This document is a Statement of Work (SOW) for the Leeds Creek #1 and Castle Creek Bridge Reconstruction project. The SOW outlines the required work, which includes removing and disposing of existing bridges and culverts, relocating utilities, installing footings, riprap, and precast/prefabricated superstructures, as well as constructing roadway approaches and installing wear surfaces and object markers.

The project locations are provided, along with site information and limitations, such as no available utilities on-site and the need for the contractor to take precautions for public and worker safety. The SOW also specifies that the work is anticipated to start on September 1, 2024, and be completed by July 31, 2025. The technical and forest contact information is provided for the project.

The related federal contract opportunity is Solicitation Number 1240LT24R0029, issued by the Department of Agriculture Forest Service, for the Leeds Creek #1 and Castle Creek Bridge Reconstruction project, which aligns with the details provided in the SOW.

Text of this file

Leeds Creek #1 and Castle Creek Bridge Reconstruction

Statement of Work

1. PROJECT DESCRIPTION

The Contractor shall submit a proce and technical proposal to:

Leeds Creek #1
Remove and dispose of existing bridge and wingwalls.
Relocate existing utilities

Install footings Install class 6 riprap with geotextile and reconstruct channel to tie into existing banks.

Install precast superstructure.

Construct roadway approaches and install wear surface.

Install type 3 object marker.

Castle Creek
Remove and dispose of existing culverts.
Install precast grade beams.

Install class 6 riprap with geotextile and reconstruct channel to tie into existing banks.

Install prefabricated steel superstructure.

Construct roadway approaches and install wear surface.

Install type 3 object marker.

2. PROJECT LOCATIONS

Leeds Creek #1
Latitude: 37.259616° and Longitude: -113.369380°
Castle Creek
Latitude: 37.681743° and Longitude: -112.763017°.

3. SITE INFORMATION AND LIMITATIONS

No utilities are available on-site for contractor’s use.

In conjunction with applicable sections of the Occupational Safety and Health Act (OSHA) the Contractor shall take such precautions as are necessary for the protection of the public, government personnel, and all personnel working under this contract. No work that endangers, interferes, or conflicts with access to work sites shall be performed until a plan for satisfactory warning and handling of use has been submitted by the Contractor and approved by the COR. Contractor shall not be paid directly for this item, rather it will be considered incidental to lump sum project payment.

4. WORK CAMPS, STAGING AND STORAGE AREAS

Areas for staging operations and storage of materials shall be approved by the Contracting Officer (CO).

5. INSPECTION OF WORKSITE

The Contractor acknowledges that s/he has taken the necessary steps to ascertain the nature and location of task, and has investigated and satisfied her/himself as to the general and local conditions which can affect the task or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the task, or for proceeding to successfully perform the task without additional expenses to the Government.

6. QUALITY CONTROL

The Contractor shall provide and maintain a quality control system that will ensure all services and supplies required under this contract conforms to the contract and manufacturer requirements. The Contractor shall perform, or cause to be performed, the inspection required to substantiate that all services, and supplies conform to the contract requirements.

8. CONTRACT TIME

Work is anticipated to start September 1, 2024, and be completed by July 31, 2025

9. TECHNICAL / FOREST CONTACT

Jake Dodds jake.dodds@usda.gov 435-865-3754

Other files

File Type Posted
Leeds Creek 1 Design Question.docx DOCX document
CASTLE CREEK FSSS.docx DOCX document
Washington County WD.pdf PDF
Leeds Creek 1 Bridge FSSS.docx DOCX document
G-092 CASTLE CREEK BRIDGE FINAL 2_26_2024 SIGNED.pdf PDF
Iron County WD.pdf PDF
solicitation mod 1.pdf PDF
1240LT24R0029.pdf PDF
G-091 LEEDS CREEK 1 BRIDGE FINAL 2_26_2024 SIGNED.pdf PDF
Leeds Creek 1 SOI.pdf PDF
Castle Creek SOI.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .