roof_Replacement.xlsx | XLSX spreadsheet | |
| Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| DOL_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
George Washington Carver National Monument 5646 Carver Road
VC and Maintenance Shop Roofing Replacement
PMIS 321981
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
2025-04-03
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 07 – THERMAL and MOISTURE PROTECTION Section 07 31 13 Asphalt Shingles Section 07 53 23 EPDM Roofing
SITE PLAN – APPENDIX A
PHOTOGRAPHS – APPENDIX B
EXISTING BUILDING DRAWINGS – APPENDIX C
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The Visitor Center building was designed in 1958-1959 and dedicated 1960. It is one of twenty-eight Mission 66 era visitor centers constructed between 1956 and 1966 in National Park Service units designated as national monuments. The building has undergone substantial modifications, including new siding and a new roof in 1993, and a major expansion in 2007. The expansion increased the size of the building, from 3,000 to 18,000 square feet and significantly altered its appearance. Because of this, the Visitor Center no longer retains its historic integrity and it is not a contributing resource.
The Maintenance Building located just south of the Visitor Center was built at the same time as the Visitor Center, also as part of the Mission 66 program. An open breezeway to the east links the two buildings. There have been few apparent exterior alterations to the building. The structure is one-story, with an asphalt covered gable roof installed in 2007. It is contributing to the second period of significance.
The goal of the project is to replace the roof coverings on both structures and the connecting breezeway.
1.2 Work Covered by the Contract Documents:
1. Project Location: George Washington Carver National Monument 5646 Carver Rd, Diamond Missouri, 64840.
2. Work consists of the removal and replacement of the following (all measurements are approximate and subject to verification by the bidder):
a. 17,668 square feet of laminated asphalt shingle roofing and underlayment on the Visitor
Center (VC) Building and breezeway,
b. 2900 square feet of EPDM roofing including the underlying tapered solid insulation and coverboard on the VC building, and thirty 30”x30” flexible walkway pads,
c. 3540 square feet of laminated asphalt shingle roofing and underlayment on the
Maintenance shop (MS) building,
d. Metal flashing replacement will include:
i. 150 linear feet of step flashing,
ii. 400 linear feet of apron/wall flashing,
iii. 1700 linear feet of drip edge,
iv. 62 linear feet of cap flashing (12” wide),
v. 150 linear feet of valley flashing,
vi. other assorted flashings, and underlayments,
e. Flashing, boots, etc. for the following roof penetrations:
i. 75 linear feet of ridge vent on the VC roof
ii. Two 4” heater vents on MS roof
iii. four 3” plumbing (soil stack) vents on shingled roof
Page | 4
iv. one 3” plumbing (soil stack) vent on EPDM roof
v. one 20” powered downdraft exhaust vent on EPDM roof
vi. one 34”x39” roof hatch on EPDM roof
vii. one 82”x108” energy recovery ventilator on EPDM roof
viii. two 28”x40” exhaust hoods on the VC shingle roof
ix. two 36”x36” exhaust hoods on the MS roof
f. Up to 10% of damaged roof sheathing/decking will be replaced as needed.
g. Work will also include the temporary removal and reinstallation of the following existing items:
i. one antenna mast, MS roof
ii. lightning protection system (both buildings)
iii. guttering (removal and reinstallation only as required), VC roof.
Shingles will be replaced with equivalent (design and color) minimum 30 year laminated architectural shingles, and EPDM roofing will be replaced with minimum 0.060” thick EPDM.
3. All work will be performed under a single contract.
4. Period of performance: Work shall be completed within 90 calendar days of the start date provided on the Notice to Proceed.
a. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
i. The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
ii. IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50-foot radius of discovery and notify the Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
iii. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays
Page | 5 and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
iv. The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure involved in the work of this Contract is a designated historic structure listed in the National Register of Historic Places. Every precaution shall be taken by the Contractor to prevent damage to existing historical materials, structural components of the building and to the surrounding area. Should any damage be incurred as a result of the Contractor’s operations at the site, it shall be repaired, or the damaged materials replaced in kind by the Contractor to the satisfaction of the Contracting Officer at no additional expense to the Government.
C. There is no excavation required for this project.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/gwca/learn/management/superintendent-s-compendium.htm
Page | 6
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. e. Contractor will work with COR to ensure that work does not interfere with special events. Known dates with scheduled special events will be provided at the time of award. These dates are subject to change and additional dates may be added.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
Monday through Friday 7 am to 3:30 pm., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year’s Day Inauguration Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
• Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 7
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to within 30’ of the building perimeter. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork, and clearing of vegetation, to:
1. n/a
Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: Water from existing water system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Sanitary Operations:
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual
Page | 8 inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant protection is not required for this project.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Not required.
6. Hot Work Permit: Not Required
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area shown in appendix A below may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features:
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site.
Coordinate with COR for approved dumpster locations prior to commencing construction.
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local means.
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
Page | 9
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated. Contractor will maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR. Contractor will maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied:
1. N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
Page | 10
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
a) 1. Do not exceed the following dB(A) limitations at 50 feet: 70 dB(A) More than
12 minutes in any hour, 80 dB(A) More than 3 minutes in any hour. 2. Maximum permissible construction equipment noise levels at 50 feet: Compressors 75 dB(A), Pneumatic Tools 80 dB(A), Pumps 75 dB(A), Saws 75 dB(A), Generators 75dB(A), Vibrators 75 dB(A) 3. Ambient Noise maximum noise levels (dB) for receiving noise area at property line shall be as follows. Residential receiving area: Daytime 65 dB Nighttime 45 dB. Commercial/Industrial receiving area:
Daytime: 67 dB Nighttime: 65 dB
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Page | 11
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 12
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
Page | 13
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
Page | 14
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
Page | 15
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
Page | 16
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line-Item No. 1, VC and Maintenance Shop Roofing Replacement
1. This item consists of removal and replacement of asphalt shingle and EPDM roofing and associated materials to ensure a watertight roof.
2. Payment will be made per the contract and percentage of completion level.
Bentley, Thomas L You will need to place at least one CLIN even if you define it as the title of the project. Item consists of ‘removal and replacement of asphalt shingle and EPDM roofing and associated materials to ensure a watertight roof’ or similar.
Page | 17
END OF SECTION
Page | 18
Appendix A Site Plan
Page | 19
Appendix B Project Photos
Page | 20
Page | 21
Page | 22
Page | 23
Page | 24
Page | 25
Page | 26
Photo Index
1. VC and Breezeway E side
2. VC SE side
3. VC E side
4. VC NE side
5. VC N side
6. VC NW side
7. VC W side
8. VC SW side
9. VC S side (1)
10. VC S side (2)
11. VC S side (3)
12. Breezeway W side
13. Maintenance Shop NE side
14. Maintenance Shop N side
15. Maintenance Shop W side
16. Maintenance Shop S side
17. EPDM roof drains (1)
18. EPDM roof drains (2)
19. EPDM roof EVR
20. EPDM roof Elevator Shaft
21. EPDM roof exhaust fan
22. EPDM roof access hatch
23. EPDM roof cap flashing
24. VC roof detail (1)
25. VC roof detail (2)
26. VC roof detail (3)
27. VC roof detail (4)
28. VC roof detail (5)
29. VC roof detail (6)
30. VC roof detail (7)
31. VC roof soil stack
32. VC roof exhaust hoods
33. Maintenance Shop antenna, soil stack, turbine vent, exhaust hood
34. Maintenance Shop heater vents
35. Maintenance Shop turbine ventilator
36. Maintenance Shop exhaust hood (1)
37. Maintenance Shop exhaust hood (2)
Page | 27
Appendix C Existing Building Drawings (for Contractor’s convenience)
Page | 28
Page | 29
Page | 30
Page | 31
Page | 32
Page | 33
Page | 34
Page | 35
Page | 36
Page | 37
Page | 38
Page | 39
Page | 40
GWCA 321981 4/02/2025
Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113
SECTION 073113
ASPHALT SHINGLES
PART 1 - GENERAL
1.1 SCOPE OF WORK
A. Project Location: George Washington Carver National Monument, 5646 Carver Road, Diamond
MO 64840.
B. Building(s) Name/Identifier: Visitor Center Building #21, and Maintenance Shop Building #22
1.2 SUMMARY
A. Section Includes:
1. Selective Demolition.
2. Glass-fiber-reinforced asphalt shingles.
3. Underlayment materials.
4. Vents and plumbing stack boots.
5. Sheet metal flashing and trim.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For the following:
1. Asphalt shingles.
2. Underlayment materials.
3. Ridge vents.
4. Asphalt roofing cement.
5. Elastomeric flashing sealant.
6. Vents and plumbing stack boots.
7. Sheet metal flashing and trim.
B. Sustainable Design Submittals:
Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113
1. Product Test Reports: For roof materials, documentation indicating that roof materials comply with Solar Reflectance Index requirements.
