This is a Performance Work Statement (PWS) for ramp striping services at U.S. Coast Guard Base Astoria in Warrenton, Oregon. The contractor must provide all personnel, equipment, tools, transportation, and supervision necessary to paint and stripe the aviation ramp (apron) to facilitate safe movement of helicopters and aviation support vehicles. Work must be completed within 120 days of contract award, performed Monday through Friday between 8:00 a.m. and 4:00 p.m., with a mandatory bid walk scheduled for February 4, 2026 at 9:00 a.m. The Contracting Officer's Representative is LT Gary Nelthropp, (503) 706-3150, Gary.C.Nelthropp@uscg.mil.
The contractor must furnish 100% acrylic polymer latex waterborne traffic paint with VOC content less than 100 grams per liter, meeting ASTM specifications for flexibility, abrasion resistance, and scrub resistance, applied at minimum 15 mils thickness. Paint colors required are yellow, red, blue, and white, with approximately 1,800 linear feet of 6-inch-wide striping per Figure 2 specifications. Reflective glass beads must match existing ramp striping. The contractor shall clean surfaces prior to application, apply paint during appropriate weather conditions per manufacturer requirements, and schedule work to paint only the east or west half of the ramp at a time to maintain operational continuity. All contractor employees require Real ID valid identification, a submitted roster with names, dates of birth, and license numbers, and must be licensed to conduct road striping work in accordance with Federal and State requirements. The contractor shall provide a minimum 1-year warranty on materials and workmanship. The government will furnish on-site parking and 120-volt electricity. Invoicing must be submitted through the Invoice Processing Platform (IPP) at https://www.ipp.gov/.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FP SVC R.pdf | ||
| Wage Rates Clatsop County.pdf | ||
| FP SVC A.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT – SCOPE OF WORK
U.S. COAST GUARD BASE ASTORIA RAMP STRIPING
SECTION 1 – GENERAL INFORMATION
1.1 Scope of Work
The contractor shall provide all personnel, equipment, tools, transportation, supervision and other items and services necessary to paint (stripe) Base Astoria’s aviation ramp, also known as an apron. The contractor must perform to the standards in this Scope of Work (SOW) contract. All questions regarding this Scope of Work for Services must be sent through the US Coast Guard Contracting Officer’s Representative (COR).
The COR is LT Gary Nelthropp, Phone, (503) 706-3150; Email: Gary.C.Nelthropp@uscg.mil
A bid walk will be offered on Wednesday 04FEB2026 at 0900 at the below listed address. No other bid walk will be offered.
1.1.1 Place of Performance
Coast Guard Base Astoria, Warrenton Campus 2185 SE 12th Place Warrenton, OR 97146
1.2 Contractor Personnel
1.2.1 Contract Manager
The contractor must provide a contract manager who must be responsible for the performance of the work.
1.2.1.1 The contract manager or alternate(s) must have full authority to act for the contractor on all contract matters relating to daily operation of this contract.
1.2.1.2 The contact manager and alternate or alternates must be able to read, write, speak, and understand the English language.
1.2.1.3 The contract manager’s firm must be licensed to conduct road striping work in accordance with Federal and State requirements.
1.2.2 Contractor employees
The contractor must not employ persons for work on this contract if such employee is considered by the contracting officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.
1.2.2.1 Contactor personnel must present a neat appearance and be easily recognized as contractor employees.
1.2.2.2 The contractor must not employ any person who is an employee of the U. S. Government if employing that person would create a conflict of interest. Additionally, the contractor must not employ any person who is an employee of the U. S. Coast Guard unless such person seeks and receives approval according to U. S. Coast Guard regulations.
1.2.3 Security requirements
Due to heightened Security at USCG Facilities, all contractor employees performing tasks related to this SOW, while onboard a Coast Guard facility, shall have proper valid identification, specifically a Real ID.
Time spent undergoing entrance to USCG facilities will not be considered a government delay of work or differing site condition. Prior to commencing work the contractor shall send a roster to the COR which includes the names of the contractor employees who will be onsite, their dates of birth, and their license number.
