This Statement of Work (SOW) details a project for the U.S. Customs and Border Protection (CBP) at the Champlain Port of Entry to procure and install a failover server for their access control system. The primary objective is to provide a backup directory server that connects to the existing Access Control Server (ACS), ensuring uninterrupted operations in case of a catastrophic system failure. The contractor must install a Streamvault 2040E Series 6-Bay Multi-Purpose Appliance with specific hardware specifications, including a Xeon E-2436 processor, 32GB RAM, 480GB M.2 SSD, Windows Server 2022, and Genetec Security Center pre-installed.
The project requires the contractor to install the server in the cargo lobby's security room, perform comprehensive testing of access control points, validate door security, and ensure system integration with other security systems. Work will be conducted during normal business hours (7:30 AM - 4:00 PM, Monday through Friday), with potential for after-hours work requiring written approval. The contractor must provide a standard 5-year warranty covering hardware, software, programming, and installation services, and will be responsible for cleaning up the work area daily and removing all installation-related debris.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sole Source Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
Failover Server
Champlain Port of Entry (POE) 237 West Service Road Champlain, NY 12919
Statement of Work for CHM Failover Server PR 20151529
1. OBJECTIVE/PURPOSE
The purpose of this project is to provide another directory server that will connect to the existing onsite Access Control Server (ACS) at the Port of Champlain to ensure failover capability, preventing disruption to Port operations in the event of a catastrophic failure of the ACS. Server redundancy involves using an additional server to replicate the functions of the primary server, ensuring uninterrupted service and data availability during system failures, crashes or similar incidents.
2. SCOPE
The U.S. Customs and Border Protection (CBP) intends to procure and install a failover/directory server to connect to the current ACS at the Port of Champlain. The contractor shall:
1. Install and configure a reliable access control system that meets the security needs of the facility, including all necessary hardware, software, and programming.
2. Ensure seamless integration of the access control system with existing security infrastructure. This shall include any required upgrades necessary to the primary server
(hardware, operating system, or application software) to accommodate the installation of the backup server.
3. Provide training to personnel on the operation and management of the access control system.
4. Provide standard warranty on part and labor, covering hardware, software, and installation services
REQUIREMENTS:
The contractor shall provide and install one (1) directory server that meets the following requirements:
2.1 System Components:
• Control software and server hardware - Upgrade Synergis Base from Professional to
Enterprise; Streamvault - 2040E Series:
o 6-Bay Multi-Purpose Appliance
Statement of Work for CHM Failover Server PR 20151529 o Xeon E-2436 32GB RAM 2 o 480GB M.2 SSD o 1GBE RJ45 2x 600W PSU Windows Server 2022; Standard 5-year warranty o Genetec Security Center pre-installed
• Power supply and backup systems to ensure continuous operations
• All miscellaneous installation hardware and associated freight costs.
2.2 Site Assessment:
• The backup server will be installed in the security room in the cargo lobby at the Champlain Port of Entry.
• In the event of unforeseen circumstances, a field change order may be prepared and delivered to CBP for review, discussion and approval.
2.3 Compliance
• The installation complies with relevant local and national codes, regulations, and industry standards.
2.4 Installation Process
2.4.1. Customer and Contractor Responsibilities:
• Customer will provide 110VAC power requirements at all head-end and applicable field device locations.
• Customer is responsible for providing all required connectivity to their card access network that includes an open port on the local card access switch/router and IP addresses.
• Contractor is not responsible for any service outages connected to our system for example, power, phone lines and internet.
• Contractor will confirm site readiness, including necessary structural modifications, electrical work, and network setup.
• Contractor will verify that all access control equipment has been delivered and is in serviceable condition.
• Contractor shall install and configure access control software on the designated server.