C. Shop Drawings: For sheet metal flashing and trim.
D. Samples: For each exposed product and for each color and blend specified.
1.5 INFORMATIONAL SUBMITTALS
A. Product test reports.
B. Research reports for synthetic underlayment.
C. Sample warranty.
1. Material warranty.
2. Roofing installer warranty.
1.6 SUBMITTAL COORDINATION
A. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of the submittal requirements and not a comprehensive list. The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.
1.7 CLOSEOUT SUBMITTALS
A. Maintenance data.
1.8 QUALITY ASSURANCE
A. Installer Qualifications: An authorized installer who is trained and approved by manufacturer.
1.9 WARRANTY
A. Materials Warranty: Manufacturer agrees to repair or replace asphalt shingles that fail within specified warranty period.
1. Materials Warranty Period: 30 years from date of Substantial Completion, prorated, with first 10 years nonprorated.
2. Wind-Speed Warranty Period: Asphalt shingles will resist blow-off or damage caused by wind speeds of up to 130 mph (58.1 m/s) for 15 years from date of Substantial Completion.
3. Algae-Resistance Warranty Period: Asphalt shingles will not discolor for 20 years from date of Substantial Completion.
B. Roofing Installer’s Warranty: Roofing installer to provide and sign a Roofing Installer’s Warranty in which Installer agrees to repair or replace components of asphalt-shingle roofing that fail in materials or workmanship within specified warranty period.
1. Warranty Period: Five years from date of Substantial Completion.
http://www.arcomnet.com/sustainable_design.aspx?topic=6
Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Exterior Fire-Test Exposure: Provide asphalt shingles and related roofing materials identical to those of assemblies tested for Class A fire resistance in accordance with American Society of Testing Materials (ASTM) E108 or UL 790 by Underwriters Laboratories or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify products with appropriate markings of applicable testing agency.
B. Wind Resistance: Provide asphalt shingles that comply with requirements of ASTM D7158/D7158M, Class H.
C. Shingles:
1. Mineral granular-surfaced asphalt shingles.
a. Self-sealing.
b. Square tab.
c. Fungus-resistant.
d. Impact resistant shingles, Class 4.
e. Type I, weighing not less than 290 pounds per 100 square feet.
2.2 GLASS-FIBER-REINFORCED ASPHALT SHINGLES
A. Laminated-Strip Asphalt Shingles: ASTM D3462/D3462M, laminated, multi-ply overlay construction; glass-fiber reinforced, mineral-granule surfaced, and self-sealing.
1. Basis of Design: Atlas Pinnacle Pristine High-Performance Shingles.
2. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Atlas Molded Products; a Division of Atlas Roofing Corporation.
b. CertainTeed Corporation.
c. GAF.
d. Owens Corning.
e. Tamko Building Products, Inc.
f. Other Approved Equals.
3. Strip Size: Manufacturer's standard approximately 42 inch.
4. Algae Resistance: Granules resist algae discoloration.
5. Impact Resistance: Underwriters Laboratory (UL) 2218, Class 4.
6. Fire Resistance: UL 790 for Class A.
7. Color and Blends: As selected by COR from manufacturer's full range.
B. Hip and Ridge Shingles: Manufacturer's standard units to match asphalt shingles.
2.3 UNDERLAYMENT MATERIALS
A. Synthetic Underlayment: UV-resistant polypropylene, polyolefin, or polyethylene polymer fabric with surface coatings or treatments to improve traction underfoot and abrasion resistance;
evaluated and documented to be suitable for use as a roof underlayment under applicable codes by a testing and inspecting agency acceptable to authorities having jurisdiction.
http://www.specagent.com/Lookup?ulid=4726 http://www.specagent.com/Lookup?uid=123457152155 http://www.specagent.com/Lookup?uid=123457152156 http://www.specagent.com/Lookup?uid=123457152154 http://www.specagent.com/Lookup?uid=123457152159 http://www.specagent.com/Lookup?uid=123457152161
Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113
1. Basis of design: RhinoRoof U20, as manufactured by InterWrap, Inc.
a. Product requirements include the following minimum characteristics listed below:
1) Permeability ASTM E96 - .05 perms.
2) Water Transmission ASTM D4869 – pass.