1.3 Hours of Operation – Projected Date of Completion
The contractor must perform the tasks as required by the SOW under this contract during the following hours: Monday through Friday between 08:00am and 4:00pm unless other time is specified. The contractor shall have all work completed within 120 days of award of contract.
1.3.1 Holidays: If applicable.
1.3.2 Special event, or adjusted work hours: If circumstances should arise wherein the contractor desires a different work schedule as required in section 1.3 above, the contractor must request the same in writing.
Submit written request to the Contracting Point of Contact (POC) a minimum of 24 hours before the requested adjusted work schedule. If the desired schedule change is to be effective on a Monday, the request must be submitted to the (POC) prior to 9:00am on the Friday prior to commencement of work.
1.4 Invoicing
In conjunction with the subject award, proper invoices will be submitted through the Invoice Processing Platform (IPP) at https://www.ipp.gov/. IPP is a secure web-based electronic invoicing system provided by the U.S. Department of the Treasury’s Bureau of the Fiscal Service in partnership with the Federal Reserve Bank of St. Louis (FRSTL). IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency.
Actions to take:
If you are already enrolled in IPP:
If your company is already registered to use IPP, you will not be required to re-register and you do not need to contact IPP.
If you are NOT already enrolled in IPP:
The point of contact you provided in your SAM.gov registration will receive two emails from ipp.noreply@mail.eroc.twai.gov. Please note that emails from this email address may filter into your spam or junk folder:
1. The first email will have the IPP Logon ID and a link to the IPP application.
2. A second email, which will be sent within 24 hours of the first email, contains a temporary password.
Once your contact receives these emails, please ensure they log into IPP and complete the registration process.
Once registered to use IPP, your company may submit invoices electronically, receive e-mail notifications when requests are paid, view payment history, and access remittance downloads. The e-mail notification of payment is sent when a payment is distributed to your bank account and may include the following payment information: Date of payment, dollar amount, invoice number, paying agency, payee name, and ACH trace number.
Vendor training materials, including a first time login tutorial, are available on the https://www.ipp.gov/ website. Once you have logged in to the IPP application, you will have access to user guides that provide step-by-step instructions for all IPP capabilities, ranging from creating and submitting an invoice to setting up email notifications. Live webinars are held monthly and provide a great opportunity to learn the basic of the system and to call in and ask the IPP team questions about the IPP application.
IPP Customer Support is available to assist users of the system and can answer your questions related to accessing IPP or completing the registration process.
Toll-free number: 866-973-3131 Email address: IPPCustomerSupport@fiscal.treasury.gov Hours of operation: Monday through Friday (excluding bank holidays) from 8:00 am - 6:00 pm ET
SECTION 2 – DEFINITIONS
2.1 General Definitions
When the (SOW), solicitation provision or contract clause uses a word or term that is defined in the Federal Acquisition Regulations (FAR), the word or term has the same meaning as the definition as contained in section 2.101 of the FAR. The FAR index is available via the Internet at http://www.acqnet.gov at the end of the FAR, after the FAR Appendix.
2.1.1 Defective Service: A service or commodity output that does not meet the standard of performance requirement specified in the contract for that service or commodity.
2.1.2 Quality Assurance: A planned and systematic pattern of all government actions necessary to provide confidence that adequate technical requirements are established; products and services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the government assurance functions for a contracted service.
2.1.2 Quality Control: Those actions taken by a contractor to control the production of outputs to ensure that they conform to the contract requirements.
2.1.3 Technical Definitions: Not applicable to contract.
SECTION 3 – GOVERNMENT FURNISHED PROPERTY AND SERVICES
3.1 General Information:
The Government must provide the facilities, equipment, materials, and services listed here:
3.1.1 On-site parking for contractor vehicles
3.1.2 120V Electricity necessary for use by contractor in conjunction with this contract
SECTION 4 – CONTRACTOR FURNISHED ITEMS AND SERVICES
Except for those items, services, or commodities specifically stated in section 3 as government furnished, the contractor must furnish everything needed to perform this contract according to all its terms.
SECTION 5 – SPECIFIC TASKS
The aviation apron ramp at Base Astoria was recently resurfaced and striped, however the end user determined that further striping is necessary to assist aircraft operations. This Scope of Work is to put down additional striping on the apron and road to facilitate safe movement of helicopters and aviation support vehicles.
