Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights

10.0 Section 508 – Electronic and Information Technology Standards Attachment.................................................................................. Error! Bookmark not defined.

Project Name

Grider Creek Campground Gravel Cap and CXT Removal

General Information

1.0 Scope of Work

Grider Creek Campground Gravel Cap and CXT Removal This solicitation is for contract work that includes tasks that shall be carefully coordinated and scheduled. The project consists of installing a 4-inch gravel cap comprised of aggregate surface course to 46N24X and Grider Creek Campround, roadway reconditioning, and CXT removal.

The exisiting CXT at Grider Creek Campground shall be removed and stored at Brown Bear River Access while the vault shall be decommissioned and backfilled in place.

1.1 Project Location

The project sites are located along Forest Service Road FS 45N24X, Grider Creek Campground, and Brown Bear River Access, within the Oak Knoll/Happy Camp Ranger District of the Klamath National Forest. Refer to project location maps below.

From Yreka, CA head north on N Main St. toward Lennox St for 0.3 miles. The continue for 8.1 on CA-263 N/N Main St to CA-96 W/ State Hwy 96. Contine on CA-96 for approximely 55 miles to turn left onto Walker Creek Rd. Continue for approximelty 3 miles to turn right onto Grider Rd to travel onto Grider Creek Rd. Continue for approximely 3 miles to arrive at project vicinity Forest Serivce Route 46N24X/ Grider Creek Campground.

From Yreka, CA head north on N Main St. toward Lennox St for 0.3 miles. The continue for 8.1 on CA-263 N/N Main St to CA-96 W/ State Hwy 96. Contine on CA-96 for approximely 10 miles then turn left to arrive at project vicinity Brown Bear River Access.

Diagram (above): Project location map for Grider Creek Campground

Grider Creek Campground

15 miles to Brown Bear River Access

Diagram (above): Project location map for Brown Bear River Access

2.0 Background

Grider Creek Campground sits just off the Pacific Crest Trail (PCT) and is heavily used by both PCT through hikers and the local community. The existing CXT is to be removed as it sits in the path of flood water during storm events with heavy precipitation that allow the creek to deviate from the established waterway. The gravel cap and roadway reconditioning are necessary project components to address geologic concerns at Grider Creek Campground, as well as to maintain the campground’s accessibility and visitor experience.

Contractor Requirements

3.0 Technical Requirements / Tasks

FAR 52.236-4 Physical Data (APR 1984)

N/A

Storage And Stockpiling Of Materials

Brown Bear River Access

23 miles to Yreka, CA

Campground loops and suitable areas adjacent to the site may be utilized for temporary stockpiling of materials as approved by the CO.

Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

The Contractor shall also minimize erosion of soil during construction, storage, and stockpiling.

Pollutants such as fuels, lubricants, bitumen’s, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

A. Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

B. Project specific Best Management Practices (BMPs) such as, FSH 7709.56, 77709.57, FSM 7709.59, FSM 7720, FSM 7722, FSM 7732 are required.

The contractor shall use the locations indicated by CO for temporary storage and stockpiling of materials. Any additional sites needed for storage and stockpiling are required to be approved prior to use.

Local Disposal Sites

The Contractor shall not dispose of material at storage and stockpiling sites mentioned above.

All construction debris and material remain property of the Contractor and shall be properly disposed of off National Forest Land.

Industrial Camps

N/A

Prosecution Of Work – Work Hour Limits – Work Item Limits Construction activity may be performed Monday through Friday and shall be limited to the hours between 7:00 a.m. and 6:00 p.m., unless other hours are approved in writing by the COR. No work will be allowed on Federal Holidays unless approved by CO in writing. All ground disturbing construction activity shall be performed during the period between July 15, 2022 and September 30, 2022 inclusive.

All in-stream work in live streams shall be limited to the period July 15, 2022 and September 15, 2022 inclusive.

Unusual Hazardous Conditions

The following conditions have been identified as inherently hazardous to a degree that failure to take the proper precautions could lead to serious injury or loss of life. This listing shall not be construed as all inclusive. The Contractor shall provide a written job-specific hazard analysis and safety plan that addresses and conforms to the requirements of 29 CFR 1910 and 1926 and the clause entitled Accident Prevention (FAR 52.236-13) included herein. Appropriate actions shall be taken by the Contractor to implement this plan during performance and to take any and all other necessary steps to mitigate the dangers from hazards.

• Burned Area

Water Source Sites

N/A

Landscape Preservation

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall always conduct the work in compliance with the following requirements.

A. The Contractor shall confine operations to within clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the clearing limits shall repaired as directed by the Contracting Officer.

B. Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems and impoundments (lakes, reservoirs, etc.)

C. Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

D. Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

E. Prevention of Oil Spills – If the Contractor maintains storage facilities for oil or oil products on project Area, appropriate preventive measures shall be taken to ensure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual States.

F. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Road Maintenance

The Contractor(s) shall perform road maintenance work in accordance with the following:

A. The Contractor shall avoid permanent fouling of gravel or bituminous with earth or debris from side ditches, slides, or other sources.

B. The Contractor shall avoid blading surface material off roads.

C. The Contractor shall minimize damage to ditches, slopes, and road surfaces. Where damage does occur, the Contractor shall restore the road to a condition agreed to by the Contracting Officer within a reasonable timeframe.

D. The Contractor shall remove all excess materials and debris from roadways, trails, and campground loops immediately after backfilling has been completed. This may require brooming and/or hosing down with water.

E. Upon completion and acceptance of work requirements, including acceptance of road maintenance by the Forest Service, the Contractor’s road maintenance responsibilities shall terminate.

Final Cleanup

Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

Traffic Control

The Contractor shall provide a traffic control plan which accommodates traffic according to the Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD), the FHWA Standard Specification FP-14 sections (156 and 635), and relevant Forest Service Supplemental Specifications. The Contractor shall perform work in a manner that ensures safety and convenience to the public. The contractor shall have at least one lane of traffic open during road improvement work and maintain this lane in a condition that will adequately accommodate traffic. Delays may not exceed 15 minutes at any one time followed by an open period of no less than 60 minutes. The road may be closed for no more than 60 minutes. The traffic control plan shall accommodate public traffic on roads adjacent to and within the project until project completion.

The Contractor shall provide, erect, disassemble, remove, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, pilot cars, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public.

Suitable warning signs and flaggers shall be provided to properly control and direct traffic.

A. Flaggers shall be certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Flaggers shall perform the work described under MUTCD Part 6 and use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Flaggers shall not be permitted the use of flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02. Flaggers shall be provided uninterrupted two-way communications between flaggers and between flaggers and pilot cars unless flaggers are able to see each other and communicate.

The use of communications devices shall be approved by the CO.

B. The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points, where the project crosses or coincides with an existing road or trail.

The contractor shall notify the public of potential delays or closures caused by construction and changes in traffic control configuration a minimum of 15 days prior to the delays or closures. The traffic control plan must detail the contractor’s procedure to notify emergency services, Klamath National Forest, and Happy Camp Ranger District listed below, of on-going construction activities and when delays of more than 15 minutes are anticipated.

Emergency Services include:

• Klamath National Forest: (530)-841-4588

• Happy Camp Ranger District: (530)-493-2243

The traffic control plan shall be prepared as an electronic flier and approved by the CO prior to the contractor instituting any traffic delays or closures.

3.1 Applicable Specifications

[X] FHWA Standard Specification 2014 applies [_] FHWA Standard Specification 2014 Metric applies

The attached “List of Specifications” and “Supplemental Specifications” apply. All specifications not included in the specification listing, but referenced by listed specifications, are applicable.

# DESCRIPTION DATE

101 TERMS, FORMAT, AND DEFINITIONS 2014

102 BID, AWARD, AND EXECUTION OF CONTRACT 2014

103 SCOPE OF WORK 2014

104 CONTROL OF WORK 2014

105 CONTROL OF MATERIAL 2014

106 ACCEPTANCE OF WORK 2014

107 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC 2014

108 PROSECUTION AND PROGRESS 2014

109 MEASUREMENT AND PAYMENT 2014

151 MOBILIZATION 2014

153 CONTRACTOR QUALITY CONTROL 2014

154 CONTRACTOR SAMPLING AND TESTING 2014

155 CONSTRUCTION SCHEDULE 2014

156 PUBLIC TRAFFIC 2014

157 SOIL EROSION AND SEDIMENT CONTROL 2014

203 REMOVAL OF STRUCTURES AND OBSTRUCTIONS 2014

204 EXCAVATION AND EMBANKMENT 2014

209 STRUCTURE EXCAVATION AND BACKFILL 2014

301 UNTREATED AGGREGATE COURSES 2014

303 ROAD RECONDITIONING 2014

635 TEMPORARY TRAFFIC CONTROL 2014

637 FACILITIES AND SERVICES 2014

703 AGGREGATE 2014

718 TRAFFIC SIGNING AND MARKING MATERIAL 2014

3.2 Product Samples and/or Submittals

Title

Referenced by Contract clause or Specification No.

Time of Government Approval After Submittal

Hazardous Spill Plan 107.10 15 working days Fire Plan Fire Protection and

Suppression 15 working days

Construction Schedule/ Plan of Operation

FAR 52.236-15 15 working days

Traffic Control Plan 156 & 635 15 working days Job Hazard Analysis / Safety Plan FAR 52.236-13 15 working days

3.3 Material Certifications and Testing Reports

The following material certifications and testing reports are required:

Referenced by Contract clause or Specification No.

Time of Government Approval After Submittal

Aggregate Surface Course FP-14 301, 703 15 days

4.0 Government Furnished

None

4.0 Deliverables / Schedule

Referenced by Contract clause or Specification No.

Time of Government Approval After Submittal

Hazardous Spill Plan 107.10 15 Days Fire Plan Fire Protection and

Suppression 15 Days

Construction Schedule/ Plan of Operation

FAR 52.236-15 15 Days

Traffic Control Plan 156 & 635 15 Days Job Hazard Analysis / Safety Plan FAR 52.236-13 15 Days Erosion Control Permits 157.04 15 Days

6.0 Travel

7.0 Contractor’s Key Personnel

Equipment Operator – Successful performance of this contract will require a skilled equipment operator(s). Please provide any experience which correlates to the SOW requirements, education, and past performance on similar projects to support key personnel qualifications.

Contractor Representative - Successful performance of this contract will require an experienced Contractor Representative to be on site during working hours. Please provide any experience which correlates to the SOW requirements, education, and past performance on similar projects to support key personnel qualifications.

8.0 Security Requirements

All work is performed on a federal installation. Contractor shall comply with all federal laws and regulations.

9.0 Data Rights

None

10.0 Section 508 – Electronic and Information Technology Standards

Project Name
General Information
1.0 Scope of Work
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
Traffic Control
3.1 Applicable Specifications
4.0 Government Furnished
4.0 Deliverables / Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements
9.0 Data Rights