This Statement of Work (SOW) outlines conservation requirements for metal fixtures and commemorative plaques at the San Juan National Historic Site in Puerto Rico. The work involves treating two World Heritage Site plaques, a National Register plaque, a 65th Infantry plaque, a political prisoners plaque, an Old San Juan plaque, four rails and two pins at Bastion del Carmen, and metal rails at the WWII Battery at La Princesa.
The work period is January 15, 2025 - January 15, 2026, with work to be performed Monday-Friday between 7:00am-4:00pm. Treatment requirements include cleaning surfaces, removing oxidized patina, applying corrosion inhibitors, epoxy resin as needed, protective coatings including clear urethane and Coraflon, and photographic documentation before/during/after treatment. A professional conservator must directly supervise all work. The contractor must provide their own transportation, though the park will provide site access. All work must comply with NPS policies, OSHA regulations, and professional conservation standards. The images show the current condition of the plaques and fixtures requiring treatment, including significant deterioration from environmental exposure.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Conservation of Metal Fixtures and Commemorative Plaques Statement of Work San Juan National Historic Site Page 1 of 9
STATEMENT OF WORK
Conservation of Metal Fixtures and Commemorative Plaques
San Juan National Historic Site
SCOPE: In accordance with the terms and conditions of the Contract, the Conservator shall perform the work of this Statement of Work for the National Park Service (NPS) as described herein.
The services shall include the treatment of two World Heritage Site designation commemorative plaques, a National Register of Historic Places designation commemorative plaque, a 65th Infantry commemorative plaque, a commemorative plaque honoring the political prisoners at El Morro, an Old San Juan plaque in Castillo San Cristóbal, four rails and two pins at Bastion del Carmen, and the metal rails at the World War II Battery at La Princesa. Treatment will include stabilization, rinsing, removal of concretions, application of inhibitor and finish coating.
CONFIDENTIALITY: The information developed under Statement of Work is the property of the U.S.
government and shall be kept in strict confidence. Proprietary or copyrighted material may not be included into the report document unless approved by the Contracting Officer.
PERFORMANCE PERIOD: The work performed under this Scope of Work shall be approximately from January 15, 2025 – January 15, 2026, in duration from the issuance of a notice to proceed.
Contractor must be able to start work within the next day upon receipt of the notice to proceed.
WORK SCHEDULE: Work shall be performed from Monday to Friday between 7:00 am - 4:00 pm.
GENERAL CONSIDERATIONS: Park housing is NOT available for this project. Transportation to and from the site will be the responsibility of the contractor. The park will provide access to the site.
I. PROJECT BACKGROUND
The objects that are to be treated through this project are located throughout the San Juan National Historic Site. The various commemorative plaques memorialize different historic events and important designations associated with the historic site. The rails and pins are important structural remnants of the artillery emplacements that once were common throughout the park but that, because of the harsh environmental conditions (salt air, high humidity, abrupt changes in temperature), wear and human action have made them almost disappear. The features that will be conserved through this project are the last of their kind in the fortifications.
II. STANDARDS
All conservation work produced under this Delivery Order shall be performed under the direct supervision of a professional conservator.
All conservation work performed shall be derived with the expectation of compliance with:
San Juan National Historic Site Page 2 of 9
• NPS law and policy, specifically the standards contained in Director’s Order 24: Museum Collections Management, Director’s Order 28: Cultural Resources Management, the Museum Handbook, and Reference Manual 28: Cultural Resource Management Guideline
• Occupational Safety and Health Administration (OSHA) laws, standards, and regulations.
• Generally accepted professional practice standards for conservation of museum items.
• Follow treatment prescribed in the Metal Objects Conditions Survey.
• Local codes only if required.
III. GENERAL DESCRIPTION OF WORK:
The work shall include, but not be limited to, the following components:
• Submit written treatment proposal.
• For the five commemorative plaques:
• Clean the surfaces
• Remove oxidized patina
• Apply corrosion inhibitor
• Apply coats of clear urethane as protective coating
• Photographic documentation before, during and after of treatment.
• For the rails and pins:
• Clean the metal surfaces and remove corrosion
• Apply epoxy resin as necessary
• Apply corrosion inhibitor
• Apply at least two coats of primer
• Apply at least two coats of Coraflon
• Photographic documentation before, during and after of treatment.
• For the Old San Juan plaque in Castillo San Cristóbal:
• Clean the whole surface with sand or glass blasting material and equipment until leaving the metal bare and without old and damaged patina.
• Apply new patina to the front of plaque surface only.
• Apply new patina, like original appearance as possible.
• Apply corrosion inhibitor to whole metal surface.
• Apply several coats of protective coating to the whole surface.
• Apply two coats of clear urethane with UV absorbers to prolong durability of this finish.
• Photo document before and after treatment.
IV. COMMUNICATIONS
A. COMMUNICATIONS: All communications and purchases for the work to be performed in accordance with this Statement of Work will be coordinated through the Contracting Officer Representative (COR). The contractor shall not contact, or request any supplies, equipment, vehicles, or materials from any NPS employee without express authorization from the COR. Written progress reports shall be submitted to the COR and Project Manager. Invoices shall be submitted to the COR as a
San Juan National Historic Site Page 3 of 9 separate document and shall record tasks, time allotted to them and a detailed account of what was accomplished (see Appendix A).
B. PROGRESS MEETINGS: Contractor shall meet with the COR and/or the Project Manager at least every two weeks. In these meetings, contractor shall expand on what was accomplished, what has not bee completed and what is the plan for the next two weeks.
V. DATA AND MATERIALS TO BE PROVIDED BY NPS
The items outlined herein will be provided (or have previously been provided) by the NPS for the use of the contractor, as required for the express purpose of completing the services required in this contract.
• The park will provide at least a staff member that will work at the project. The employee will be there to perform basic tasks associated to perform basic cleaning of objects. In particular situations (move and transportation of objects) the park may provide additional personnel.
VI. CONTRACTOR’S MINIMUM SAFETY REQUIREMENTS
A. GENERAL
• Plan for possible emergency situations, such as floods, cave-ins, slides, and windstorms. Such planning shall take into consideration the nature of the work done, site conditions, and degree of exposure of persons and property.
• Conduct daily safety meetings for all personnel. These meetings shall be used to review the effectiveness of the Contractor's safety effort, and to resolve current health and safety problems.
• First Aid: Have adequate training to ensure prompt and efficient first aid.
B. QUALIFICATIONS OF EMPLOYEES
• Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
• Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
• Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
C. PROTECTIVE EQUIPMENT
• Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
VII. PROJECT PERSONNEL
San Juan National Historic Site Page 4 of 9
A. GOVERNMENT REPRESENTATIVES
Unless otherwise designated, the Government representatives will be as follows:
1.Contract Specialist:
Provided upon award
2. NPS Project Contracting Officer Representative:
Provided upon award
B. CONTRACTOR REPRESENTATIVES:
1. The Contractor will submit a list of key personnel assigned to this project. The list should include a brief description of the roles and responsibilities for each key person.
2. The Contractor must request permission in writing from the Contracting Officer before substituting key project personnel.
3. The Contractor will transact contract matters solely with the Contracting Officer or her designated representative.
San Juan National Historic Site Page 5 of 9
Appendix A
San Juan National Historic Site Page 6 of 9
Commemorative Plaques and Fixtures in Need of Treatment
World Heritage Site Plaque, Castillo San Felipe del Morro
World Heritage Site Plaque, Castillo San Cristóbal
San Juan National Historic Site Page 7 of 9
Political Prisoners Plaque, Castillo San Felipe del Morro
National Register of Historic Places Plaque, Castillo San Cristóbal
San Juan National Historic Site Page 8 of 9
65th Infantry Plaque, esplanade, Castillo San Felipe del Morro
Railings, Del Carmen Battery, Castillo San Felipe del Morro
World War II Railings, La Princesa Battery, Outer Defenses, Castillo San Cristóbal
San Juan National Historic Site Page 9 of 9
Cannon Pivot Pin, Del Carmen Battery, Castillo San Felipe del Morro
Old San Juan Plaque, Castillo San Cristóbal