5.1 Paint & Bead Selection
5.1.1 The contractor shall select and use paint that satisfies the following criterion. Paint shall be a 100% acrylic polymer latex waterborne traffic paint, have a VOC content of less than 100, pass the D522 flexibility test, pass the ASTM D4060 abrasion resistance test, pass the ASTM D4060 scrub resistance test, have a viscosity at 77 degrees Fahrenheit of 08 to 90, have a 60-63% weight percentage of pigment solids, can be applied up to 22 wet mils thick, and perform equally well on both asphalt and concrete.
5.1.2 The contractor have paints in the colors yellow, red, blue, and white.
5.1.3 The contractor shall select and use reflective glass beads to match the dimensions and type of beads used in the other striped portions of the aviation ramp.
5.2 Preparation Work
5.2.1 Prior to applying paint, the contractor shall clean the asphalt or concrete surface such that it is free of dust or debris, to increase the adhesion between paint and the surface.
5.3 Paint & Bead Application
5.3.1 The contractor shall stripe in accordance with Figure 2 below.
5.3.2 For bidding purposes, assume approximately 1800 linear feet of stripe, all stripe will be 6” wide unless Figure 2 denotes otherwise.
5.3.3 The contractor shall paint each line on to match the color in Figure 2. Numbers 1, 2, 3 and 4 shall be painted in yellow and the letters “HG” shall be painted in red.
5.3.4 The contractor shall apply all stripe to a minimum thickness of 15 mils.
5.3.5 Superimposed on the blue lines, the contractor shall paint in neat white letters are oriented to be read by oncoming traffic: US GOVERNMENT PROPERTY
5.3.6 Following the application of paint and in accordance with manufacturers’ instruction, the contractor shall apply reflective glass beads to the paint.
5.4.7 The contractor shall select a weather window that complies with the manufacturer requirements for paint and bead application, particularly with regards to temperature and moisture.
5.4 Licensing, Certifications, and Qualifications:
5.4.1 The contractor shall be certified and licensed to conduct the work described above.
5.4.2 Prior to commencing work, the contractor shall provide the COR with digital copies of their licenses & certification.
5.5 Interferences:
5.5.1 The contractor shall be responsible for any/all interferences that may be encountered while completing this SOW.
5.5.2 The contractor shall schedule their work such that they only paint one half (in an east/west division) of the aviation apron at a time to allow for continuous air station operations. Once the paint is dry on the half and aircraft can transit over the stripes, the contractor may proceed to paint the other half.
5.6 Safety:
All work shall be conducted in a safe manner and shall comply with all applicable Federal, State, and local safety standards and requirements. Base Astoria reserves the right to inspect for compliance with safety standards and requirements. The Contractor shall comply with all Federal, State, and local laws, including
OSHA.
5.7 Operations and Storage Facilities:
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the on-site representative with the concurrence of the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor’s performance.
5.8 Warranty
5.8.1 The contractor shall offer a minimum 1-year warranty on materials and workmanship.
SECTION 6 – ACCEPTANCE
6.1 Acceptance
6.1.1 Acceptance on behalf of the government will be made by the POC as attested to / witnessed by signatures on the contractor generated document / form per section 6.1. above.
SECTION 7 – APPLICABLE PUBLICATIONS AND FORMS
Publications and forms that apply to the (SOW) are listed below. The publications and forms have been designated as either mandatory or informational. The contractor is obligated to follow those publications and use those forms designated as mandatory to the extent specified in other sections of this (SOW). The contractor must be guided by those publications or use those forms designated as informational to the extent necessary to accomplish requirement in this (SOW).
7.1 Publications
7.1.1 OSHA Safety and Health Standards, 29 CFR Part 1926 – Safety and Health Regulations for Construction
7.1.2 Federal Specification 1952 Paint, Traffic, and Airfield Marking, Waterborne
SECTION 8 – DESIGN FIGURES
Figure 1: Existing Painting Configuration
Figure 2: Desired Painting Configuration, with specifics in the box highlighted in purple