3) Tear Strength ASTM D4533 – MD 30 lbs (14 kg).
4) Tensile Strength ASTM D751 – MD 80 lbs (36 kg).
5) Bursts Strength ASTM D751 – 150 psi (1033 kPa)
6) Nominal Thickness ASTM D1777 – 6 mils (0.15 mm).
7) Width Per Roll – 36 inches.
2. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Atlas Roofing Corporation.
b. CertainTeed Saint-Gobain.
c. GAF.
d. Owens Corning.
e. Tamko Building Products, Inc.
f. Other Approved Equals.
B. Valleys, Eaves, Rake, and Roof/Wall Intersections: Install Self-Adhering, Polymer-Modified Bitumen Sheet: ASTM D1970/D1970M, minimum 55-mil- (1.4-mm-) thick sheet; glass-fiber-mat-reinforced, polymer-modified asphalt; with slip-resistant top surface and release backing; cold applied. Material to be supplied in 36 inch wide rolls. Provide primer for adjoining concrete, masonry, and metal surfaces to receive underlayment as recommended by the manufacturer.
Approved product includes but is not limited to the following:
1. Grace Ice & Water Shield; Grace Construction Products.
2. WinterGuard Waterproofing underlayment; CertainTeed.
3. RhinoRoof Granulated Self-Adhered underlayment.
4. Other Approved Equals.
2.4 VENTS
A. Rigid Ridge Vent: Manufacturer's standard, rigid-section, high-density, UV-stabilized plastic ridge vent for use under ridge shingles. Provide vents to match the size and net free area of the existing vents being replaced.
1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:
a. VenturiVent Plus, as manufactured by Air Vent Inc.
b. Certainteed Ridge Vent - 12".
c. Owens Corning VentSure.
d. Other Approved Manufacturers.
2. Minimum Net Free Area: 18 sq. in. per ft.
2.5 ACCESSORIES
A. Asphalt Roofing Cement: ASTM D4586/D4586M Type II, asbestos free.
http://www.specagent.com/Lookup?ulid=9296 http://www.specagent.com/Lookup?uid=123457152955 http://www.specagent.com/Lookup?uid=123457152918 http://www.specagent.com/Lookup?uid=123457152205 http://www.specagent.com/Lookup?uid=123457152207 http://www.specagent.com/Lookup?uid=123457152209
Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113
B. Roofing Nails: ASTM F1667, aluminum, stainless steel, copper, or hot-dip galvanized-steel wire shingle nails, minimum 0.120-inch- (3-mm-) diameter, sharp-pointed, with a 3/8- to 7/16-inch- (10- to 11-mm-) diameter flat head and of sufficient length to penetrate 3/4 inch (19 mm) into solid wood decking or extend at least 1/8 inch (3 mm) through sheathing less than 3/4 inch (19
mm) thick.
1. In areas where the underside of the roof decking is exposed, such as an exposed soffit or eave, or under the breezeway roof, the maximum nail length must not penetrate through the sheathing and be visible from the bottom side.
2. Where nails are in contact with metal flashing, use nails made from same metal as flashing.
C. Synthetic Underlayment Fasteners: As recommended in writing by synthetic-underlayment manufacturer for application indicated.
2.6 SELECTIVE DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Full Roof Tear-off: Removal of existing roofing system down to existing roof deck or structure.
2. Temporarily protect existing roofing system and components that are to remain as required from damage.
3. Existing roof drains and roof drainage shall be protected during each stage of reroofing, and roof-drain plugs shall be installed when demolition is taking place so that debris cannot be lost down the drains. Contractor shall remove all drain plugs when demolition is completed in the area affecting the drain.
4. Do not remove more roof than can be replace in a day, and the roof will be made watertight each night.
5. Remove debris and materials so as not to impose excessive loads on supporting roof, structure or framing.
6. Dispose of demolished items and materials promptly.
B. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Reinstall items in locations indicated, or in original locations as required. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
3. Lightning protection to be removed and reinstalled by a certified installer.
C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition.
D. Inspect deck after tear-off of roofing system.
1. If broken or loose fasteners that secure deck panels to one another or to structure are observed, or if deck appears or feels inadequately attached, immediately notify COR.
Div. 7 V. 2021-10-18 ASPHALT SHINGLES 073113
a. Do not proceed with installation until directed by COR.
2. If deck surface is unsuitable for receiving new roofing or if structural…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .