NFG NASEB Fence & Roof Replacement 2021
Summary of Work 1
STATEMENT OF WORK (SOW)
Project Name: Camp Pendleton
Facility: NFG NASEB JCN: 18067791
Location: Camp Pendleton, CA (33.287374, -117.330691)
Author: Veronica Corona
Date Prepared: April 1st, 2021
Summary of Work 2
SUMMARY OF WORK
1.0 GENERAL
1.1 SCOPE
The site is located at 33.287374, -117.330691 is near Camp Pendleton Air
Terminal. NFG NASEB is located near Camp Pendleton Air Terminal.
Contractor shall furnish all labor, product, equipment, materials, and supervision for the removal and installation associated with the Fence Replacement at Camp
Pendleton North, California NFG NASEB facility.
“Removal” includes but is not limited to removing and disposing of the existing chain-link fence.
“Installation” includes but is not limited to providing and installing a new chain link fence with 3 barbed wire on to, new drive-in gate, and grounding. All work shall conform to the latest or current requirements of OSHA General Industry
Safety and Health Standards as well as the FAA’s Facility Security requirements for fencing, and FAA-STD-19F. All materials used will need to meet the requirements as listed in the “Applicable Publications” section of the document.
Also, the roof is a flat surface 61 feet in length by 26 feet in width which needs to be replaced, it has been badly weathered. It can get replaced with an Asphalt or
TPO Singe-membrane roofing system with 25 year warranty and integral 4 to 6 inch metal drip-edge fascia all around.
The length of the fence perimeter is 650 feet, the height of the fence is 8 feet topped with 3 feet of barbed wire. The following items are a summary of the project and are provided solely for the purpose of describing the general nature of the work. Contractor is responsible for accomplishing all items of work identified in the applicable drawings, specifications, and provisions of the contract.
A. General
1. A utility locater must be conducted to identify all of the potential utilities in the vicinity of the NASEB and fence line to avoid any possible impacts during construction. Will have DIG Alert identify where they are.
2. Contractor shall comply with all applicable federal requirements for protecting the safety of their employees and the environment. In particular, all applicable standards of the Occupational Safety and Health Administration (OSHA) shall be followed.
3. The existing fence surrounds the facility, approximately 8 feet in height.
4. Construction material shall be stored only in SSC approved areas.
5. Construction staging shall be allowed only in the SSC approved areas.
6. There are no bathroom facilities on site. Contractor will have a portable restroom for the crew.
Summary of Work 3
7. Contractor shall clean up and restore the site grounds to its original condition after the work has been performed.
8. Contractor will need to submit project schedule prior to commencement of work.
9. There is no water on site, portable water tank will be needed.
B. Submit product data for project material to Contracting Officer for approval.
1. Submit Operation and Maintenance literature for project material to the Contracting
Officer for approval. Information must include any required maintenance for system operation and listing and source of replacement parts for system. Provide a hard copy of the Operation and Maintenance literature to maintain on site.
2. Submit any manufacturer's warranty information, final system testing certificate and project as built information after completion of the project. In addition, provide three hard copies of the warranty to maintain on site.
3. The Contractor must submit digital copies of all submittals for approval; submittals will be returned to the contractor after FAA action. The Contractor must provide the following information on all submittals:
a. Date
b. Watermark
c. Name of project and facility (full name)
d. Name of Contractor or Subcontractor
e. Contractor's approval on the submittal, signed and dated.
4. The FAA must have one working days to review and respond to the contractor submittals, unless stated otherwise by the FAA. Any delay as a result of submittal disapproval and required re-submittal must not be grounds for any contract adjustment. Receive submittal approvals prior to starting the work. All materials installed in the work must match the approved submittals. After a submittal has been approved, no substitutions will be permitted without written approval by the CO and the COR.
B. Funding Amount
Item Cost
Materials, Labor, Equipment for chain-link fence with barbed wire and grounding
Asphalt Gravel Roof Material and Labor
Contingency (%)
Total